0% found this document useful (0 votes)
112 views7 pages

Creating Dependencies in The Task

The document discusses the four types of dependencies that can be created in project scheduling: finish-to-start (task B cannot begin until task A finishes), start-to-start (task B cannot begin until task A starts), finish-to-finish (task B cannot finish until task A finishes), and start-to-finish (task B cannot finish until task A starts). It notes that finish-to-start is the default dependency type in Gantt charts and lists the four types as options that can be selected in Gantt chart views.

Uploaded by

Ashu Kalra
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
112 views7 pages

Creating Dependencies in The Task

The document discusses the four types of dependencies that can be created in project scheduling: finish-to-start (task B cannot begin until task A finishes), start-to-start (task B cannot begin until task A starts), finish-to-finish (task B cannot finish until task A finishes), and start-to-finish (task B cannot finish until task A starts). It notes that finish-to-start is the default dependency type in Gantt charts and lists the four types as options that can be selected in Gantt chart views.

Uploaded by

Ashu Kalra
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd

Creating Dependencies in the task 1.

Finish-to-start (FS): The dependent task (B) cannot begin until the task that it depends on (A) is complete.

2. Start-to-start (SS): The dependent task (B) cannot begin until the task that it depends on (A) begins.

. Finish-to-!inish (FF): The dependent task (B) cannot be completed until the task that it depends on (A) is completed.

". Start-to-!inish (SF): The dependent task (B) cannot be completed until the task that it depends on (A) begins.

Dependencies in Gantt Chart 1. Finish-to-start (FS) (#e!ault)

2. Start-to-start (SS):

. Finish-to-!inish (FF):

". Start-to-!inish (SF):

GANTT CHART VIEW