LAMPIRAN E
DENAH GUDANG BAHAN PELEDAK
LAMPIRAN C
KLASIFIKASI DETONATOR NONLISTRIK
PRODUK ORICA-AUSTRALIA
MS Delay Time
(MS)
0
25
50
75
100
125
150
175
200
250
300
350
400
450
500
600
LP Delay Time
(MS)
25
200
400
600
1000
1400
1800
2400
3000
3800
4600
5500
6400
7400
8500
9600
J-Hook Colour
Dark green
Red
Pink
Tan
Orange
Cream
Yellow
Lime
Light green
Green
Aqua
Light blue
Blue
Mauve
Purple
Hot pink
Sumber : Orica-Australia
LAMPIRAN B
FOTO BAHAN, PERALATAN, DAN PERLENGKAPAN PELEDAKAN
AN kemasan 1200 kg
Power Gel
Blasting Machine
Bunker
LAMPIRAN D
FOTO PROSES PELEDAKAN
Final check
Sebelum peledakan
Peledakan
Sesudah Peledakan
LAMPIRAN A
PERHITUNGAN GEOMETRI PELEDAKAN
1.
a. Burden (B)
B = 3,15 De (SGe/SGr)0,33
= 15,227 ft
= 4,64 m
b. Spasi (S)
S = 1,4 B
= 1,4 x 4,64 m
= 6,496 m
c. Stemming (T)
T = 0,7 B
= 0,7 x 4,64 m
= 3, 248 m
d. Sub drilling (J)
J
= 0,3 B
= 0,3 x 4,64 m
= 1,392 m
g. Kedalaman (L)
L =H+J
= 10,287 m + 1,392 m
= 11,679 m
h.
i. Volume batuan yang akan dibongkar (VR) dan jumlah lubang (n)
VR
=BxSxHxn
30.000
= 97
2.
a. Burden (B)
B = Kb . De/12 , di mana Kb = 25 jika memakai ANFO
= 25 x 6,75 /12
= 14,0625 ft
= 4,28 m
b. Spacing (S)
S = Ks . B
= 1,15 x 4,28 m
= 4,92 m
c. Stemming (T)
T = KT . B
= 0,7 x 4,28 m
= 2,99 m
d.
= 0,2 x 4,28 m
= 0,856 m
J2 = 0,3 x 4,28 m
= 1,284 m
JR = (J1+J2)/2
= (0,856+1,284)/2
= 1,07 m
e. Kedalaman lubang (L)
L = Kh . B
= 2,6 x 4,28 m
= 11,128 m
f.
g.
=BxSxHxn
= 142
=5m
Spacing (S)
= 6,5 m
= 1,5B = 7,5m
Stemming (T)
= 0,5B = 2,5m
Subdrilling (J)
= 0,1B = 0,5m
= 0,8 g/cc
Densitas batuan
= 2,2 gr/cc
=BxSxHxn
30000
= 5 x 6,5 x 7 x n
= 30000/227,5
= 131,9 lubang 132 lubang
= VR x densitas batuan
= 30.000 m3 x 2,2 ton/m3
= 66.000 ton
Powder factor