QC/QA Plan

EXAMPLE OF INSPECTION SCHEDULE


REINFORCING, FORMWORK AND CAST-IN-PLACE CONCRETE

Inspection Parameter
Minimum QC
Inspection Frequency
by Contractor Acceptance Criteria (verified by QA)
Concrete Placement Continuous during
pouring of concrete
In accordance with approved Work Plan,
height of concrete drop not to exceed
5 feet, place and compact within
60 minutes after water is first added, do
not place after evidence of initial set
Equipment Size and Type Continuous during
pouring of concrete
In accordance with approved Work Plan
Concrete Lift Thickness Continuous during
pouring of concrete
Max. 18 inches per lift in continuous
approximately horizontal layers
Maximum Deviation Continuous during
compaction of concrete
1/4-inch from 10-foot straightedge for
exposed finishes, no low spots to impound
water
Formed Concrete Curing Daily during curing of
concrete
Forms maintained in wet condition until
removed, concrete continuously moist for
min of 7 days after pouring
Formed Concrete
Finishing
After finishing of
concrete
Fill holes and patch surfaces in
accordance with Section 03301
Slabs and Flatwork
Curing
Daily during curing of
concrete
Concrete continuously wet for entire
curing period
Note: this table is for illustration only and is not intended to replace or modify contract specifications
that will form the basis of actual CQCP submittals by contractors