Fresh Concrete Properties: Workability Requirements
Fresh Concrete Properties: Workability Requirements
Workability Requirements
In general, concrete tends to lose its workability at a faster rate when the slump measurement reaches the threshold value of 100mm, unless some special technology is used.
Type of Structure Method of Placing Speed of Placing Method and Speed of Compaction Manpower available to handle the concrete
WORKABILITY (SLUMP) SHALL BE SITE & STRUCTURE SPECIFIC Example: With Direct dumping from Truck or faster pumping for structures like flooring, big footing, raft foundation etc slump of 100 +/- 25 mm is sufficient
For structures with narrow width and or higher % of re-bars and where slow rate of placing, compaction is to be adopted like in the case of Columns, Plinth Beams, thin Walls, etc - slump of 150+/-25 mm is required
The mix shall be cohesive and uniform for any given workability, lower or higher.
Since the usage of admixture decides the workability and workability retention and not water, higher workability can be achieved without increasing water to cement ratio. Hence strength and durability of the structures can get enhanced even at higher workability.
Slump @ Site
Footing & Raft & Flooring 100+/-25 mm Slab & Pile caps Column & Wall Piles & Diaphragm walls Critical Structures 125+/-25 mm 150+/-25 mm 200+/-25 mm or 500 to 600 mm (flow table measure) SCC Flow of 550 to 850 mm
50mm
100mm
140mm
180mm