Professional Documents
Culture Documents
Item Description
Unit
Quantity
Rate per unit
Total Amount
Process of preparation of BOQ for RCC
Description:
In this step, the appropriate narrative of a particular work is provided to explain and justify the
work being done.
Working Up:
This step includes recording every measurement required into a sheet called the TDS Sheet.
The times column (multiplier column) is for filling up the number of repetitions of the same work.
It depicts the factor of multiplication. Dimension column is the one where all the dimensions like
length, width & depth are recorded. Whereas in the Sums column we simply multiply the
previous elements (Multiplication factor x Dimension) to get the total quantity of the work.
Calculation of materials for Reinforced Concrete Construction
Materials requires for reinforced concrete are cement, sand, coarse aggregate and steel. Let us
assume a standard quantity of 1m3 Cement mortar and a mix proportion of 1:1.5:3 (1-part
Cement, 1.5 parts Sand & 3 parts CA). The quantity can preferable calculated by two methods,
which are weight & volume method.
Let us consider the volume method for reinforced concrete construction. Dry volume of total
materials is equivalent to 1.54 times the volume of wet concrete. Hence let us take the quantity
of cement mortar as 1.54 m3.
Quantity of cement
The formula to calculate the volume of cement is as follows:
(1.54×1)/(1+1.5+3)=0.28 m^3
Since the cement is available in bags, volume of 1 cement bag is 0.0347 m3.
0.28/0.0347=8.07 bags of cement
Quantity of sand
Formula to calculate volume of sand is as follows:
(1.5×1.54)/(1+1.5+3)=0.42 m^(3 ) of sand
Quantity of Coarse aggregates
To calculate volume of CA is as follows:
(3×1.54)/(1+1.5+3)=0.84 m^(3 ) of CA
BOQ of Steel reinforcement
Percentage of steel reinforcement usually depends on the type of components used. The values
of percentage of steel differ from structure to structure. Some of which are mentioned below:
Slabs = 1.0% of concrete volume
Beam = 2 % concrete volume
Column = 2.5% of concrete volume
RCC roads = 0.6% concrete volume
Assuming 2.5% as the steel reinforcement required, the formula to calculate steel is:
2.5/(100×1)×7850=196.25 kg
Estimation of labour for reinforced concrete
The requirement for labour as per the specified quantity of work is as follows: