GANTT CHART

Project Name: TODAY’S DATE


Five-Storey School Building with Basement 12/12/2022

OBJECTIVES JAN FEB MAR APR MAY JUN JULY AUG SEPT OCT NOV DEC
Pre- Construction
Submission of Documents
Approval of Documents
Design Phase
Site Survey
Geo technical Report
Site Design Approval
Outline and Design Specification
Construction Planning
Procurement
Submission of BOQ
Approval of BOQ
Issue Purchase Order for BOQ
Apply for Building Permits
Site Preparation
Grading/Leveling the Area
Install.of Fence around the site area
Cleaning and Grubbing of site
Excavation
Back filing/Leveling
Construction
1st floor
Steel Work for Foundation and Footing
Installation of Column Framework
Concreting footings and Column Ground
Framework for Stairs
Installation of Beams and Girders
Installation of Tie Bar
Pouring of Concrete for Slab
2nd floor

Steel Work for Foundation and Footing


Installation of Column Framework
Concreting footings and Column Ground
Framework for Stairs
Installation of Beams and Girders
Installation of Tie Bar
Pouring of Concrete for Slab
3rd floor
Steel Work for Foundation and Footing
Installation of Column Framework
Concreting footings and Column Ground
Framework for Stairs
Installation of Beams and Girders
Installation of Tie Bar
Pouring of Concrete for Slab
4th floor
Steel Work for Foundation and Footing
Installation of Column Framework
Concreting footings and Column Ground
Framework for Stairs
Installation of Beams and Girders
Installation of Tie Bar
Pouring of Concrete for Slab
5th floor
Steel Work for Foundation and Footing
Installation of Column Framework
Concreting footings and Column Ground
Framework for Stairs
Installation of Beams and Girders
Installation of Tie Bar
Pouring of Concrete for Slab
Other Civil Works
Wall Framing
Fabrication of steel works for wall
Wall Frameworks Installation
Wall Concreting
Installation of Plumbing
Installation of Electrical Lines
Installation of Doors and Windows
Installation of Railings for Stairs
Painting
Clearing Site