You are on page 1of 1

22 Engi neer ed Syst ems December 2010

BY AMANDA MCKEW
AHU WORKORDER Unit Tag: AHU
TheFacilityFiles
CARBON FOOTPRINT
Carbon Neutral

Equipment Information
Description Item quantity Actual quantity
AHU Draw-through 1 1
Special Instructions Yes No N/A
1 Turn on electrical power.
2 Make sure you have special tools.
3 Make sure you have the correct strainer and lters.
4 Make sure you have the correct lubricants.
5 Follow lock-out/tag-out and safety procedures and follow safety procedures.
6 Attach manufacturer's maintenance checklist.
Task #
Weekly Monthly Quarterly
Semi-
annually
Annually
1
WARNING: To prevent personal injury, follow lock-out/tag-out procedures and follow safety
procedures identied in the manufacturer's manual. Disconnect all electrical power to the unit
to prior to performing any of the following maintenance procedures. Read, understand, and
follow all the instruction warnings in all of the component instruction manuals.
2 Inspect general conditions.
3 Inspect wiring/components for loose connections; tighten as required.
4 Check unit over its range of control.
5 Check source of the signal and its amplication on electronic controls.
6 Check air system for leaks.
7 Check belt conditions for wear, proper tension, and alignment. Adjust if necessary.
8 Check belt tension in accordance with the manufacturer's O&M manual.
9 Lubricate fan shaft bearings in accordance with the manufacturer's O&M manual .
10 Clean fan.
11 Replace lters.
12 Inspect exterior piping and valves for leaks.
13 Check operation and clean dampers, louvers, and shutters; lubricate all pivot points.
14 Clean area around equipment.
15 Workorder: Complete and report deciencies and corrective measures taken.
Technician's Comments:
1 CAUTION: To prevent injury, follow lock-out/tag-out procedures and follow safety procedures identied in the manufacturers manual.
2 Check with operating personnel for deciencies.
3 Check for noise and vibration.
Equipment Type
Manufacturer
Model No.
Serial No
Building
Floor
Room name
Year installed
Double duct, blow-through unit
A-B-C
AHU1987
18_1987-01
Veterinary School Of Research
Penthouse
None
1987
McKew is a senior project engineer with
InterPro Solutions. Reach her at amckew@
interprosoft.com.