Daily Proposed Work Plan & Actual Execution

Name of the Site/Structure .


Name of the Construction Company / Contractor ....................

Item

Name
Component

(i) Excavation ............ a)

Qty. in M3/M2 / M
L
B/D
H/T

Total Qty.
Planned /
proposed

Executed

b)
c)
(ii) P.C.C .a)
b)
c)
(iii) Bar cutting /
Bending / fixing .

a)
b)
c)

(iv) Shuttering a)
b)
c)
(v) Dewatering / Plastering
Painting / Blasting /
a)
Other Miscellaneous Works b)
c)
Specification / Details .

A) Type of Manpower Engaged

No.
i)
ii)
iii)
iv)
v)

Supervisor/ Technician ------Mason / Mistry ---------------Skilled Labour ---------------Semi-skilled Labour --------Un-skilled ---------------------

B) Curing done --- Yes / No


C) Daily Existing Stock Verification

Item
a) Cement (Bags No.) ---------b) Sand (Cum) .
c) Chips (Cum)
40 MM ----------------20 MM -----------------10 MM -----------------d) Steel (Size in MT)
i)
ii) ..
iii)
iv) ..
e) Const. Chemical / Other material

Signature of
Supervisor

Site Engineer

Site I/C

V.P