Professional Documents
Culture Documents
Batching
Mixing
Transport to the job site/Placement in the
Formwork
Consolidation
Finishing
Curing
Formwork Removal
BATCHING
Process of measuring concrete mix
ingredients by either mass or volume and
introducing them into the mixer.
Why Measuring ingredients accurately?
To produce concrete of uniform quality the
Most specifications require that batching be
done by mass rather than by volume (ASTM
C 94 or AASHTO M 157).
Water and liquid admixtures can be measured
accurately by either volume or mass.
Why Sand should be measured by
Mass?
What is isBulking
Bulking the of sand?
increase in total
volume of moist
fine aggregate over
the same mass dry.
Good practice
Weighing the
aggregate and
adjusting for
moisture content
when proportioning
concrete
Surface tension in the moisture holds the particles apart, causing an increase in
volume.
Bulking of a fine aggregate (such as sand) occurs when it is shoveled or
otherwise moved in a damp
condition, even though it may have been fully
MIXING
Concrete should be mixed thoroughly until it is
uniform in appearance i.e. all ingredients
evenly distributed.
How to ensure Concrete is adequately mixed?
Samples taken from different portions of a
batch will have essentially the SAME density,
air content, slump, and coarse-aggregate
content.
MIXING
Precautions
Don’t overload the Mixer.
Operate Mixer at a speed recommended by the
manufacturer.
For Increased output use a larger mixer or
additional mixers.
Proper cleaning of Mixer
Mixer would be less efficient if the blades of a mixer
become worn or coated with hardened concrete.
Stationary Mixing
Many stationary mixers have timing devices,
some of which can be set for a given mixing time
and locked so that the batch cannot be
discharged until the designated mixing time has
elapsed.
Nonagitating trucks used for Truck agitators used for long hauls
short hauls
Nonagitating trucks are used with central mix batch plants where short hauls
and quick concrete discharge allows the rapid placement of large volumes of
concrete.
Agitation mixing capabilities allow truck agitators to supply concrete to
projects with slow rates of concrete placement and at distances greater than
nonagitating trucks.
External Vibrators
Form vibrators Connect the forms to a vibrating
mechanism (shake the entire form)
Used for thin or heavily reinforced concrete members
For stiff mixes where internal vibrators can’t be used
Vibrating table Used in Precast industry
Surface Vibrators Used to consolidate concrete in
Floors up to 10 in thick. Example Vibratory Screeds
Vibratory screeds such as this truss-type unit reduce the work of
strikeoff while consolidating the concrete
Where floor tolerances are not critical, an experienced operator
using this vibratory screed does not need
screed poles supported by chairs to guide the screed. Instead, he
visually matches elevations to forms or previous
passes. The process is called wet screeding
Consequence of Improper Vibration
Honeycomb results when the spaces between coarse aggregate particles do not become filled with mortar.
Reasons Faulty equipment, improper placement procedures, a concrete mix containing too much coarse aggregate, or congested
reinforcement can cause honeycomb.
Excessive entrapped air voids are similar to, but not as severe as honeycomb. Vibratory equipment and operating procedures are the
primary causes of excessive entrapped air voids, but the other causes of honeycomb apply too.
Sand streaks results when heavy bleeding washes mortar out from along the form.
sand streaking is caused by excessive bleeding. As bleed water moves upward along the form in long channels, it washes away some
of the paste and exposes sand. Sand streaks can be avoided by reducing bleeding. You can do this by taking one of the following
steps.
Reduce water content
Add an air-entraining admixture
Add a water-reducing admixture
Increase cement content
Add fly ash to the concrete as a supplementary cementing material, or use a blended cement
Blend a fine sand to increase the amount of material passing the No. 50 and No. 100 screens.
Undervibration
Honeycomb
Excessive amount of entrapped air voids –
Bugholes
Honeycomb Bugholes
Consequence of Improper Vibration
Undervibration
Sand streaks
Cold joints
Placement lines Sand steaks
Subsidence cracking
Cold joints
Consequence of Improper Vibration
Overvibration
Segregation
Sand streaks
Loss of entrained air in air-entrained concrete
Excessive form deflections or form damage;
Form failure caused by excessive pressure from
vibrating the same location too long
Most of the problems are caused by under vibration
(over vibration tends to cause segregation)
FINISHING OF CONCRETE
Bull Floating
Darbying
Bull Floating must be completed before any excess bleed water accumulates
on the surface. because this is one of the main causes of surface defects
such as dusting or scaling in concrete slabs.
Darbying brings the surface to the specified level and is done in tight places
where a bullfloat cannot reach.
Bullfloating must be completed before any bleed water accumulates on the
surface
Purpose
To embedding the aggregate just beneath the surface
To remove slight imperfections, humps and voids.
To compact the mortar at the surface in preparation
for additional finishing operations
Carried out with flat wood, metal blades etc
Floating tend to bring paste to the surface, so
floating too early or too long can weaken the
surface.
Exterior concrete should not be troweled because troweled
surface can be slippery when wet.
Trowling
When smooth, hard, dense surface is desired,
floating should be followed by steel troweling.
Trowling should not be done on a surface that
has not been floated.
Exterior concrete should not be troweled
Brooming
Objective of Curing
To prevent loss of moisture and
To control the temperature of concrete for a period
sufficient to achieve a desired Strength level.
Ponding
Spraying
Moisture retaining coverings saturated with water
e.g burlap
Water proof curing paper (polyethylene sheets)
Curing Methods & Materials
Methods that maintain the presence of mixing water
in the concrete during the early hardening period.
Example ponding or immersion, spraying or fogging, and
saturated wet coverings.
Fogging Sprinklers
Curing Methods & Materials
Methods that reduce the loss of mixing water from
the surface of the concrete.
Example covering the concrete with impervious paper or
plastic sheets, or by applying membrane-forming curing
compounds.
Composite property
f(conditions, equipment, type of concrete, mix).
E.g., dry mix --> poor workability if pumped, but
good workability when placed in a conveyor belt
(mass concrete)
Slump test – Measure consistency
Vebe test – For mixtures having low consistency
Compacting factor test – Evaluate compactibility
characteristic of concrete mixture
Factors affecting Workability (Reading assignment)
Segregation and Bleeding
Laitance – Water rising to the surface and carrying cement particles and sand
with it
Porosity goes up --> paste can easily be abraded --> dusting.
Segregation: Separation of components of a fresh
concrete so that they are no longer uniformly
distributed.
Coarse aggregate tends to segregate due to gravity.
Typical of dry mixes.
Bleeding: water rising to the surface. Typical of wet
mixes.
Laitance – Water rising to the surface and carrying
cement particles and sand with it
Causes of bleeding and segregation:
Improper consistency
Excessive amount of coarse aggregate
Lack of fines
Inappropriate placing and compacting
methods
Control of Segregation