Professional Documents
Culture Documents
Network Scheduling
Network Scheduling
Define Activities
Sequence activities
Estimate time and
Develop schedule
Project Scheduling Techniques
Gantt chart- This is represented by the graph or bar chart with a specific
bar for activities in the project that shows the passage of time. Gantt
chart limits a clear indication of interrelation between the activities.
CPM- Critical path method was developed for industrial projects where
activity times are generally known.
PERT- Program evaluation and review technique were developed for
R&D projects where activity times are generally uncertain. Its prime
objective is taking the shortest possible time.
Microsoft projects- All the work is performed on the computer memory
and changes can be saved only when the program is asked to operate.
Constructing a Network Diagram
Things to know before we construct
4 types of logical relationships between two dependent
activities/milestones.
FS Relationship – Start Event of a Successor
is dependent Finish event of Predecessor.
SS Relationship – Start Event of a Successor
is dependent Start event of Predecessor.
FF Relationship – Finish Event of a Successor
is dependent Finish event of Predecessor.
SF Relationship – Finish Event of a Successor
is dependent Start event of Predecessor
Finish to Start is a Logical Relationship in which a Successor Activity cannot start until a
Predecessor Activity has finished.
Consider 2 activities A and B. Let us
also consider A to be the predecessor
and B to be the successor.
A – document requirements, b – get
approval
A – design machine, B – develop
prototype
A – write user manual, B – print user
manual
Start to Start is a Logical Relationship in which a Successor
Activity cannot start until a Predecessor Activity has started.
The "from" activity must start before the
"to" activity can start.
on a telemarketing project the compilation of
phone lists must be started before people can
actually be called.
Rule 2 :
No two activities can be recognized by the same
end events
Rule 3 :
To assure the correct precedence relationship in
the arrow diagram, various questions must be
tested every time any activity is added to the
network
What activity must be finished immediately
before this activity can start?
What activities must occur at the same time
with this activity?
What activities must follow this activity?
Common Errors in Drawing Networks
1.Dangling
2. Looping or Cycling
3.Redundancy