Design, operation and maintenance of the GIS installations including procedures for fault
attending (at contractor works) for 3 man-weeks.
The contractor shall also provide training in the area of testing, commissioning and
maintenance for atleast 5 personnel for 5 days at one of the GIS Substations.
Design, operation, maintenance and commissioning aspect for 5
(Five) persons at
3 days
3 days
PLCC
2 days
The Contractor shall provide auxiliary system (like battery, AC/DC feeders etc) for future bays
also as per single line diagram in addition to bays under present scope.
7.3
As 400 kV, 220kV, 132kV GIS is likely be extended in future, the contractor shall make
available during detailed engineering and document Hand -Over stage, all details such as cross
section, gas pressure etc. required for designing in future for extension of GIS.
7.4
Construction Power and Water: These shall be arranged by the contractor. However in case
the Owner is in a position to provide the same at a later date, the charges for the same shall be
intimated and if acceptable to contractor , these could be availed. It may be noted that reliability
of power and water would not be ensured by the Owner and in no case be held responsible for
any delay in works because of non-availability of power and water.
7.5
The contractor shall be responsible for safety of human and equipment during the working. It
will be the responsibility of the Contractor to co-ordinate and obtain Electrical Inspector's
clearance before commissioning. Any additional items, modification due to observation of such
statutory authorities shall be provided by the Contractor at no extra cost to the Owner.