Professional Documents
Culture Documents
All sequential inspections and correction notices shall be completed and signed off.
Exception: Demolition inspection may be scheduled with the foundation inspection if
demolition requirements are completed. See “Demolition” checklist.
Verify a min. 4” inch layer of crushed drain rock at entrance(s) where construction equipment
and vehicles access the site.
Verify that a washout pit has been constructed in a dirt area for surplus discharge of
concrete/wash water from concrete pump, concrete trucks, and cement/plaster mixer.
PROJECTS IN FLOOD ZONES require inspection and approval by Public Works inspector
1. Survey: Lot line survey required for new structures and additions within 2’ of setbacks or
within 3’ of property line. Surveyor letter shall state how property corners were marked. Survey
letter is required at foundation inspection. Basement surveyor letter is required at wall steel
inspection. See [SURVEY LETTER REQUIREMENTS]
Exception: If this is an addition where the layout of the wall that is parallel to the
property line is in line with the existing house, a survey is not required. (i.e. the property
line wall is an extension of the existing wall).
2. Special Inspection: if applicable, all special inspection activities shall be performed and
written field report completes prior to the arrival of the Building Inspector.
3. Raised Foundation: At all exterior doors, and where concrete is placed against building
the foundations shall be raised/extended. Provide 2” minimum vertical separation from concrete
steps, porch slabs, patio slabs and similar horizontal surfaces. If raised foundation detail is not
included in the approved plans, the engineer of record shall provide the contractor with an
approved detail of the raised foundation prior to inspection. The raised foundation detail shall
be on site at time of inspection.
See [ FIGURE A-2]
4. Grounding Electrode: Provide UFER at panel location: Option 1. (1) 20’ long # 4 rebar
placed 3” above bottom of footing and extend above top of footing a min. of 6”. Option 2. (1)
20’ length not smaller than # 4 bare copper wire clamped at end of line to bottom rebar with
an
approved weaver clamp and extend above top of footing un-spliced to panel. CEC 250.52(3)
6. Wood Stakes: Measures shall be taken to allow all wood stakes and form lumber to be
removed. We recommend using Plastic-Sleeve to slip over the wood stake. Note: Wood
stakes/forms not removed shall be drilled and treated with copper green.
FOUNDATION INSPECTION * 2016 New code requirements
• Foundations with stem walls over 4’ high require a wall steel inspection, install outside forms
only.
Soils:
Provide letter verifying all requirements of soils report have been met, (Required if foundation
is Pier & Grade Beam, Basement, and projects West of the 280)
Setbacks: Verify property line markers/setbacks, (property lines shall be set and lines
strung)
Grade:
If applicable, Soils report for compacted soil from approved special inspection agency.
Provide ¼” (2%) slope/drainage away from building foundation. CRC R401.3 Exception. See
your project Grading and Drainage plan for all drainage requirements.
Stumps and roots shall be removed from the soil to a depth of at least 12” below and
adjacent to building/foundation. Exceptions to leave roots in foundation must be stated on SCC
approved plans.
Utilities: Verify utility locations for Electric, Gas, Sewer, and Water.
Forms shall be substantial and sufficiently tight to prevent leakage of mortar. ACI 318 6.1.2
Forms shall be properly braced or tied together to maintain position and shape. ACI 318
6.1.3
Design of formwork shall include rate and method of placing concrete, construction loads,
including vertical, horizontal, and impact loads.
Removal of forms and shoring: forming and shoring shall not be removed until concrete
has sufficient strength to support safely its weight and loads placed thereon. ACI 6.2 (B)
Compressive strength of concrete:
* Minimum compressive strength 3,000 psi. Special inspection is not required unless specified
by project engineer, however contractor shall show proof of design mix from the readi-mix
company CRC R404.1.2.3.1.
Footings:
See attached CPA Minimum Foundation Requirements.
Minimum footing depth 20”, width 14”, and foundation wall min. 8”. See plans
Verify footing is widened at Strong wall location per ESR 1267 or per ESR report
Remove all trash, roots, debris, and loose dirt from bottom of footing.
Elevation of foundation above street gutter shall be 12” plus 2% of the distance. R403.1.7.3
Reinforcement:
• See attached Rebar Lap Splicing Table
Verify specified size and grade of steel.
Verify min. 3” clearance when permanently exposed to earth. ACI 7.7.1
Lap splices shall be a minimum 12”. Refer to plans for lap splices. ACI 12.15
Verify splices are staggered a minimum of 24”. ACI 12.15.4.1
Minimum reinforcement: (2) # 4 bars at bottom and (1) at top of footing.
See [FIGURE A-1]
Wall openings shall have additional vertical reinforcement, or the same size placed within 12”
of each side of the opening. R404.1.2.3.7.3
Steel shall be clean and free from oil, dirt and excessive rust.
Anchorage:
All embedment’s and anchor bolts shall be installed at time of inspection. (no wet setting)
Verify anchor bolts and hold-downs anchors are sized and spaced per “shear-wall schedule”.
Hold-down anchors shall extent into footing.
Minimum anchor bolt size shall be 5/8” diameter, 7” embedment.
Min. 4” distance from end of sill, max. 12”
Min. (2) anchor bolts/straps per piece of sill plate.
HARDYFRAMES: X Series Hardy Frames requires X series bolt template, must install bottom
bolt bracing bracket.
Verify required panel height, (may need to raise foundation wall to comply with max. blocking
height requirement.)
Access openings: Under-floor foundation access openings min. 18”x24” (pipes, ducts and
other nonstructural construction shall not interfere with the accessibility to or within under-floor
areas.
Note: The number one Code Defect/Correction at the joist inspection is ducts and
pipes blocking the access openings. If necessary, widen the access openings to
accommodate ducts and pipes.
Water Proofing: if applicable, provide letter from manufacturer’s rep. for waterproofing.
Special Inspection Reports: All results of special inspections, field reports, surveys, etc
shall be addressed to the City of Palo Alto with job address and permit # for inclusion in city
records
Concrete against wood is prohibited except for existing buildings and when door swings-
out over landing
See “Concrete Entries and exits” guidelines.
Flood and Air vents: If applicable, verify location and size of foundation vents are in
compliance with approved plan specifications. See flood vent illustration and requirements
below.
FLOOD ZONE (See plans)
Concrete slab/footing shall not bear directly on plumbing lines. Concrete shall extend
6” minimum below plumbing pipes. See [FIGURE A-1]
FIGURE A-1