Inspection Parameter Minimum QC Inspection Frequency by Contractor Acceptance Criteria (verified by QA) Concrete Placement Continuous during pouring of concrete In accordance with approved Work Plan, height of concrete drop not to exceed 5 feet, place and compact within 60 minutes after water is first added, do not place after evidence of initial set Equipment Size and Type Continuous during pouring of concrete In accordance with approved Work Plan Concrete Lift Thickness Continuous during pouring of concrete Max. 18 inches per lift in continuous approximately horizontal layers Maximum Deviation Continuous during compaction of concrete 1/4-inch from 10-foot straightedge for exposed finishes, no low spots to impound water Formed Concrete Curing Daily during curing of concrete Forms maintained in wet condition until removed, concrete continuously moist for min of 7 days after pouring Formed Concrete Finishing After finishing of concrete Fill holes and patch surfaces in accordance with Section 03301 Slabs and Flatwork Curing Daily during curing of concrete Concrete continuously wet for entire curing period Note: this table is for illustration only and is not intended to replace or modify contract specifications that will form the basis of actual CQCP submittals by contractors