Project : PCMC - 8 Storey Building Project

Location : Agham Rd. Cor. Quezon Ave., Quezon City


Company : SC Megaworld Construction & Development Corporation
Subject : PROPOSED 14 DAYS WORK CYCLE

DAYS
DESCRIPTION
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Column Works
line & grade
rebar works
Installation of ties
installation of vertical flies
installation of column forms
Augment / Bracing
Concrete pouring 1st lift

Girders & Beams


Scaffolding Works
Installation of Beams
Bottom forms
Installation of Girders
Installation of side forms
Tie rods

Conventional Slab
Scaffolding Works
Insallation of Slab rebars
Bracing
Supports
Column neck
Tie rods

Concrete Pouring of Slab