5 Pdfsam Planning & Scheduling
5 Pdfsam Planning & Scheduling
93
PROJECT
BUILDINGS
TANKS
Project Manager
CTRL ROOM
POWERHOUSE
TURBO GEN.
PIPING
AUXILIARIES
Prj engineer
Procur mng
worker
Fig. 8.5 Example of WBS/OBS allocation matrix for a power station construction project
with a specified number of resources and related estimated work load required to
perform the task.
Figure 8.5 is a simplified depiction of how a WBS and OBS correlate. It is imperative during the monitoring and controlling phase of the construction project that
there is a responsible person for each activity.
To summarize the planning process thus far, we have created the WBS and have
now incorporated a responsible committee or person to each element of the WBS. In
essence, from activities developed in the WBS we have allocated resources through
the OBS.