MCC CAR PARK

Logic diagram
Paving - kerbs &
concrete

Road marking

Floor paint

Asphalt

Painting to ground
floor columns

Handover ground
floor

MEP works on
column

Remove Roof beam


props

Painting final
coat
MEP high level
works for
ground floor

Painting to ceiling
soffit (mist coat)

1st floor Hollow core


slab

Paving -kerbs
& concrete

Grouting

Parapet wall
concrete

Paving - kerbs
& concrete

1st floor
concrete

PU floor paint (28 days


after screed)

Floor screed

Floor screed

Handover 1st
floor

PU floor paint (28days


after screed)
Handover
project

Chemical anchor
bolt

Structural steel
erection

1st floor metal


decking

1st floor soffit


painting

Grouting

Paving- kerbs &


concrete

Painting final coat

2nd floor
concrete

MEP works on
columns/wall

1st floor column


painting

Roof hollow
core slab

2nd floor metal


decking

Paving- kerbs &


concrete

PU floor paint (28


days after screed)

MEP high level works


for 1st floor

Floor screed

Pre-cast external
wall cladding

PU floor paint (28 days


after screed)

Ground floor works DOHI scope

Ground floor works Sub-contract

1st floor works DOHI scope

Roof works DOHI scope

Roof works Sub-contract

Structural steel sub-contract

Logic between 2 activities is not Finish to Start.

Handover roof

1st floor works Sub-contract