REPAIR
MAIN CODE: 5663 LOCATION: B 2 DATE:
STEP 1
MANPOWER USE : 24 HOPPER 10
SOLID STAR
21-Apr-13
ENG'R./SUPERVISOR IN CHARGED: BRYAN ACURANTEZ NO. OF DAYS IN BLASTING PER SESSION NO. OF DAYS
1
NO. OF GUNS 3 3
DATE & TIME STARTED DATE 04/21/13 04/22/13 TIME 200 200
DATE & TIME FINISHED TIME 700 700 DATE 04/21/13 04/22/13
HOURS
CONSUME
FORMULA ( A )
24 HOPPER FORMULA ( B )
hrs. consumed X no. of guns = ______hrs-gun 1.5 hrs. X no. of guns = _______hrs-gun
hrs - gun 3 x 5 = 15 3 x 5 = 15
1.5 x 3 = 4.5 1.5 x 3 = 4.5
10
6
1.) REST TIME 2.) REFUELING = =
30 1 hr
30 min
21
SUMMARY :
NO. OF DAYS BLASTING 1 DAY 2 DAY 3 DAY 4 DAY 5 DAY 6 DAY 7 DAY TOTAL : 21
REMARKS
3 gun = 3 men + 1 pottender + 1 operator = 5 MH 3 gun = 3 men + 1 pottender + 1 operator = 5 MH
THE TOTAL WORKING HRS. ARE TO BE DEDUCTED TO THE CONSTANT LOSSED TIME
FOR ( s.a 1.0 ) FACTOR OF LOSS TIME = 2.21 HRS ( CONSTANT ) WHERE : > FACTORS OF LOSS TIME * FILLING OF GRITS TO POT ( 10 MIN) * TRANSFERRING OF HOPPER ( 10 MIN) * TRANSFERRING OF POSITION OF BLASTER ( 1 MIN.) * REFRESHING ( 2 HRS. ) TO COMPUTE THE TOTAL TIME
TOTAL WORKING HRS.
STEP 2
FOR ( s.a 2.0 ) FACTOR OF LOSS TIME = 2.21 HRS ( CONSTANT ) WHERE : > FACTORS OF LOSS TIME * FILLING OF GRITS TO POT ( 10 MIN ) TOTAL OF 2.21 HRS * TRANSFERRING OF HOPPER (10 MIN) * TRANSFERING OF POSITION OF BLASTER ( 1 MIN ) * REFRESHING ( 2 HRS. ) TO COMPUTE THE TOTAL TIME
TOTAL WORKING HRS.
EX: ______
EX:
x _____
__21__
"COMPUTATION"
FOR ( s.a 2. 0 )
STEP 3
AB
>
m/M-H-gun
______5.48_____m/M-H-gun
COMPUTATION :
5.48
B
COMPUTATION :
T
6240 1030
note : For ( s.a 2.0 ) deduction of 10 % constant due to remaining of grits per hopper
TGC =
TGU
BLASTED AREA ( s.a 2.0 )
>
6.06
kg/m