The document discusses construction project schedules and timelines. It explains that construction schedules define the timeline and execution of tasks for a project. Schedules include all parts and general works of the project, planned start and finish times, and critical paths. Gantt charts can be used to visualize schedules, accounting for task durations and dependencies between tasks. Dependencies consider whether a task must finish before another can start or finish. Well-planned schedules are important for coordinating construction work.
The document discusses construction project schedules and timelines. It explains that construction schedules define the timeline and execution of tasks for a project. Schedules include all parts and general works of the project, planned start and finish times, and critical paths. Gantt charts can be used to visualize schedules, accounting for task durations and dependencies between tasks. Dependencies consider whether a task must finish before another can start or finish. Well-planned schedules are important for coordinating construction work.
The document discusses construction project schedules and timelines. It explains that construction schedules define the timeline and execution of tasks for a project. Schedules include all parts and general works of the project, planned start and finish times, and critical paths. Gantt charts can be used to visualize schedules, accounting for task durations and dependencies between tasks. Dependencies consider whether a task must finish before another can start or finish. Well-planned schedules are important for coordinating construction work.
VACIAR! ¿CÓMO QUE RECIÉN VAS A IR A COMPRAR EL CEMENTO? SITUACIÓN:
TU CARA CUANDO TE DAS CUENTA QUE
TU CALENDARIO DE OBRA CONTEMPLA DESENCOFRAR LOSAS AL DÍA SIGUIENTE DEL VACIADO LOS CRONOGRAMAS DE OBRA
INSTRUMENTO PARA ESTABLECER EL TODAS LAS PARTES Y PARTIDAS
CALENDARIO Y EL PLAZO DE EJECUCIÓN GENERALES DE LA OBRA DE OBRA DE UN PROYECTO TIEMPOS PREVISTOS DE INICIO Y FINAL DEFINE EL CALENDARIO DE EJECUCIÓN DE TAREAS Y LAS PARTES QUE LO COMPONEN. LA RUTA CRÍTICA
HITOS O PUNTOS DE CONTROL
SE RECOMIENDA CONTAR CON UN CALENDARIO GENERAL Y OTROS ESPECÍFICOS POR TAREAS DIAGRAMA DE GANTT DIAGRAMA DE GANTT
LA DURACIÓN DE LA PARTIDA SE CALCULA COMO
METRADO / CUADRILLA x RENDIMIENTO
DEPENDENCIAS: DEPENDENCIA FIN – INICIO (FS)
DEPENDENCIA FIN – FIN (FF)
DEPENDENCIA INICIO – INICIO (SS)
DEPENDENCIA INICIO – FIN (SF)
“TARRAJEO DE MUROS” NO PUEDE EMPEZAR SI “MUROS DE ALBAÑILERÍA NO HA FINALIZADO”* DEPENDENCIA FIN – INICIO (FS) “PINTURA DE MUROS” NO PUEDE EMPEZAR SI “TARRAJEO DE MUROS” NO HA FINALIZADO* LA TAREA “B” NO PUEDE EMPEZAR ANTES QUE LA “A” HAYA CONCLUIDO “LOSA ALIGERADA” ¿PUEDE EMPEZAR ANTES QUE LOS MUROS HAYAN FINALIZADO? “ENCOFRADO DE LOSA” NO PUEDE FINALIZAR SI ANTES “TUBERÍAS DE PVC (Varios)” NO HA DEPENDENCIA FIN – FIN (FF) FINALIZADO PREVIAMENTE
LA TAREA “B” NO PUEDE TERMINAR NO NECESARIAMENTE DEBEN
ANTES QUE LA “A” HAYA CONCLUIDO FINALIZAR SIMULTÁNEAMENTE. DEPENDENCIA INICIO - INICIO (SS)
LA TAREA “B” NO PUEDE EMPEZAR SI ES NO NECESARIAMENTE DEBEN
QUE LA “A” NO HA INICIADO TAMBIÉN COMENZAR SIMULTÁNEAMENTE.
“EXCAVACIÓN MANUAL DE ZANJAS” “COLOCACIÓN DE PUNTOS DE LUZ”
“ACARREO DE MATERIAL EXCEDENTE” “ENCOFRADO DE LOSA ALIGERADA” DEPENDENCIA INICIO – FIN (FS)
LA TAREA “B” NO PUEDE CONCLUIR
ANTES QUE LA “A” HAYA INICIADO CALENDARIO DE AVANCE VALORIZADO CALENDARIO DE ADQUISICIÓN DE MATERIALES