You are on page 1of 4

STREET LIGHT CLASSIFICATIONS WITHIN ILORIN

METROPOLIS
CLASS A ROADS
S/NO

ROAD DESCRIPTION
Offa garage road[Asa Dam road round
about to
Ola-olu]

Murtala Mohammed road[Ola-olu to


Kulende]

Ahmadu Bello Avenue

Umaru Audi Road

Fate Road

Abdul Azeez Attah Road[Geri-Alimi


R/About to Isale oja]

Ibrahim Taiwo Road

Asa Dam Road[Geri Alimi R/About to


Dangote]

REMARKS
The sum of N29,265,348.00
has been proposed for the
street light
Construction by contract
awaiting approval[new
construction]
From Ola-olu to Challenge is
presently on solar
powered.The sum of
N9,359,775.00 has been
proposed by direct labour
for conversion from solar to
conventional type.
Very functional.presently
being maintained by the
Min. of Energy
Currently being
rehabilitated by Devtech
power Nig. Ltd
Currently being
rehabilitated by Devtech
power Nig. Ltd
Presently on solar
powered.The sum of
N16,986,275.00 has been
proposed by direct labour
for conversion from solar to
conventional type.
Currently being
rehabilitated by Devtech
power Nig. Ltd
Presently on solar
powered.The sum of N19,
813,431.75 has been
proposed by contract for
conversion from solar to

conventional type.

1.

CLASS B ROADS

S/NO
1.

ROAD DESCRIPTION
New Yidi Road[Wahab Folawiyo Rd.jnct
to Asa Dam jnct.]

Wahab Folawiyo Road

University of Ilorin permanent site Road

Emir Road

Balogun Fulani Road

6.

Micheal Ibru Road[Maraba jnct to Emir


palace]

Kaiama Road[Idi ape to FGC]

8.

Admiralty Drive way,GRA,Ilorin

REMARKS
Presently on solar
powered.The sum of
N13,671,575.00 has been
proposed by direct labour
for conversion fromsolar to
conventional type.
Very functional.presently
being maintained by the
Min. of Energy
The sum of N65,000,000.00
has been proposed for the
street light
Construction by contract
awaiting approval[new
construction]
Currently being
rehabilitated by Devtech
power Nig. Ltd
Currently being
rehabilitated by Devtech
power Nig. Ltd
Currently being
rehabilitated by Devtech
power Nig. Ltd
The sum N12,009,450.00
was proposed for the
rehabilitation of the existing
street light installation by
Direct labour .Awaiting
approval
Abandoned during late
Lawal regime.Appropriate

9.

Kano Road,Adewole Housing


Estate,Ilorin

10.

Lagos Road,Adewole Housing


Estate,Ilorin

recommendation has been


made for the completion of
the project by Contract.
Abandoned during late
Lawal regime.Appropriate
recommendation has been
made for the completion of
the project by Contract.
Abandoned during late
Lawal regime.Appropriate
recommendation has been
made for the completion of
the project by Contract.

2.

CLASS C ROADS
S/NO
1.

ROAD DESCRIPTION
Offa Road

2.

Pakata Road

3.

Ita Amodu Road

4.

Ipaye Road

5.

Iloffa Road

6.

Olorunsogo Road[part]

7.

Mohammed Abdullahi
Road,Tanke,Ilorin

REMARKS
Currently being
rehabilitated by Devtech
power Nig. Ltd
Currently being
rehabilitated by Devtech
power Nig. Ltd
Currently being
rehabilitated by Devtech
power Nig. Ltd
Very functional.presently
being maintained by the
Min. of Energy
Very functional.presently
being maintained by the
Min. of Energy
Very functional.presently
being maintained by the
Min. of Energy
Abandoned during late
Lawal regime.Appropriate

Baba Daodu Road,Tanke area,Ilorin

3.

recommendation has been


made for the completion of
the project by Contract.
Abandoned during late
Lawal regime.Appropriate
recommendation has been
made for the completion of
the project by Contract.