USARI IDOHO PIPELINES REPLACEMENT PROJECT

26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 26/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
9.3. PROCEDURE MAIN STEPS

IMPORTANT NOTE










STEP DESCRIPTION
1. Mooring of installation vessel away from platform
2. Loading the riser from supply vessel to the installation vessel
3. Installation vessel in position at platform
4. Installation of all equipment on the platform

PREPARATORY WORK ON PLATFORM
5. Preparation works on platform:
- Scaffolding erection
- Winch transfer, positioning, welding on main deck and load testing
- Cable overboarding system installation and routing of cable
6. Subsea survey
7. Identification of subsea working area & cleaning of jacket area by diver

RISER INSTALLATION
8. Hanger clamp installation
9. Subsea clamp installation
10. Clamp alignment checking
11. Riser upending on deck
12. Riser overboarding
13. Winch connection
14. Riser load transfer to winch
15. Crane disconnection
16. Positioning of riser into upper clamp
17. Riser rotation into final orientation
18. Riser lowering (hanger flange stopped by hanger clamp)
19. Positioning of riser into lower clamp
Diver to monitor
20. Riser tie-in
21. Diver Survey

PRE-COMMISSIONNING ACTIVITY
22. Pigging & Hydrotest test (once subsea spool installed, before or after the riser guard
installation)

Whichever installation vessel is chosen to carry out the work, the step by step
written in section 10 as well as the installation drawings in Appendix L shall be
followed.
In the few instances where the use of the DSV texas requires more details (i.e.
vessel positioning, cranage verification, diver umbilical checks) refer to
Addendum.


USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 27/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
STEP DESCRIPTION
RISER GUARD INSTALLATION
23. Ensure subsea cleaning of jacket area by diver
24. Subsea stabbing guide installation
25. Riser guard installation
26. Riser guard bracing adjustment and welding
27. Diver Survey

TOPSIDE SPOOL REMOVAL & INSTALLATION
28. Existing topside spool removal
29. Metrology (by laser survey)
30. Finalization of topside spool fabrication
31. Installation and connection of topside spool and its support
32.
PRE-COMMISSIONNING ACTIVITY
33. Leak test

CLEAN-UP
34. Platform Clean-up

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 28/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
10. INSTALLATION PROCEDURE
The flowchart presented in this section indicates the planned sequence of operations. The
implemented offshore sequence of operations may have to be revised to accommodate
unforeseen site or weather conditions, in order to avoid unnecessary vessel stand-by or site
access conflict.

Since the task plans are principally live working documents, the task plans may be revised offshore
at the time of the installation, following discussions between Offshore Manager, Field / Project
Engineer and Client representative onboard. Any procedural changes will only take place
according to SAIPEM Management of Change Procedure.

10.1. Task plans

Task plan n1:
Preparation activities
onboard vessel
Task plan n5:
Riser installation
Task plan n4:
Riser upending,
overboarding and
flooding
Task plan n6:
Riser guard installation
Task plan n2:
Preparation activities
on USARI FA platform
Task plan n3:
Hanger clamp &
Subsea Clamp
installation
Task plan n7:
Existing topside spool
removal &
Topside spool
installation
Task plan n8:
Platform clean-up

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 29/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
10.2. Task plan n1: Preparation Activities onboard S355

PREPARATION ACTIVITIES ONBOARD S355
Step
n
Sequence Responsible Drawings
1.
INST. VESSEL Permit To Work in
place.
Master
HSE rep
/
2.
INST. VESSEL is positioned bow at
North-East of USARI FA platform and
parallel to the swell. INST. VESSEL
is far away from platform.
Master 0062671-03
3.
All personnel involved in the
operations are informed about the job
to be performed.
ALL /
4.
Preparation of rigging for riser
transfer to INST. VESSEL.
Deck foreman 0062671-11
5. All rigging certified. Deck foreman /
6.
Preparation of INST. VESSEL deck
layout for riser transfer (wood
supports).
Deck foreman 0062671-01
7. Supply vessel berthing.
Master
Deck foreman
/
8.
USARI FA riser is horizontally lifted
and transferred from supply vessel
deck to INST. VESSEL deck.
Tug Master
Master
crane operator
Deck foreman
0062671-02
9.
Disconnection of lifting rigging used
for transfer
Deck Foreman
Crane Operator
/
10.
Connection of up-ending rigging.
Installation of tag lines.
Deck Foreman
Crane Operator
0062671-11
11. All rigging certified. Deck foreman /
12. Riser secured on deck. Deck foreman /
13.
Supply vessel moves away from
INST. VESSEL.
Tug Master
Master
/
14.
Marking of riser flange and hanger
clamp in order to monitor visually the
rotation of the riser during
installation.
Deck foreman /
15. Marking of flooding line on riser Deck foreman 0062671-06

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 30/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
PREPARATION ACTIVITIES ONBOARD S355
Step
n
Sequence Responsible Drawings
16.
Installation of blind flange at bottom
with flooding valve and protection if
required.
Only 4 bolts will be pre-installed on
the flange
Diver superintendent or his team to
witness
The riser upper flange can be:
- the pre-commissioning flange
equipped with an open valve to
exhaust the air pressure during
the flooding
- a wood flange
Deck foreman
Diver superintendent
/
17.

Check position of
valve on bottom flange

Valve shall be on the upper part of
the flange (when the riser is up)

Valve shall be open

Deck foreman /
18.
Installation of the 2 transponders,
one close to the flange and the
second one at the exit of the bottom
bend, to get data for riser orientation
confirmation

Deck foreman
Survey
/

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 31/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
10.3. Task plan n2: Preparation Activities on USARI FA Platform

PREPARATION ACTIVITIES
Step
n
Sequence Responsible Drawings
1.
Permit To Work from USARI FA in
place.
Dive permit in place.
Inform platform HSE responsible.
Barge Master /
2.
Move all temporary equipment and
personnel from INST. VESSEL to
USARI FA Platform main deck:
rigging, cutting, grinding, welding
equipment, air hoses, electric hoses,
scaffolding, and lightingetc.
Riggers
Deck Foreman
/
3.
A topside survey shall determine if a
winch frame shall be fabricated and
installed to rest on deck frame or
spread the load.
Superintendent
1rst Assistant
Inst. Eng.
0062671-04
4.
Erection of scaffolding on:
- jacket level
- at future hanger clamp location
- at existing/new topside spool
bottom and upper flange and
support
- at riser guard location (leg)



Scaffolders /
5. Transfer the winch on platform.
Riggers
Deck Foreman
0062671-04
6.
Installation of winch at main deck.
Secure it by welding to the main deck

Riggers
1rst Assistant
0062671-04
7.
Load Test of the winch to be
performed at 12.5t on the padeye to
be used for the topside spool
removal/installation.
Deck Foreman,
QA/QC
Client Rep
/
SCAFFOLDING AREA

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 32/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
PREPARATION ACTIVITIES
Step
n
Sequence Responsible Drawings
8.
Remove main deck net.
Weld horizontal pipe for cable
overboarding and vertical pipe for
cable guiding
Deck Foreman 0062671-04
9.
Remove any obstructing item that
prevent the riser installation if
necessary
Deck Foreman
Welder Foreman
/
10.
If required, install diver installation
aids (come alongs, chain hoistetc)
on the platform and prepare electric
cables for power supply coming from
INST. VESSEL.
Diving Supervisor /


USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 33/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
10.4. Task plan n3: Riser Clamps Installation on USARI FA Platform
Clamps will be installed by different teams, platform team or divers, according to the tasks to be
performed and the water depth where to operate.

Level
(approx)
Clamp type
Weight
(kg)
Installation
Activities
+4.3 m Hanger clamp 400 kg
Platform
rigger
-10.9m
Subsea Riser
Clamp
1.0t Air diving


Check that lifting padeyes are welded on the subsea clamp
If not, a round sling will be installed on the clamp.


Note: No diving to be performed while hanger clamp is being installed


RISER CLAMP INSTALLATION
Step
n
Sequence Responsible Drawings
RISER HANGER CLAMP INSTALLATION
1.
Platform team to mark position of
doubler plates and hanger clamp
using metrology.
Platform rigger
0062645
0062648
2. Welding of the 2 doubler plates Welding Foreman 0062648
3.
Deck team to prepare clamp in
configuration for lifting in close
position.
Riggers
Deck Foreman
/
4.
Lifting rigging connection to clamp.
Deck lifting trial for rigging
adjustment.
Riggers
Deck Foreman
/
5. Clamp overboarding.
Crane operator
Deck Foreman
/
6.
Load transfer of clamp to winch.
Disconnection of crane rigging.
Clamp lowering.
Riggers
Deck Foreman
Crane operator
/
7.
Platform team to position the hanger
clamp in final position and secure it.
Riggers
Deck Foreman
/
8.
Platform team to weld the clamp to
the bracing.
Welder Foreman /
9. Platform team to perform NDT. Welder Foreman /
10. Paint touch up at welding location Painters /
11.
Platform team to open clamp and
secure it in open position with ropes.
Riggers
Deck Foreman
/


USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 34/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.

RISER CLAMP INSTALLATION
RISER SUBSEA CLAMP INSTALLATION
1.

Ensure that the subsea bracings are
checked by divers to avoid loose
poles on upper braces.

If necessary, install a downline from
installation vessel to platform.
Diver Supervisor
Superintendent
/
2.
Diver to perform metrology/taut wire to
localize subsea clamp areas.
Area of cleaning can be delimited by
rope.
Diver
Diving Supervisor
NG00-SA-
NDZZZ-0062647
0062671-05
3.
Diver to clean area using HPWJ
according to drawing.
Diver 0062671-05
4.
Diver to mark position of clamp using
taut wire.
Diver 0062671-05
5.
Superintendent and Dive supervisor
to confirm clamp location
Diver Supervisor
Superintendent
0062671-05
Safety note:
Ensure that before any
diving, the scaffolding
work will stop.
Scaffolding to be green
tagged upon completion
insuring competent
construction, insure
there are no objects
from the scaffolding that
can fall into the dive
area and there is no
work progressed during
dive operations.
Prework survey by diver
to determine the work
area and the area above
the divers work area is
clear from all potentially
hazardous items.

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 35/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
RISER CLAMP INSTALLATION
6.
Deck team to prepare clamp in
configuration for lifting.
Deck lifting trial for rigging
adjustment.
Diving superintendent or his team to
view and accept prior to leaving the
deck.
The riser clamp will be installed close
at riser side while the clamp will be
installed open at bracing side.
Riggers
Deck Foreman
0062671-10
7. Clamp overboarding.
Crane operator
Deck Foreman
0062671-10
8. Lowering clamp into water
Load transfer of clamp to winch with
clamp into water.


Crane operator
Deck Foreman
0062671-14
9.
Diver to position clamp in final
position.

Note: Pay attention to below anode
on jacket horizontal bracing while
installing
Diver 0062671-14
10.
Clamp to be bolted up but final
tightening to be carried out later
Diver to check batter angle.
Diver 0062671-14
11.
Diver to open the clamp (riser side)
with tirfor and to secure it by rope
Diver 0062671-14
12. Diver to perform visual inspection. Diver 0062671-14
Safety note:
No diver into water

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 36/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.

METROLOGY
1.
Diver to perform measurement/taut
wire and to confirm accuracy of
clamp positioning and alignment with
hanger clamp.
Record measurement on datasheet
Diver Appendix F
2.
If not accurate, redo clamp
positioning
Diving Supervisor
/ Superintendent
/
3.
Clamp bolts final tightening using
spanner or impact
Diving Supervisor
/ Superintendent
Appendix F
4.
Secure subsea clamp to bracing to
avoid any motion during riser
installation
Diver
Platform riggers
0062671-14
5. Recovering of clamp rigging.
Diver
Platform riggers
0062671-14

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 37/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
10.5. Task plan n4: Lifting, Up-Ending and Transfer of the Riser on USARI
FA Platform

To summarize the operations, we can consider 3 phases:
UPENDINGOVERBOARDING/FLOODINGTRANSFER TO WINCHINSTALLATION

Status on USARI FA Platform:
o All equipment and rigging necessary for the riser transfer are on the platform, ready to use.
o All riser clamps, hanger and subsea clamps are installed and in open position.
o All the platform personnel have been transferred onto USARI FA.
o Winch tested and ready to use.
o Riser prepared on INST. VESSEL deck.

RISER UPENDING, OVERBOARDING, UP-ENDING AND TRANSFER
Step
n
Sequence Responsible Drawings
PREPARATION AND UPENDING
1.
All persons involved must be familiar
with this procedure.
Ensure that INST. VESSEL Permit To
Work and USARI FA platform Permit
To Work, Dive Permit, JSA and Tool
Box Talk briefings have been
completed and correct PPE is
utilized.
Master
Diving Supervisor
/
2.
Weather forecast and weather
window are favorable for the whole
riser updending and transfer.
Superintendent /
3.









ALL /
The dive team is to be
debriefed by the dive
supervisor on the scope of
work.
All equipment ready as
per subcontractor
procedure documents.
JSA/Tool Box Talk
completed (DWP and
Task plan included).

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 38/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
RISER UPENDING, OVERBOARDING, UP-ENDING AND TRANSFER
Step
n
Sequence Responsible Drawings
4.









Diving supervisor /
5.
During the operations, weather
forecasts will be thoroughly reviewed
to establish if the weather and sea
conditions are likely to deteriorate
during the operation or not. A
weather watch is to be posted to give
warning of approaching squalls or
storms. During all tasks, diving
supervisor, divers and surface
tenders are to maintain watch on
weather and sea conditions.
Deteriorating conditions are to be
reported and diving operations
suspended when conditions are
unsafe.
Weather window time frame to be
agreed by all partied prior to riser lift.
ALL /
6.
Pre dive checks to be carried out.
Checklists completed, signed and
kept in dive control.
Diving Supervisor /
7.
Dive Supervisor to keep a detailed
log of all directives, communications,
actions and results in the dive
logbook.
Diving Supervisor /
8.
Deploy diver to make an inspection of
the pre-installed riser clamp, ensuring
that the riser clamp is tied back in the
open position and free from
obstruction.
Diving Supervisor /
Safety Note:
Diving Supervisor
should consider all
possible safety
hazards and
precautions
including those
identified in the
HIRA and Risk
Assessments

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 39/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
RISER UPENDING, OVERBOARDING, UP-ENDING AND TRANSFER
Step
n
Sequence Responsible Drawings
9.




ALL /
10.
INST. VESSEL in position at USARI
FA platform.
Superintendent 0062671-03
11.
Ensure lifting rigging for transfer is
checked.
Connection of riser rigging to crane.
Connect crane tugger line to riser
bottom for riser orientation.
Riggers
Deck Foreman
/
12.
Perfect communications will have to
be established. Perform a full radio
communication, check with all parties
involved with the operation. VHF
hand held radios to be used with
dedicated operating channel
allocated.
ALL /
13.
Final communication test is done
between crane operator, the platform
team, the responsible of the lifting
operations, Bridge and Masters.
Master /
14.


OPEN the valve on the bottom and
on the upper flange.

Ensure that pre-commissioning liquid
is inserted into the riser as requested
in the pre-commissioning procedure.
Superintendent
Deck foreman
0062671-06
15. Riser up-ending by crane
Superintendent
Crane operator
Deck foreman
0062671-14
OVERBOARDING & FLOODING
16.
Riser is overboarded and lowered
into water.
Pay out tugger line to follow riser.
Superintendent
Crane operator
Deck foreman
0062671-14
17.
Lower the riser into water until
flooding marking is at water level.
Crane operator 0062671-14
Ensure that line for
level of free-flooding
is marked on riser
Deck crew, and all
personnel involved in
the operations are
informed about the job
to perform. JSA will be

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 40/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
RISER UPENDING, OVERBOARDING, UP-ENDING AND TRANSFER
Step
n
Sequence Responsible Drawings
18.
Diver to close valve once free-
flooding is completed.

(typical)
Diver 0062671-14
TRANSFER TO PLATFORM
19.
Connect the riser top rigging to the
lifting winch with zodiac
Rigger
Zodiac
0062671-14
20.
Lower riser with INST. VESSEL
crane and slowly transfer the weight
to the winch.
Platform team
Crane operator
Superintendent
0062671-14
21.
Disconnect INST. VESSEL crane
rigging and secure it on the deck.
Platform team
Superintendent
Crane operator
0062671-14


USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 41/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
10.6. Task plan n5: Riser Installation on USARI FA Platform

Status:
o INST. VESSEL close to platform
o Riser hanged on winch installed on platform
o Riser clamps on the platform in open position
o Riser rigging disconnected from crane
o INST. VESSEL crane released

RISER INSTALLATION
Step
n
Sequence Responsible Drawings
1.
Slowly position the riser into hanger
clamp. The hanger flange should
remain about 1m over the top of
clamp.
Platform riggers 0062671-14
2.
Riggers to close hanger clamp and
keep the clamp loose tighten.
Platform riggers 0062671-14
3.
Rigger to install flat slings around top
of riser for rotation
Platform riggers

0062671-14
4.
Start rotation of riser.
Continue rotation until the marking of
the riser is aligned with the marking of
the clamp.
Stop rotation.
Platform riggers 0062671-14
5.
Once rotation is completed, lower
riser with winch until the hanger
flange sits on permanent support of
hanger clamp.
Platform riggers 0062671-14
6.
Diver to report measurement of riser
flange location and elevation.
Diver
Diving Supervisor
0062671-14
7.
Confirmation of the orientation by
transponder data
Survey 0062671-14
8.
Approval of riser configuration
(position, elevation and orientation).
Superintendent 0062671-14
9.
Platform rigger to tighten the bolts of
the hanger clamp using torque or
impact.
Platform rigger to respect tighten
torque indicated in Appendix B.
Platform riggers 0062671-14
10.
The diver will use Tirfor (suitable size)
as well as come alongs (suitable
size) to pull the riser into the clamp.
Diving Supervisor 0062671-14
11.
Diver to close the subsea clamp
around.
If required adjust position of subsea
clamp on bracing.
Diver 0062671-14

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 42/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
RISER INSTALLATION
Step
n
Sequence Responsible Drawings
12.
Diver to tighten the bolts of the
subsea clamp using torque or impact.
Diver to respect tighten torque
indicated in Appendix B.
Diver 0062671-14
13. Diver to perform visual inspection. Diver 0062671-14
14.
Release tension from winch.
Diver to disconnect slings from riser
and recover rigging.
Platform riggers
Diver
0062671-14
15.
Ensure accessibility of on riser top
flange (by scaffolding if necessary)
for pre-commissioning
Platform riggers 0062671-14


USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 43/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
10.7. Task plan n6: Riser Guard Installation on USARI FA Platform

NOTE: Riser guard installation is eased when low tide as crane operator has both stabbing guides
in sight.

RISER GUARD INSTALLATION
Step
n
Sequence Responsible Drawings
PREPARATION ACTIVITIES
1.
INST. VESSEL permit to work in place in
accordance with the USARI FA platform
PTW system.
Superintendent
Safety officer
Client
/
2.

ALL /
3.
All Rigging used is certified and checked.
Welding spread checked (to weld the
riser guard to the jacket)
Deck Foreman
0062671-12

Welding procedure
4.
Transfer of personnel and material on
the platform including cutting / grinding /
welding equipment / rigging for securing
the riser guard in final position (chain
blocks 3T, tirfors) to the platform.
Deck Foreman /
5.
On USARI FA platform, prepare the
scaffolding on both location for upper
bracing installation and welding
Scaffolder
Assistant
/
6.
Welding of doubler plates for both upper
bracing
Deck Foreman
Engineers
/
7.
On USARI FA platform, verify the riser
guard location, remove any obstruction
that can prevent the installation.
Deck Foreman
Engineers
/
8.
On the USARI FA platform, confirm that
the pre-installed winch is fully
operational.
Deck Forman
Engineers
/
Deck crew, and all personnel
involved in the operations are
informed about the job to
perform including diving
subcontractor. TBT and job
safety analysis is performed
prior the operation start.

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 44/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.

RISER GUARD INSTALLATION
Step
n
Sequence Responsible Drawings
SUBSEA CLAMPS INSTALLATION
1.


Diver Supervisor
Superintendent
/
2.
Diver to perform visual inspection to
localize subsea clamp areas.
Diver
Diving supervisor
0062671-05
3.
Superintendent and Diver supervisor to
confirm the location
Diving supervisor
Superintendent
/
4.
Diver to mark position of clamps by
measurement.
Area of cleaning can be delimited by
rope.
Diver /
5. Diver to clean area according to drawing. Diver 0062671-05
6.
Once cleaning operation is completed,
redo marking of clamp location.
Diver /
7. Diver to perform visual inspection. Diver /
8.
Deck team to prepare clamp in
configuration for lifting.
The clamps will be tied open.

Install the lifting rigging and tag lines
according to drawing.
Deck lifting trial for rigging adjustment.
Adjust by means of chain hoist.
Diving superintendent or his team to view
and accept prior to leaving the deck.
Riggers
Deck Foreman
Diver superintendent
Diver
0062671-12
Safety note:
Ensure that before any
diving activities, the
scaffolding work will
stop. The existing
scaffolding will be
checked to ensure it is
secured.

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 45/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
RISER GUARD INSTALLATION
Step
n
Sequence Responsible Drawings
9.
Confirm that the air diving team is ready
to assist the riser guard installation
especially to guide the riser guard during
final setting on pre-installed guide
clamps.
Diving Team /
10. Clamp overboarding.
Crane operator
Deck Foreman
0062671-15
11.
Lowering clamp into water
Load transfer of clamp to winch with
clamp into water.


Crane operator
Deck Foreman
Platform riggers
0062671-15
12.
Diver to position clamp on the bracing in
final position and secured it
Diver 0062671-15
13. Diver to cut rope to close the clamps. Diver 0062671-15
14.
Diver to check batter angle of stabbing
guides
Diver /
15.
Clamps to be tighten using torque or
impact.
Diver to respect tighten torque indicated
in Appendix B
Diver Appendix B
16.
Recovering of clamp rigging.
Diver to disconnect rigging from clamp
Diver
Platform riggers
/
17.
Diver to perform visual inspection and
metrology
Datasheet to fill
Diver Appendix F
RISER GUARD INSTALLATION
1.
All persons involved must be familiar with
the present procedure. Ensure that INST.
VESSEL permit to work, USARI FA
platform permit to work, dive permit and
JSA have been completed and correct
PPE is utilized.
Superintendent
Safety Officer
Diving Supervisor
/
2.

ALL /
Deck crew, and all personnel
involved in the operations are
informed about the job to
perform including diving
subcontractor. TBT and job
safety analysis is performed
prior the operation start.

Safety note:
No diver into water


USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 46/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
RISER GUARD INSTALLATION
Step
n
Sequence Responsible Drawings
3.
Personnel are transferred on USARI FA
platform.
Deck Foreman
Master
/
4.
Perform a full radio communications
check with all parties involved with the
operation. bridge, platform team with
winch operator, dive control or
mobile/portable surface supplied system,
crane operator. VHF hand held radios to
be used with dedicated operating
channel allocated.
ALL /
5.
On the USARI FA platform, the winch
cable is routed through the snatch blocks
according to the layout and preparation
works.
Deck Foreman
Riggers team
0062671-04
6.
INST. VESSEL main crane is connected
on the riser guard rigging, and the riser
guard is over boarded and positioned
close (+/- 3m) to the platform for the
transfer to the winch by zodiac.


Deck Foreman
Crane Operator
0062671-15
7.
Winch end to be lower at sea level
Riser guard rigging connection to winch
end
Riggers
Zodiac
Crane op
0062671-15
8.
Riser guard is lifted up out of water
Load transfer to winch


Riggers
Winch op
0062671-15
9.
Riser guard to be lowered into water
Disconnection of crane grommet by
zodiac
Recover the Crane
Riggers
Winch op
Zodiac
0062671-15
10.
Riser guard is lowered about 1m above
guide




Riggers
Winch op

ALL
0062671-15
NOTE: Pay attention to
subsea guide out of water
during load transfer
Safety note:
No diver into water

Ensure good
communication is
required between
winch operator and
riggers foreman,
divers, INST. VESSEL
management team

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 47/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
RISER GUARD INSTALLATION
Step
n
Sequence Responsible Drawings


11.
Chain hoist is connected to platform to
pull the riser guard to move the riser
guard over the guide
Riggers
Winch op
0062671-15
12.
Lower the riser guard with the winch
Rigger to guide the riser guard for
entering the 1st pin
Riggers
Winch op
0062671-15
13.
Continuing lowering riser guard
Rigger to continue guiding the riser guard
for entering the 2
nd
pin.
Diver to monitor if necessary
Riggers
Winch op
Diver
0062671-15
14.
Finish lowering the riser guard until it
bumps into the flange.
Riser guard to be secured by hold back
rigging.
Riggers
Winch op
0062671-15
15.
Divers to confirm that the riser guard is
properly set on the stabbing pins. Divers
to check if the stabbing guide has not
moved during riser guard final set down.
A Video Survey on each Clamp is
performed, if visibility allows it.
Divers remove the Riser Guard Rigging.
Diver 0062671-15
16.
Once in position, ensure riser guard is
correctly secured. Install hold back
rigging and disconnect winch if required
Rigger
Crane op
0062671-15
17.
Rigger to take metrology on upper
bracing (leg side)
Deck foreman 0062671-15
18.
Welder to adjust upper bracing (leg side)
according to metrology
Welder foreman
Welder
0062671-15
19.
Rigger to position upper bracing to riser
guard flanges
Welder to weld them to the leg
Rigger
Welder foreman
Welder
Welding Procedure
20.
Rigger to clamp the upper sliding bracing
(bracing side) on the riser guard
Deck foreman 0062671-15
21.
Welder to adjust the upper sliding
bracing (bracing side) to the bracing and
secure it
Welder foreman
Welder
0062671-15
22.
Perform MPI / UT Test in accordance
with the NDT procedure.
QAQC NDT Procedure

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 48/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
RISER GUARD INSTALLATION
Step
n
Sequence Responsible Drawings
23. Disconnection of hold back/winch rigging Rigger 0062671-14
24. Paint touch up at welding location Painting /
25. Remove installation aids from platform Riggers 0062671-14



USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 49/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
10.8. Task plan n7: Topside Spool Removal & Installation on USARI FA
platform

Status:
o Gauging and hydrotest from top of riser to top of riser performed and accepted by
COMPANY for topside spool installation.

Prior to the existing topside spool removal, existing 24 USARI FA-FR line shall
be deoiled and depressurized. Certificates shall be issued to SAIPEM.

For topside spool installation and removal, Asabo Usari 20in Topside spool
shall not be installed.

TOPSIDE SPOOL REMOVAL & INSTALLATION
Step n Sequence Responsible Drawings
TOPSIDE SPOOL REMOVAL
1.
Erection of scaffolding at existing
topside spool area (flanges and topside
spool support)

NOTE: For scaffolding erection, pay
attention to topside spool
removal/installation operation for any
clash
Platform rigger /
2.
Rigger to connect hold back rigging
and rigging on the topside spool
Riggers
Deck foreman
0062671-14
3.
Rigger to connect winch cable to the
rigging & to maintain in tension the
winch cable to secure the topside spool
Riggers
Deck foreman
Winch Operator
0062671-14
4.
Riggers to cut the topside spool
between the 2 clamps, in the straight
part.



Deck Foreman 0062671-14

Safety note:
Potential motion of
riser after cutting

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 50/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
TOPSIDE SPOOL REMOVAL & INSTALLATION
Step n Sequence Responsible Drawings
TOPSIDE SPOOL REMOVAL
5.
Riggers to remove bolts of the spool
from the flange valve using Flogging
Spanner/nut Splitter/Impact




Deck Foreman /
6.
Slackening & release of the hold back
rigging from spool until weight is totally
sustained by winch
Rigger to guide the spool to avoid clash
with platform
Riggers
Deck foreman
/
7.
Lower the spool to the sea level
Riggers or zodiac to connect crane
whip hook to the dedicated grommet of
the spool rigging
Winch Operator
Deck Foreman
/
8.
Load transfer from winch to vessel
crane hook until weight is fully
sustained by the vessel crane.
Crane operator
Winch operator
/
9. Zodiac to disconnect winch cable
Crane operator
Winch operator
Zodiac
/
10. Recovery on deck
Deck foreman
Crane operator
/
11.
Temporary plug to install on top of
existing riser at cut location
Deck foreman
Riggers
/
Safety note:
Potential motion of riser
after disconnection

USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 51/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.

TOPSIDE SPOOL INSTALLATION
1.
Ensure erection of scaffolding at new
topside spool area (flanges and topside
spool support)
Platform rigger /
2.
Laser metrology between valve flange
and top of riser.
Platform rigger
NG00-SA-NDZZZ-
0062646
3.
Final spool construction according to
metrology received
Pay attention to hole alignment
Welder foreman
NG00-SA-NDZZZ-
0062677
4.
Ensure spool hydrotest performed as
per pre-commissioning procedure.
Deck Foreman
QAQC
Pre-commissioning
procedure
5.
Riggers to install hold back rigging
arrangement on platform (flat round
sling, tirfor or beam clamp if required).
Platform rigger /
6.
Riggers on deck to prepare rigging of
topside spool.
Deck Foreman 0062671-13
7.
Topside spool lifting by crane,
overboarding, lowering into water and
connection to winch at sea level.
Deck Foreman
Crane operator
0062671-16
8. Connection of hold back rigging
Platform rigger
Zodiac
0062671-16
9.
Load transfer to winch at required
location and level to avoid any clash
Deck Foreman
Crane operator
0062671-16
10.
Slowly transfer spool to rigging
arrangement on platform.
Keep winch connected and in tension
for 1rst steps
Platform rigger 0062671-16
11.
Rigger to position topside spool in final
location by tirfors.
Platform rigger 0062671-16
12.
Torque/tightening of topside spool
Platform rigger to respect tighten value
indicated in Appendix B.
Platform rigger
Appendix B
NG00-SA-OPZZZ-
0058520
13. Welding of topside spool support Welding Foreman
NG00-SA-NDZZZ-
0062658
NG00-SA-KPWLD-
0058621
14. Paint touch up at support location Painting /
15.
Insulation test to be conducted
according to supplier procedure
Assistant
Installation Eng.
/


USARI IDOHO PIPELINES REPLACEMENT PROJECT
26/06/12
RISER INSTALLATION PROCEDURE at FA
REVISION : REV 1
F10190-SAI-FAFR-OPS-PRO-0062671
NG00-SA-OPZZZ-0062671
PAGE: 52/ 198


RESTRICTED INFORMATION: May not be copied or distributed without SPECIFIC AUTHORIZATION.
Warning: This document as printed may not be the latest version. Please refer to the electronic file in the EDMS.
10.9. Task plan n8: Remaining Activities on USARI FA Platform

REMAINING ACTIVITIIES ON USARI FA PLATFORM
Step
n
Sequence Responsible Drawings
1.
Remove winch, horizontal pipe on
helideck, lifting arrangement, welding
and scaffolding equipment off
platform
Clean-up platform.
Platform rigger
Superintendent
/
2. Touch up at required location Painting /
3.
Redo grating, net and deck which
could have been removed for
installation.
Platform rigger
Superintendent
/