Date: 13
th
April 2014

FILE NOTE
SITE WALK AROUND MEETING AT ZETA CAF (THE ADDRESS)

Attendees:-
Mr. M.A Husein - DBB
Mr. Amr Abbas - DBB
Mr. Mehmood - DBB
Mr. Ansari GM - DBB
Mr. Anjum - BKG
Mr. Anees - Dutco Tennant
Mr. Jayakumar - DBB Joinery
Mr. Pravin - Al Fahad
Mr. Ghalib - Al Fahad
Mr. Ahmed - Belhasa Projects
Mr. Mathews - Mathews Metal

S # Description Action By Date
1.
Counters
Expansion Joint
Banquet Seating
Cladding + 3 D
Polishing
Kitchen External wall cladding
Cocktail Bar
Planter Box (Banquet Seating)
Lime stone Main Bar (delivery of material 15/04)
Main Bar floor
Banquet Seating
Counter horizontal support polishing
Al Fahad

24/04/14

23/04/14

19/04/14

TBA

26/04/14

TBA

21/04/14

24/04/14

21/04/14

16/04/14

19/04/14

19/04/14
2.
Level 5
Kitchen Ceiling - Clearance
Light Fittings delivery and installation
Temporary Power
AC Duct / Extract
Light Fittings
Duct work for shaft
Fire place provision
Level 4
LPG / Fire Alarm (to use Address Hotel existing
contractor)
BKG


23/04/14

19/04/14

21/04/14

21/04/14

20/04/14


19/04/14
TBA

BKG to
proceed

Page 2 of 2


Date: 13
th
April 2014

FILE NOTE
ZETA CAF (THE ADDRESS)



S # Description Action By Date
3.
Adult - Swimming Pool
- Reflection Pool
- Water Feature
Belhasa
Project
Inspection by
Tuesday upon
clearance from
BH water to be
filled in the pool
4.
Kitchen Ceiling
Table (L Shaped)
All Counters (Car casing)
Cushion and Fabric
F26
DBB Joinery

28/04/14


24/04/14


15/04/14

Local material
Updated delivery schedule of equipments
Kitchen ceiling / Hood
Dutco Tennant
23/04/14

09/05/14
5. Hoarding around dumb water and associated work &
hording removal from Main Pool area
DBB 24/04/14
6. Toilets at Level 4 (ready for public use)
DBB 25/04/14
7. Removal of Scaffold Access and provide new (other
way)
DBB 24/04/14
8. Umbrellas - Delivery Corradi 12/05/14
9.
Fireplaces
The Kontainer 28/05/14
.