Professional Documents
Culture Documents
Purpose
The purpose of this guide is to identify the points to be inspected to ensure that
ready-mixed concrete produced off-site by the supplier is delivered to site,
placed in the forms and compacted correctly in order to achieve the designer’s
requirements.
The aspects covered are as follows:
Delivery to the site by agitator trucks
Methods of delivery to and placing where needed
Preparation of construction joints
Compacting of concrete
Curing of concrete
There are numerous methods of delivering and placing concrete where needed
and each has its disadvantages as well as advantages. The types are listed and
assessed below:
Wheelbarrow/Bucket
Cheap but labour-intensive
Slow rate of delivery so cannot be used for large pours
Watch for segregation if long travel distance
Useful if no access available for larger plant delivery methods, i.e. in
existing buildings or refurbishment
Page 1 of 6
Issued by Issue Date Document No.
Chute
Cheap but not convenient if casting a large area
Quick delivery method if big quantity needed in one location
Gradient needs to be sufficient for concrete to flow freely
Watch for segregation at discharge point
Chute needs to be grout-tight to avoid loss of grout
Concrete Skip
Concrete skips come in many sizes but their use is often governed by the
capacity of cranes on site
Speed of delivery is governed by the safety aspects of maneuvering the
skip to and from the concrete delivery truck
Speed of delivery is governed by the hoisting and slewing time of the
concrete skip by the crane
Discharge in to a column or wall is slowed by the need to have a tremie
pipe and hopper to avoid segregation
Skips need to be kept clean so that the opening mechanism remains easy
to operate and does not cause grout to be lost
Page 2 of 6
Issued by Issue Date Document No.
Concrete Pump
Very versatile for both vertical and horizontal reach
Horizontal reach can be increased by addition of pipes
Fast delivery of concrete
Can be used for casting walls and columns without the need for tremie
pipe as hose can be fed between the steel into the element being cast
Workability of concrete needs to be high to avoid blockage in pipes
Blockages can cause disruption to the casting operation while the pipe
blockage is being cleared
Delivery pipes need to be kept away from steel reinforcement as there is
much movement during the pumping operation that will loosen it
Page 3 of 6
Issued by Issue Date Document No.
Placing Boom
Needs holes through the floors and support to the mast
Needs the pipe risers to be attached to a core wall, plus access to the
joints to clean out in the event of a blockage
Needs a stationary pump located at the ground level with access by
concrete truck
Fast delivery of concrete
Placing boom is installed on site permanently until the concrete
operations are complete
If placing boom supplied by ready-mixed concrete supplier no chance to
change suppliers
Range of boom is limited
Construction joints are the joints formed between cast concrete and new
concrete. They need to be clean and clear of debris so that the new concrete
bonds with the existing concrete. Construction joints are unavoidable so need to
be in the position with the least detriment to the structural integrity.
In beams and slabs they are placed within the middle third of the span. In walls
and columns they are just above the slab level for storey-height casting; for
others the joints are minimized.
In slabs and beams the construction joints are vertical (or perpendicular to the
main axis if sloping). In columns they are horizontal and in walls they can be
both horizontal and vertical dependent upon the wall length.
Page 4 of 6
Issued by Issue Date Document No.
Compacting of Concrete
Curing of concrete
Page 5 of 6
Issued by Issue Date Document No.
Curing is basically the prevention of loss of moisture from the concrete before it
is used in the hydration process, and can be achieved by either wrapping the
concrete in an impervious layer (polythene sheet or sprayed on membrane) or
by having a sacrificial water layer (water-ponding of slabs or wet hessian sheets
on vertical surfaces).
With large volume casts, such as deep rafts, curing should also take into account
the dissipation of the heat built up during the hydration process. Concrete will
rise in temperature, approximately 10 oC for every 100kg/m3 of cement used in
the mix, and this heat needs to be dissipated slowly to avoid large differential
temperatures between the core of the concrete and the external surfaces. In
these cases, insulated mats or polystyrene boards will be needed along with the
curing method chosen –water-ponding or sprayed membrane.
Comments
This is probably the single most important operation on the site as the structural
integrity and expectations of the designer rely on this being correctly performed.
Good quality concrete can be achieved with very little additional effort.
Page 6 of 6