You are on page 1of 1

PORT OF : Savona

DATE
:
September 1996

M/T VENETIA
ANDROS 569

DURING CRUDE OIL WASHING OPERATION CHECK LIST


1.

Is quality of I.G. delivered frequently checked and


recorded ?

___________

Are all deck lines and machines frequently checked


for leaks ?

___________

3.

Is C.O.W. in progress in designated tanks only ?

___________

4.

Is Pressure in the tank wash line as specified ?

___________

5.

Are the cycle times of the tank washing machines as


specified ?

___________

2.

6.

Are the washing machines in operation , together with


their drive units, if applicable, frequently checked
and working properly ?
___________

7.

Is a responsible person stationed continuously on


deck ?

___________

Will the trim be satisfactory when bottom washing is


in progress as specified ?

___________

9.

Will recommended tank draining method be followed ?

___________

10.

Have Ullage gauge floats been raised and housed in


tanks been Crude oil washed ?

____N/A____

Is the level in holding tank for tank washing


frequently checked to prevent any possibility of
overflow ?

___________

8.

11.

Time _______________________________
Completed By __Konstantinos Motzakis___
Chief Officer