You are on page 1of 56

Paper No.

502

DEVELOPMENT OF PAVEMENT MANAGEMENT


SYSTEM FOR INDIAN NATIONAL HIGHWAY
NETWORK
By
SANJIV AGGARWAL*, PROF. (DR.) S.S. J AIN** & DR. M. P ARIDA***
CONTENTS
Page
1.
2.
3.
4.
5.

Introduction
Research Survey
Identification of National Highway Network
Data Acquisition and Database
Calibration and Validation of HDM-4 Pavement
Performance Prediction Models
Pavement Management at Project Level
Pavement Management at Network Level
Applications of the Study
Conclusions

6.
7.
8.
9.

...
...
...
...
...

...
...
...
...
...

272
273
274
276
289

...
...
...
...

...
...
...
...

290
305
323
324

SYNOPSIS
The objective of the study is to develop a Pavement Management System (PMS)
for an identified National Highway Network to assist the highway engineers responsible
for maintaining the highway network as well as the authorities responsible for allocating
funds, in making consistent and cost effective decisions, related to maintenance and
rehabilitation of pavements. This requires development of a systematic procedure that
would predict the most economical maintenance strategy for a particular pavement section
and prioritization of such maintenance activities in the event of a constrained budget.
The HDM-4 is a new international standard assisting pavement managers to predict
future economic, technical, social and environmental outcome of possible investment

Written comments an this Paper are invited and will be received upto 31st December
2004.
* Assistant Professor, Department of Civil Engineering, GZS College of Engineering,
Bhatinda 151001 (Punjab)
** Professor & Coordinator, Centre of Transportation Engineering, Transportation
Engineering Section, Department of Civil Engineering, Indian Institute of Technology,
Roorkee 247667 (Uttaranchal)
*** Associate Professor, Transportation Engineering Section, Department of Civil
Engineering, Indian Institute of Technology, Roorkee 247667 (Uttaranchal)

272

AGGARWAL, PROF. JAIN & DR. PARIDA ON

decisions concerning maintenance management of pavements. The pavement deterioration


models incorporated in HDM-4 have been calibrated to adapt to local conditions and
suitable calibration factors have been determined. These calibrated models have also
been validated by comparing the values of distresses predicted by the HDM-4 model
with those actually observed in the field. In the present study, different aspects of project
level PMS have been demonstrated through four different case studies by making use of
Project Analysis application of HDM-4. Since the size of the highway network is not
very large and the analysis period is of medium duration, the Programme Analysis
application of HDM-4 has been used for the network level pavement management
analysis.
1. INTRODUCTION

1.1. Background
Road Transportation occupies a very dominant position in the overall
transportation system of India. The growth of road traffic in the post
independence era has been quite unprecedented both in terms of goods
and passenger traffic. The vehicular traffic has increased from 3 lakh to 430
lakh during the period 1951-2001. But unfortunately, the corresponding growth
in the road network has not been commensurate with the huge growth in vehicular
population, which has increased from 4-lakh km to 33-lakh km during the same
period. The traffic loadings have also been much heavier than the specified
limit of 10.2 tonnes. Without adequate and timely maintenance, roads deteriorate
excessively, leading to higher vehicle operating costs, increased number of
accidents and reduced reliability of transport services.
Thus, there is a need of developing a scientific approach towards
determining the maintenance and rehabilitation requirements of pavements.
Efforts are also needed to develop road management and planning tools to
improve upon the existing highway network. These tools are essential for
assessing the financial needs, evaluating the alternative maintenance strategies
and prioritizing the work programs. In such a situation, development and practice
of an efficient Pavement Management System (PMS) would provide objective
information and useful analysis to ensure consistent, and cost-effective decisions
related to preservation of the highway networks.
1.2. Objectives and Scope of Study
The objective of the study is to develop a PMS for an identified national
highway network. The scope of work encompasses the following:

Comprehensive review of research literature on development of


pavement management system in India and different parts of the
world.

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

273

Study and use of World Banks highway project appraisal model


HDM-4.
Development of a time series database consisting of pavement
condition data, traffic data and other necessary data on the selected
highway network to provide necessary inputs for executing the
HDM-4 model.
Collection of other data such as road user cost data and costs of
different types of maintenance activities and defining the intervention
levels for maintenance activities.
To calibrate the pavement deterioration models of HDM-4 using
the collected data from the identified highway network.
To validate the models using the data collected from the field.
To develop the PMS methodology at Project/Network level.
2. RESEARCH SURVEY

2.1. Pavement Management System


PMS is a coordinated and systematic process for carrying out all activities
related to providing and maintaining pavements. The primary goal of the PMS
is to predict the pavement condition and the cost associated with its maintenance
and rehabilitation over a given time frame, and aid in the planning and
programming of works. With a properly developed and implemented PMS, it is
possible to make good, well informed, and consistent decisions on maintenance,
rehabilitation or reconstruction of pavements. Pavement management systems
can assist the engineer in identifying the most appropriate treatment on selected
sections of the road network through the use of economic analysis, predictive
models and time-series information. The pavement management can be taken
up at two levels: network level and project level.
2.2. Pavement Management Levels
Pavement management must be capable of being used in whole or in part
by various technical and administrative levels of management in making
decisions regarding both individual projects and an entire highway network.
All functions are essential, but not all functions need to be active at same time.
Mostly a PMS works at two separate levels, network and project level, though
a hard dividing line between the two is difficult to draw. For the most part, the
same type of data is needed for both types of activities but more detail is
beneficial for project analysis.
The pavement management at the project level deals with detailed design
decisions, for an individual project. Project level work comes on stream at

274

AGGARWAL, PROF. JAIN & DR. PARIDA ON

the appropriate time in the schedule and incorporates detailed engineering


applications to address individual pavement sections and their specific problems.
Network level pavement management has its primary purpose of using
engineering applications to develop a priority program and schedule of
rehabilitation, maintenance or new pavement construction work, within overall
budget constraints. The network level of pavement management, as commonly
used, incorporates the project selection and program levels. The project selection
level involves prioritization to identify which projects should be carried out in
each year of the program period. At the program level, budgets are established
and general allocations made over an entire network.
2.3. Highway Development and Management System (HDM-4)
The Highway Development and Management system (HDM-4) is a new
international standard assisting pavement managers to predict future economic,
technical, social and environmental outcome of possible investment decisions
concerning maintenance management of pavements. The HDM-4 system assists
pavement managers in making effective investment choice at all management
levels. The possibilities range from policy or strategic planning studies, through
programmed allocation of funds to maintenance or improvement works on a
network, to the detailed economic assessment of investment options at the project
level.
The project level pavement management analysis for a highway network
can be accomplished by using the Project Analysis application module of
HDM-4, whereas the network level pavement management analysis can be done
using the Programme Analysis and Strategy Analysis application modules
of HDM-4, depending upon the size of the highway network involved in the
analysis and the length of analysis period. For a smaller highway network and
shorter duration of analysis, Programme Analysis is usually preferred, whereas
for a larger highway network and for a long term strategic planning, Strategy
Analysis is more useful. In the present study, since the size of the highway
network is not very large and the analysis period is of medium duration,
Programme Analysis application has been used for the network level pavement
management.
3. IDENTIFICATION OF NATIONAL HIGHWAY NETWORK

3.1. General
The first step in establishing a PMS is to identify the highway network
for which the pavement management system needs to be developed. In the

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

275

present study, a sub-network of the 65,000 km strong National Highway


Network of India has been identified for the purpose of development of
Pavement Management System for the same. The selected highway network,
consisting of total road length of 310 km, comprises of a number of segments
of the five National Highways, as shown in Table 1. The selected segments are
confined within the administrative boundaries of Dehradun and Haridwar
districts of Uttaranchal State, and Saharanpur and Muzzafarnagar districts of
the State of Uttar Pradesh. The layout of this national highway network is
shown in Fig. 1.
TABLE 1. SELECTED N ATIONAL HIGHWAYS
Sl.
No.

National Highway
No.

Description

1.

NH-58

Delhi Meerut Roorkee - Haridwar Badrinath


Marg

2.

NH-72

Ambala - Paonta Sahib Dehradun - Rishikesh Marg

3.

NH-72A

Chutmalpur Biharigarh Mohand - Dehradun Marg

4.

NH-73

Roorkee Saharanpur Yamunanagar - Panchkula


Marg

5.

NH-74

Haridwar Najibabad Bareilly Marg

Himachal Pradesh

Uttaranchal

Haryana

Uttar Pradesh

Fig. 1. Layout of the Selected National Highway Network

276

AGGARWAL, PROF. JAIN & DR. PARIDA ON

3.2. Division of Highway Network into Pavement Sections


The above highway network has been divided into 22 manageable
pavement sections on the basis of various characteristics associated with them.
Division of highway network into sections has been done on the basis of
homogeneity with respect to: traffic volume, pavement type & thickness, and
pavement condition characteristics. The selected pavement sections are quite
homogonous within themselves but vary considerably from each other in traffic,
pavement, geometric and climatic characteristics. All pavement sections vary
widely in terms of traffic and pavement characteristics. Although the geometric
characteristics are almost similar for most of the pavement sections but these
vary considerably for some of the sections situated in the hilly areas. The climatic
conditions also vary in respect of the pavement sections situated in the plains
and the hilly regions. All the selected pavement sections have been assigned a
unique Section ID and a Section Name for their easy identification on the
highway network, as shown in Table 2.
4. DATA ACQUISITION AND DATABASE

4.1. General
It is extremely important to collect all the pavement-related information
for their effective management. Because of the sheer size of the highway network,
the study has generated a huge amount of data. While collecting data it was
aimed that the collected data, directly or in its derived form should meet the
requirements of HDM-4 system. The process of data collection was classified
under following four categories:
(i)
(ii)
(iii)
(iv)

Road Network Data


Vehicle Fleet Data
Maintenance and Rehabilitation Works Data
Cost Data

4.2. Road Network Data


The road network data collection was carried out based upon the data
requirements of HDM-4, and it consisted of obtaining secondary data from the
past records and relevant government publications, and collecting current data
from the selected pavement sections by carrying out field studies. The road
network data includes the locational data that describes the position and geometry
of the pavement section, and the attribute data, which describes the road
characteristics or inventory associated with it.

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

277

The road network data collection in the field was divided under the
following heads:
(i)
(ii)
(iii)
(iv)

Inventory data
Structural evaluation (Structural capacity)
Functional evaluation (Pavement condition and riding quality)
Evaluation of pavement material
TABLE 2. SELECTED PAVEMENT SECTIONS

Sl. Section ID
no.

Section Name

Section Description

1.

NH-5801

NH-58 [km 130-141]

Muzzafarnagar - Chhapaar

2.

NH-5802

NH-58 [km 141-153]

Chhapaar Burahedi

3.

NH-5803

NH-58 [km 153-173]

Burahedi - Roorkee

4.

NH-5804

NH-58 [km 173-192]

Roorkee Bahadrabad

5.

NH-5805

NH-58 [km 192-204]

Bahadrabad - Haridwar

6.

NH-5806

NH-58 [km 204-218]

Haridwar - Satyanarayan

7.

NH-5807

NH-58 [km 218-228]

Satyanarayan - Rishikesh

8.

NH-7201

NH-72 [km 105-118]

Paontasahib - Herbertpur

9.

NH-7202

NH-72 [km 118-132]

Herbertpur - Selaqui

10.

NH-7203

NH-72 [km 132-148]

Selaqui IMA Dehradun

11.

NH-7204

NH-72 [km 162-180]

Rispan Bridge Dehradun Bhaniyawala

12.

NH-7205

NH-72 [km 180-197]

Bhaniyawala - Satyanarayan

13.

NH-72A1

NH-72A [km 0-11]

Chutmalpur - Biharigarh

14.

NH-72A2

NH-72A [km 11-22]

Biharigarh - Mohand

15.

NH-72A3

NH-72A [km 22-33]

Mohand - Datkali

16.

NH-72A4

NH-72A [km 33-43]

Datkali - Dehradun

17.

NH-7301

NH-73 [km 0-11]

Roorkee - Karaundi

18.

NH-7302

NH-73 [km 11-25]

Karaundi - Chutmalpur

19.

NH-7303

NH-73 [km 25-35]

Chutmalpur - Gagalheri

20.

NH-7304

NH-73 [km 35-47]

Gagalheri - Saharanpur

21.

NH-7401

NH-74 [km 0-13]

Haridwar - Shyampur

22.

NH-7402

NH-74 [km 13-30]

Shyampur Chiriapur

278

AGGARWAL, PROF. JAIN & DR. PARIDA ON

4.2.1. Road network elements: In order to customize HDM-4 for use in


the study area, the following road network elements were defined:

Road class All the pavement sections included in the selected


highway network belong to the National Highway class of road as
per functional hierarchy.

Referencing system - The Kilometre-Node referencing system has


been used for the locational positioning of data pertaining to pavement
sections. Kilometre stones have been used as nodes for signaling the
beginning and end of a pavement section.

Section identification - Each pavement section has been assigned a


unique name and ID, as shown in the Table 2 above, either of which
may be used to identify the section on the highway network. The section
description includes names of places at the beginning and end of each
section. The section ID also includes the reference to the road class
(NH) and road designation number (58, 72, 73 etc.), for easy
identification of the sections.

Basis of sectioning Fixed-length Sectioning has been used as the


basis for road network representation in HDM-4 so as to obtain
homogeneous pavement sections. This sectioning has been done on
the basis of uniformity of pavement condition characteristics and traffic
characteristics with in a particular pavement section.

Speed flow type The speed flow type on various pavement sections
varies from Single Lane Standard to Two Lane Standard, depending
upon the capacity and the width of the carriageway.

Traffic flow pattern - The traffic flow pattern in case of each pavement
section is defined as of the type Inter City, as per the temporal
distribution of traffic.

Climate zone Two climate zones namely North India Plains and
North India Hills have been defined depending upon the temperature
(mean annual temperature) and moisture (mean monthly precipitation)
characteristics of the areas in which the respective pavement sections
are situated.

Geometry class The geometry class of each pavement section


has been defined in terms of the various parameters reflecting the
horizontal and vertical curvature. Most of the sections are straight and
gently undulating except for a few, which are bendy and gently
undulating.

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

279

4.2.2. Inventory Data: The inventory data includes the following


details about the selected pavement sections: Name of road, category of
road, carriageway and shoulder width, drainage conditions, surface type
and thickness, pavement layer details etc. The same was collected from
visual inspection of the pavement sections, as well as from the construction
and maintenance records of the highway divisions in-charge of the maintenance
of the respective pavement sections.
4.2.3. Structural Evaluation: The magnitude of pavement rebound
deflection is an indicator of the ability of the pavement to withstand traffic
loading. Higher the rebound deflection, poor is the structural capacity and
performance. The practice hitherto is to use the Benkelman Beam deflection
method for evaluating the structural condition of the flexible pavement. The
deflection measurements were taken with Benkelman Beam as per the procedure
laid down in IRC:81 [19979].
4.2.4. Functional Evaluation: Functional evaluation of pavements
consists of collection of road data pertinent to surface distress (crack area,
raveled area, pothole area), rut depth, surface roughness etc. The type and extent
of distress developed at the surface i.e. cracking, raveling, patch work, potholes,
rut depth, edge break, etc. were observed, based on the visual condition survey.
The extent and type of distress developed in quantitative terms were also
measured, in addition to the visual recording of the pavement surface condition.
The information on shoulder type, width, and condition, and drainage etc. was
also recorded.

Measurement of crack area - A number of representative test


sections of length 50 m were chosen for cracking and raveling
measurements for each pavement section. The effected area was
marked in the form of rectangular figures. In case of single longitudinal
and transverse cracks, the crack length was measured and the effective
width of the crack was taken as 5 mm. Thus crack area was expressed
as percentage of total pavement area. Separate measurements were
taken for cracks of width up to 3 mm and width more than 3 mm (wide
cracks). It was observed that in majority of cases the percentage of
wide crack area was found to be approximately one-third of the total
crack area.

Measurement of ravelled area - Ravelling is the loss of material from


wearing surface. This distress type is associated with thin surfacing,
such as, surface dressing, seal coat and premix carpet. The affected
area was measured by taking into account area enclosed in regular
geometric shapes such as, rectangle, triangle etc. and then it was
expressed as percentage of total pavement area.

280

AGGARWAL, PROF. JAIN & DR. PARIDA ON

Measurement of pothole area - Potholes are bowl shaped holes of


varying sizes in a surface layer or extending into base/sub base course.
The pothole area is measured in terms of square metres and the depth
of each pothole is also measured to convert into volume of potholes.
The volume is then converted into number of standard pothole units of
one litre volume each. The pothole measurements are finally expressed
as number of pothole units per km length of the pavement section, as
stipulated in HDM-4 data requirements.

Rut depth measurements - The transverse deformation across the


wheel path is defined as the rut. The rut depth measurements were
taken with a 2 m straight edge, at all deflection points under the wheel
path i.e. at a distance of 0.9 m/0.6 m from the pavement edge in case
of double lane/single lane carriageway, and maximum value of rut depth
was noted down at each observation point.

4.2.5. Roughness measurements: The pavement roughness was


measured on each section with Fifth Wheel Bump Integrator, towed by the
mobile van, as per the standard procedure. The instrument was run at a constant
speed of 32 km/h. The observations were taken on the outer wheel paths in both
direction, at a distance of 0.9 m and 0.6 m from the edges in case of two lane
and single lane pavements respectively. The instrument was calibrated with
standard calibration equipment called Dipstick, before and after its use in the
field. The roughness values were obtained in terms of Unevenness Index, using
Equation 1.
UI = B/W * 460 * 25.4 mm/km

(... Eqn. 1)

Where
UI = Unevenness Index in mm/km
B = Bump Integrator reading
W = No. of wheel revolutions
The relationship given in Equation 2 has been used to convert the UI into
the universally acceptable International Roughness Index (IRI - measured in m/
km) [Odoki and Kerali, 200016].
UI = 630 x IRI1.12

(... Eqn. 2)

4.2.6. Skid resistance measurements: The skid resistance measurements


were taken using a Portable Skid Resistance Tester developed at TRRL. This
instrument is also known by the name British Pendulum Tester . The

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

281

characteristics of the instrument are such as to simulate the sliding conditions


between vehicles with patterned tyres, braking with locked wheels on wet
pavement surface at a speed of 50 km/h. The quantity measured with the portable
tester is termed as Skid Resistance Value (SRV). The SRV is converted to
Sideways Force Coefficient (SFC, measured with Sideways Coefficient
Routine Investigation Machine - SCRIM), using relationship given in Equation
3 [Kennedy et al, 199015].
SFC = 0.01 SRV

(... Eqn. 3)

4.2.7. Evaluation of Pavement Materials: The evaluation of pavement


materials of the existing pavement section was carried out in the field as well as
in the laboratory.

Field evaluation - Test pits of size approx. 0.5 m x 0.5 m were dug
up at suitable locations with in all pavement sections. The following
tests were conducted and observations taken in the pits: Thickness of
the most recent surfacing course and old surfacing courses, Thickness
of granular base and sub-base courses, Qualitative assessment of
the level of compaction of all layers, Field dry density and field
moisture content of sub grade. For characterization of materials in the
laboratory, representative subgrade soil samples were collected from
the test pits.

Laboratory evaluation - The detailed evaluation in the laboratory


was done on the soil samples in accordance with the Indian Standard
specifications. The following tests were carried out for each soil sample:
Atterbergs limits (Liquid limit and Plastic limit), Proctor density and
optimum moisture content, CBR (unsoaked and soaked at field
conditions)

4.3. Road Network Database


All road network data items, which are required to be specified for each
pavement section, are given in the Tables 3(a) to 3(d). All these data items
reside in the road network database created in HDM-4. This road network
database has been named as National Highway Network, for all future
references and uses.

Section
Name

NH-58 [km 130-141]

NH-58 [km 141-153]

NH-58 [km 153-173]

NH-58 [km 173-192]

NH-58 [km 192-204]

NH-58 [km 204-218]

NH-58 [km 218-228]

NH-72 [km 105-118]

NH-72 [km 118-132]

NH-72 [km 132-148]

NH-72 [km 162-180]

NH-72 [km 180-197]

NH-72A [km 0-11]

NH-72A [km 11-22]

NH-72A [km 22-33]

NH-72A [km 33-43]

NH-73 [km 0-11]

NH-73 [km 11-25]

NH-73 [km 25-35]

NH-73 [km 35-47]

NH-74 [km 0-13]

NH-74 [km 13-30]

Section
ID

NH-5801

NH-5802

NH-5803

NH-5804

NH-5805

NH-5806

NH-5807

NH-7201

NH-7202

NH-7203

NH-7204

NH-7205

NH-72A1

NH-72A2

NH-72A3

NH-72A4

NH-7301

NH-7302

NH-7303

NH-7304

NH-7401

NH-7402

Haridwar - Najibabad

Haridwar - Najibabad

Roorkee - Saharanpur

Roorkee - Saharanpur

Roorkee - Saharanpur

Roorkee - Saharanpur

Chutmalpur - Dehradun

Chutmalpur - Dehradun

Chutmalpur - Dehradun

Chutmalpur - Dehradun

Dehradun - Haridwar

Dehradun - Haridwar

Paonta Sahib - Dehradun

Paonta Sahib - Dehradun

Paonta Sahib - Dehradun

Roorkee - Rishikesh

Roorkee - Rishikesh

Roorkee - Rishikesh

Roorkee - Rishikesh

Muzzafarnagar - Roorkee

Muzzafarnagar - Roorkee

Muzzafarnagar - Roorkee

Link Name

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Traffic Flow
Pattern

Two Lane Narrow

Two Lane Narrow

Two Lane Standard

Two Lane Narrow

Two Lane Standard

Two Lane Standard

Two Lane Standard

Two Lane Narrow

Two Lane Narrow

Two Lane Standard

Two Lane Standard

Two Lane Standard

Two Lane Standard

Two Lane Standard

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Inter-city

Single Lane Standard Inter-city

Two Lane Standard

Two Lane Standard

Two Lane Standard

Two Lane Standard

Two Lane Standard

Two Lane Standard

Two Lane Standard

Speed Flow
Type

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Hills

North India - Hills

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

North India - Plains

Climate Zone

TABLE 3(a). H IGHWAY N ETWORK - BASIC D ATA

17

13

12

10

14

11

10

11

11

11

17

18

16

14

13

10

14

12

19

20

12

11

Section
Length
(km)

6.1

6.1

7.0

6.5

7.0

7.0

7.0

6.5

6.1

7.0

7.0

7.0

7.0

7.0

3.7

7.0

7.0

7.0

7.0

7.0

7.0

7.0

5,520

5,480

7,650

7,670

7,750

7,840

6,040

6,250

6,310

6,550

6,840

7,280

5,870

5,720

3,650

8,540

11,260

13,860

13,980

12,290

11,370

11,450

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

2002

Carriage- Motorized AADT


way
AADT
Year
Width
(m)

282
AGGARWAL, PROF. JAIN & DR. PARIDA ON

NH-58 [km 130-141]


NH-58 [km 141-153]
NH-58 [km 153-173]
NH-58 [km 173-192]
NH-58 [km 192-204]
NH-58 [km 204-218]
NH-58 [km 218-228]
NH-72 [km 105-118]
NH-72 [km 118-132]
NH-72 [km 132-148]
NH-72 [km 162-180]
NH-72 [km 180-197]
NH-72A [km 0-11]
NH-72A [km 11-22]
NH-72A [km 22-33]
NH-72A [km 33-43]
NH-73 [km 0-11]
NH-73 [km 11-25]
NH-73 [km 25-35]
NH-73 [km 35-47]
NH-74 [km 0-13]
NH-74 [km 13-30]

Section
Name

2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001
2001

Condition
Year

2.6
3.8
4.6
3.4
4.1
4.4
5.1
5.9
5.1
5.7
5.2
6.2
6.7
6.6
6.7
3.0
3.6
2.4
6.9
6.3
4.5
4.7

2
4
8
4
7
8
6
7
10
12
10
12
10
14
15
2
4
1
15
10
6
5

1
2
4
1
4
4
4
10
5
5
8
9
12
10
10
1
5
1
10
7
5
4

0
0
2
0
2
1
1
0
2
2
1
2
3
10
10
0
1
0
10
3
1
3

Rough- Cracking Ravelled Potholes


ness
Area
Area
(no./km)
IRI
(%)
(%)
(m/km)

0
0
2
0
2
1
2
12
5
5
5
5
5
5
5
0
2
2
4
4
5
3

1
3
5
3
3
6
6
5
8
6
10
9
20
20
5
3
7
2
8
7
7
6

Edge
Rut
Break Depth
(m 2/km) (mm)

TABLE 3(b). H IGHWAY NETWORK - C ONDITION DATA

0.7
0.7
0.5
0.7
0.5
0.5
0.5
2.0
0.5
0.5
0.5
0.5
0.5
0.6
0.6
0.7
0.6
0.7
0.5
0.5
0.5
0.5

0.50
0.50
0.40
0.50
0.40
0.50
0.40
0.50
0.40
0.40
0.40
0.40
0.50
0.50
0.50
0.50
0.60
0.60
0.40
0.40
0.45
0.45

Texture
Skid
Depth Resistance
(mm)
(SCRIM)

0.45
0.49
0.66
0.45
0.62
0.62
0.70
0.85
0.70
0.75
0.90
0.68
0.95
0.92
0.88
0.75
0.65
0.80
1.02
0.95
0.95
1.10

5.29
5.02
4.16
5.29
4.32
4.32
4.01
3.54
4.01
3.84
3.42
4.08
3.31
3.37
3.47
3.84
4.20
3.68
3.16
3.31
3.31
3.01

Benkel- Adjusted
man
structural
Beam Number of
deflec- pavements
tion mm
(SNP)

DEVELOPMENT
OF

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK
FOR INDIAN

283

Surfacing Material Type

NH-58 [km 130-141] Asphaltic Concrete (AC)


NH-58 [km 141-153] Asphaltic Concrete (AC)
NH-58 [km 153-173] Asphaltic Concrete (AC)
NH-58 [km 173-192] Double Bituminous Surface Dressing (DBSD)
NH-58 [km 192-204]
Double Bituminous Surface Dressing (DBSD)
NH-58 [km 204-218] Double Bituminous Surface Dressing (DBSD)
NH-58 [km 218-228] Double Bituminous Surface Dressing (DBSD)
NH-72 [km 105-118]
Single Bituminous Surface Dressing (SBSD)
NH-72 [km 118-132]
Asphaltic Concrete (AC)
NH-72 [km 132-148] Asphaltic Concrete (AC)
NH-72 [km 162-180] Double Bituminous Surface Dressing (DBSD)
NH-72 [km 180-197] Double Bituminous Surface Dressing (DBSD)
NH-72A [km 0-11]
Single Bituminous Surface Dressing (SBSD)
NH-72A [km 11-22]
Single Bituminous Surface Dressing (SBSD)
NH-72A [km 22-33]
Single Bituminous Surface Dressing (SBSD)
NH-72A [km 33-43]
Double Bituminous Surface Dressing (DBSD)
NH-73 [km 0-11]
Asphaltic Concrete (AC)
NH-73 [km 11-25]
Asphaltic Concrete (AC)
NH-73 [km 25-35]
Double Bituminous Surface Dressing (DBSD)
NH-73 [km 35-47]
Double Bituminous Surface Dressing (DBSD)
NH-74 [km 0-13]
Double Bituminous Surface Dressing (DBSD)
NH-74 [km 13-30]
Double Bituminous Surface Dressing (DBSD)

Section Name

40
40
40
25
25
25
25
15
25
25
25
25
15
15
15
25
25
25
25
25
25
25

100
100
100
100
100
100
100
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50

1994
1992
1992
1992
1992
1990
1990
1990
1992
1992
1990
1990
1992
1993
1992
1996
1992
1994
1992
1992
1992
1992

2000
1998
1998
1997
1997
1996
1996
1996
1997
1997
1995
1995
1992
1993
1992
1996
2000
2001
1992
1992
1992
1992

2000
1998
1998
2000
2000
1999
1998
1999
1997
1997
1999
1998
1997
1998
1997
2001
2000
2001
1997
1997
1999
1999

2000
1998
1998
2000
2000
1999
1998
1999
1997
1997
1999
1998
1997
1998
1997
2001
2000
2001
1997
1997
1999
1999

Current Previous
Last
Last
Last
Last
Surface
Surface Construc- Rehabili- Surfac- Preventive
Thickness Thickness
tion
tation
ing Treatment
(mm)
(mm)
Year
Year
Year
Year

TABLE 3(c). H IGHWAY NETWORK - PAVEMENT DATA

284
AGGARWAL, PROF. JAIN & DR. PARIDA ON

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

TABLE 3(d). LABORATORY T EST RESULTS


Section Name

Optimum
Moisture
Content
(%)

OF

285

SUBGRADE SOIL SAMPLES

Atterberg Limits
(%)
LL
PL
PI

24

FOR INDIAN

CBR
(%)
UnSoaked
soaked

NH-58 [km 130-141]

8.30

20

10.4

NH-58 [km 141-153]

8.55

21

15

9.8

7.3
6.9

NH-58 [km 153-173]

7.90

28

18

10

9.8

6.8

NH-58 [km 173-192]

9.10

20

15

9.6

6.8

NH-58 [km 192-204]

7.40

27

19

10.2

7.0

NH-58 [km 204-218]

8.45

22

15

8.7

6.3

NH-58 [km 218-228]

9.50

18

12

8.6

6.5

NH-72 [km 105-118]

7.70

20

16

9.5

6.8

NH-72 [km 118-132]

9.30

24

17

10.3

6.9

NH-72 [km 132-148]

8.50

20

15

10.6

7.2

NH-72 [km 162-180]

7.90

28

19

8.9

6.3

NH-72 [km 180-197]

8.70

22

15

9.6

6.9

NH-72A [km 0-11]

9.60

18

15

8.5

5.8

NH-72A [km 11-22]

8.50

17

12

8.3

5.9

NH-72A [km 22-33]

10.40

21

16

10.4

6.8

NH-72A [km 33-43]

9.30

18

14

9.7

6.3

NH-73 [km 0-11]

8.40

19

13

9.8

5.9

NH-73 [km 11-25]

8.60

17

11

11.3

7.4

NH-73 [km 25-35]

7.70

20

15

10.9

7.2

NH-73 [km 35-47]

7.30

19

14

8.8

5.8

NH-74 [km 0-13]

9.40

21

17

9.7

6.3

NH-74 [km 13-30]

9.80

20

16

9.5

6.2

4.4. Vehicle Fleet Data


4.4.1. Categories of Vehicles: A typical traffic stream on all categories
of roads in India, including National Highways comprise of both Motorized
(MT) as well Non-Motorized (NMT) vehicles. However, only MT vehicles have
been considered in this study, and NMT vehicles excluded, taking into account
the fact that NMT vehicles do not have appreciable effect on pavement
deterioration because of not carrying heavy loads.
4.4.2. Representative Vehicles: The choice of number of representative
vehicles is influenced by factors such as the composition of traffic, functional

286

AGGARWAL, PROF. JAIN & DR. PARIDA ON

differences between different type of vehicles, the objectives of the study, and
the availability and quality of data. A typical vehicle fleet in India may be
considered to be comprised of the following vehicles for the purpose of economic
analysis to be conducted in PMS. The same set of vehicles has also been
identified as representative vehicle fleet for Indian conditions, in the latest Road
User Cost Study [MORT&H 2001c19]:

Two Wheeler (TW)


Passenger Car (PC)
Bus (BUS)
Light Commercial Vehicle (LCV)
Medium Commercial Vehicles (MCV)
Heavy Commercial Vehicles (HCV)

4.4.3. Traffic Volume Counts: Traffic Counts were conducted manually,


for three consecutive days, round the clock, by engaging adequate number of
enumerators. A separate count station was established for each pavement section,
but if there were no traffic diversions in-between, one count station was
considered adequate for all such sections. The traffic volume survey included
classified traffic volume count. The vehicles were classified as per the
representative vehicles, identified in the previous section. The vehicles not
covered under the representative vehicles defined above were suitably clubbed
with the vehicles similar to them in composition and speed.
4.4.4. Composition of Traffic and Vehicle Growth Rate: Although
traffic volumes vary considerably on all pavement sections, but the composition
of the traffic in terms of the representative vehicles was found to be nearly the
same. The traffic volume composition adopted for this study is given in Table
4. The average annual growth rate of vehicles in India has been taken as per the
latest Road Development Plan [MORT&H, 2001b 18], and the same has also
been shown in Table 4. These traffic compositions and annual growth rates
have been assumed to be applicable to all pavement sections included in the
highway network under study.
TABLE 4. COMPOSITION
Vehicle Type
Two Wheelers
Passenger Cars
Light Commercial Vehicles
Medium Commercial Vehicles
Heavy Commercial Vehicles
Bus

AND

GROWTH RATE

OF

VEHICLES

Composition of
Traffic Flow (%)

Annual Average Growth


Rate (%)

22.0
30.0
13.0
17.0
10.0
8.0

7.5
8.7
8.5
8.5
8.5
7.4

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

287

4.5. Vehicle Fleet Database


The basic vehicle fleet data items, which are required to be specified for
each vehicle type. All these data items reside in the vehicle fleet database created
in HDM-4. This vehicle fleet database has been named as National Vehicle
Fleet, for all future references and uses.
4.6. Maintenance and Rehabilitation Works Data
4.6.1. Serviceability Levels for Maintenance: It is also notable that all
sections of the National Highways cannot be maintained to the highest level of
serviceability due to constraints of funds and may not be required to that level if
the traffic requirements of the highway do not justify it. Maintenance
serviceability level is a qualitative rating of the effectiveness of a highway in
terms of operating conditions such as traffic volume, speed, comfort and safety.
Accordingly, for maintenance purposes, it is proposed to divide the maintenance
programme into three maintenance levels, which are identified as level 1, 2,
and 3. Level 1 is the desired level that provides for highest level of comfort,
convenience and safety. Level 2 is the level to which the road deteriorates from
Level 1 after two-three years of use before fresh maintenance is implemented.
Level 3 represents the minimum level necessary to protect the investment and
provide reasonable levels of safety. The suggested serviceability levels and the
limiting levels of surface defects based on measurement of roughness, cracking,
rutting etc., are given in Table 5 [MORT&H, 2001a17].
TABLE 5. MAINTENANCE SERVICEABILITY LEVELS
Sl.
No.

Serviceability Indicator

1.

Roughness by Bump
Integrator (max. permissible)
Equivalent IRI

2.

Potholes per km
(max. number)

3.

Cracking and patching area


(max. permissible)

4.

Rutting 20 mm
(maximum permissible)

5.

Skid number
(minimum desirable)

FOR

P AVEMENTS

Serviceability Levels
Level 1
Level 2
Level 3
2000 mm/km 3000 mm/km

4000 mm/km

2.8 m/km

4.0 m/km

5.2 m/km

Nil

2-3

4-8

5 per cent

10 per cent

10-15 per cent

1.0 per cent

1.5 per cent

2.5 per cent

50 SN

40 SN

35 SN

288

AGGARWAL, PROF. JAIN & DR. PARIDA ON

4.6.2. Division of Pavement Sections into Maintenance Serviceability


Levels: In the present study, standards of Level 2 have been selected for carrying
out the network level PMS analysis. However, for the purpose of project level
PMS analysis, it is proposed to divide all pavement sections included in the
selected highway network into three serviceability levels; High, Medium, and
Low on the basis of volume of traffic carried by them at present, as shown in
Table 6. The heavily trafficked pavement sections shall be maintained as per
Level 1 standards, medium trafficked as per Level 2 standards, and lesser
trafficked as per Level 3 standards.
TABLE 6. DIVISION

OF

PAVEMENT SECTIONS

INTO

MAINTENANCE SERVICEABILITY LEVELS

Serviceability
Level

Traffic Volume
(AADT)

Pavement Sections

High (Level 1)

More than 10000

NH-5801, NH-5802, NH-5803,


NH-5804, NH-5805, NH-5806,

Medium (Level 2)

5000 10000

NH-5807, NH-7202, NH-7203,


NH-7204, NH-7205, NH-7301,
NH-7302, NH-7303, NH-7304
NH-72A1, NH-72A2, NH-72A3,
NH-72A4, NH-7401, NH-7402

Low (Level 3)

Less than 5000

NH-7201

4.6.3. Maintenance & Rehabilitation Activities: Maintenance &


Rehabilitation (M&R) treatments are actions an agency take on a given section
to either reduce the pavement deterioration rate (prevention) or to repair the
effects of deterioration (reaction). An M&R strategy is a course of action to be
taken over the analysis period in order to keep the road section in a good
condition. A strategy consists of one or more treatments applied on the section
at a specific point in time during the treatment application period. There is a
diversity of maintenance activities depending upon the class and type of the
road, the cross section to be maintained, the defects recognized, and the resources
available. Maintenance operations are usually grouped according to planning
organizational and funding arrangements. These have been categorized as
Ordinary Repairs (Routine Maintenance) and Periodic Renewals (Periodic
Maintenance) as per the Report of the Committee on Norms for Maintenance
of Roads in India [MoRT&H 2001a17].
4.7. Cost Data of M&R Works
The Committee for Maintenance Norms for Roads in India, has
recommended the total costs for carrying out various types of maintenance and

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

289

rehabilitation (M&R) works on bituminous pavements situated in various price


zones of the country. This zoning has been done on the basis of cost of stone
metal (stone chips) in that particular region. For this study, the costs specified
for Zone-IV have been taken because all pavement sections in the selected
highway network are situated in this zone. Moreover, Zone-IV has also been
considered as the average representative zone for the whole country [MoRT&H,
2001a].
4.8. Road User Cost Data
One of the most important ingredients in the life-cycle cost analysis of
pavements, either at network level or project level, is the determination of road
user cost (RUC) during maintenance and rehabilitation operations. RUC models
are also important in contracting strategies, which take into account time for a
project to be completed for award and payment. Methods used to date to
determine RUC are exclusively analytical in nature as have been shown in various
road user cost studies carried out in India so far. The road user cost is composed
of three main components:(i) Vehicle Operating Cost (ii)Time Cost
(iii) Accident Cost
Amongst the above components of the road user costs, Vehicle Operating
Cost (VOC) is the largest component and also susceptible for quantification
with relative ease. VOC is defined as the price the user has to spend to move
the vehicle per unit distance. Time cost involves monetary value of the time of
passengers spent on traveling and the time taken by cargo in transit. The accident
costs involves costs of human life and property, which is very difficult to quantify
in monetary terms. Hence this cost is not included in the analysis. The road user
cost data, in respect of all representative vehicles have been taken as per the
recommendations made in the Updated Road User Cost Study [MORT&H
2001c 19].
5. CALIBRATION & VALIDATION OF HDM-4 PAVEMENT
PERFORMANCE PREDICTION MODELS

5.1. Pavement Performance Prediction Models


Pavement performance prediction models are imperative for a complete
pavement management system. The purpose of the performance model is to
predict the future condition of a given pavement. Such a prediction is necessary
to estimate, when major maintenance would be required, and also predict
performance after some maintenance & rehabilitation activity has been
undertaken. These models have been used to analyze the future pavement

290

AGGARWAL, PROF. JAIN & DR. PARIDA ON

conditions and establish the maintenance and rehabilitation (M&R) strategies


accordingly.
5.2. Model Calibration
In order to calibrate the HDM-4 deterioration models for local conditions,
the predictions made by the Indian deterioration models as developed under the
PPS-EPS and the corresponding HDM-4 road deterioration models have been
equated using 5 sets of data conditions and the respective calibration factors
have been determined, as shown in Table 7. Calibration factors, in respect of
Cracking, Ravelling, Potholing and Roughness models have been used as
determined above. However default calibration factors (value = 1.00) have been
used for other models such as Edge-break, Rutting, Skid resistance, and Texture
depth models, because no corresponding Indian pavement deterioration models
are available to facilitate their calibration.
5.3. Validation of Models
The validity of the calibrated pavement deterioration models has been
checked to test the efficacy of these models, by comparing the distress predictions
made by the calibrated deterioration models with those actually observed on
the selected pavement sections. The pavement condition data on all sections of
the highway network was collected in Dec. 2001, using various types of
equipments and methods discussed earlier. On those pavement sections, where
no M&R treatments are provided, various kinds of distresses progressed under
the combined action of traffic loadings and environmental characteristics. The
pavement condition data on these sections were collected once again by the end
of the year 2002, using the same type of equipments and methods, so as to
ascertain the annual progression of distresses during the year 2001-2002. The
observed values of cracking area, ravelling area and roughness at the end of
year 2002 for eight untreated pavement sections have been compared with those
predicted by the HDM-4 cracking area, ravelling area and roughness models
respectively. Table 8 shows the percentage variability of cracking area, ravelling
area and roughness between observed and predicted values.
6. PAVEMENT MANAGEMENT AT PROJECT LEVEL

6.1. Project Level Pavement Management


The project level pavement management analysis may be done using the
Project Analysis application of the HDM-4. Project analysis is concerned
with the evaluation of one or more road projects or investment options. In the
present study, the following four types of case studies have been undertaken for
the project level pavement management.

Potholing Progression

Roughness
Progression

6.

7.

- SCA]

(1 + 0.05 * HS)

(1 + 1* CDB)(1 + 10 * YAX)(1 + 0.005 * MMP)

(1 + 0.08 * HS)

O BSERVED
AND

0.85

0.88

0.48

0.79

0.34

0.77

AND

0.88

0.82

0.42

0.46

0.36

1.25

0.39

Set3

0.76

0.96

0.42

0.39

0.39

1.51

0.48

Set4

0.92

1.02

0.41

0.35

0.41

1.64

0.45

Set5

Kgp = 0.85

Kpp = 0.95

Kpi = 0.45

Kvp = 0.52

Kvi = 0.37

Kcpa = 1.25

Kcia = 0.43

Average
Calibration
Factor

Roughness (m/km IRI)


Observed
Predicted % Variability
2.3
2.05
10.8
4.2
3.90
7.1
5.6
4.75
15.1
5.7
5.29
7.2
6.1
5.26
13.8
2.6
2.49
4.2
7.3
6.58
9.8
4.8
4.91
2.1
y = 0.8651x +0.2294
0.97

R OUGHNESS V ALUES

0.82

0.94

0.53

0.61

0.34

1.11

0.44

Set2

Ravelling (% Area)
Observed
Predicted % Variability
3.8
2.30
39.4
5.8
4.63
20.1
6.5
8.61
32.4
10.4
7.88
24.2
13.5
15.58
15.4
4.5
6.04
34.2
10.3
13.00
27.0
10.2
14.26
39.8
y = 1.2403x 1.0396
0.79

P REDICTED C RACKING RAVELLING

Cracking (% Area)
Observed
Predicted % Variability
1.6
1.85
15.1
5.7
5.08
10.8
10.2
11.78
15.5
13.8
17.08
23.7
15.3
17.11
11.8
2.1
1.70
19.0
16.2
20.77
28.2
11.8
14.17
20.0
y = 1.2731x 1.0131
0.98

OF

-5

DRI = Kgp [134 * EXP(m Kgm AGE3) * (1+SNPKb) YE4] +


[0.0066 * DACRA] + [0.088 * DRDS] + [0.00019 (2 FM)
1.5
1.5
{((NPTa * TLF) + (DNPT * TLF/2)) (NPTa) }] + [m Kgm RIa ]

dNPTi = Kpp* ADISi

IPT =Kpi 2.0 * (1 + 1* CDB)(1 + 0.5 * YAX)(1 + 0.01* MMP)

IRV = Kvi CDS * 10 * RRF * EXP[-0.156 * YAX]


2
dARV = Kvp(1/RRF) (1/CDS ) [(0.6 + 3.0 * YAX) * 0.352 * dtv+
0.35 1/0.35
SRV]
SRV )

dACA = Kcpa (CRP/CDS) [(1.84 * 0.45 * dtA+ SCA


0.45 1/0.45

0.37

Set1

Calibration Factors

OF

NH-58 [km 130-141]


NH-58 [km 141-153]
NH-58 [km 153-173]
NH-58 [km 218-228]
NH-72 [km 118-132]
NH-73 [km 11-25]
NH-73 [km 35-47]
NH-74 [km 13-30]
Correlation
2
R value

Pavement Section

Potholing Initiation

5.

ICA = Kcia [CDS * 4.21 EXP{0.14 SNP 17.1(YE4/SNP )} +


CRT]

HDM-4 Pavement Deterioration Models

T ABLE 8. D ETAILS

Ravelling Progression

4.

3.

2.

Cracking Initiation

1.

Cracking
Progression
Ravelling Initiation

Model Description

Sl.
No.

TABLE 7. CALIBRATION OF HDM-4 PAVEMENT DETERIORATION MODELS

DEVELOPMENT
PAVEMENT MANAGEMENT SYSTEM
NATIONAL HIGHWAY NETWORK
FOR INDIAN

291

292

AGGARWAL, PROF. JAIN & DR. PARIDA ON

(i)

PROJ1 Determination of optimum maintenance and rehabilitation


strategy for a pavement section
(ii) PROJ2 - Determination of optimum improvement strategy for a
pavement section
(iii) PROJ3 Determination of remaining life of pavement sections
(iv) PROJ4 Comparative study of scheduled and condition responsive
maintenance strategies
6.2. PROJ1 Determination of Optimum Maintenance and
Rehabilitation Strategy for a Pavement Section
This case study presents the economic analysis of alternative maintenance
and rehabilitation standards for a pavement section.
6.2.1. Input data: The input data for this case study is included in the
National Highway Network and National Vehicle Fleet databases as defined
earlier. The analysis period is defined by a start year (i.e. current year 2003)
and the duration of 10 years (i.e. 2003-2012). All these project details are
specified in the opening screen of the Project Analysis application of HDM-4.
6.2.2. Selected section: The pavement section NH-58 [km 173-192], of
the NH-58 has been selected for this study. This section is situated on the
Roorkee Haridwar segment of the highway. This is a very heavily trafficked
section as the traffic from NH-73 also joins the already moving traffic on the
NH-58, at the beginning of this section i.e. at km-173 of NH-58. This pavement
section forms the part of National Highway Network and the vehicles using this
road are included in the National Vehicle Fleet as defined earlier.
6.2.3. Pavement characteristics: It is very important that to enable
pavement condition to be modelled through the analysis period, condition data
must be specified for a date prior to the start of the analysis period. In this case
study, the pavement condition data refers to the end of year 2001, which is prior
to the start year of the analysis, i.e. 2003.
6.2.4. Pavement history: For the pavement section under study, the last
reconstruction was in 1992, setting the pavement type to AMGB (Asphaltic
Mix on Granular Base). After the application of overlay in 1997, the pavement
type resets to AMAP (Asphaltic Mix on Asphaltic Pavement), and after the
application of surface dressing in 2000, the pavement type has got reset to STAP
(Surface Treatment on Asphaltic Pavement).
6.2.5. Traffic characteristics: The total traffic in terms of AADT, initial
composition of various vehicles and the annual growth rate of each type of
vehicles for the selected pavement section have been specified.

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

293

6.2.6. Proposed M&R alternatives: The five M&R alternatives


considered for this case study are defined in the Table 9. The first alternative,
Base alternative represents minimum routine maintenance in terms of crack
sealing and pothole patching only, till such time when the reconstruction of the
pavement section becomes inevitable. Several other maintenance and
rehabilitation alternatives including resealing, overlay, and mill and replace,
have been evaluated in this case study. Since the selected pavement section
belongs to the highest serviceability level (Level1) group of pavement sections,
therefore the applicable maintenance standards and the appropriate intervention
criteria based on the serviceability indicators have been defined. All the
maintenance standards defined here are applicable from the first year of the
analysis period, i.e. year 2003.
TABLE 9. P ROPOSED M&R A LTERNATIVES

AND

I NTERVENTION CRITERIA

Alternative

Works
Standard

Description of
Work

Intervention Level

Base
Alternative

Routine +
Reconstruction

Crack Sealing

Pothole Patching
Scheduled annually
Reconstruction with
Roughness > 6IRI and
200 mm WMM+
Total damage area > 20%
50 mm BM+40 mm BC

Scheduled annually

Alternative1

Resealing

Provide 25 mm DBSD

Total damage area > 5%

Alternative2

Resealing +
Overlay

Provide 25 mm DBSD
Provide 40 mm BC

Total damage area > 5%


Roughness > 2.8 IRI

Alternative3

Overlay

Provide 40 mm BC

Roughness > 2.8 IRI

Alternative4

Mill and Replace

Remove 90 mm
Roughness > 5 IRI and
surfacing and Provide
Total carriageway
50 mm BM+40 mm BC cracked > 10%

6.2.7. Project analysis: In set up to the analysis, the Base Alternative is


confirmed and a discount rate of 10 per cent is specified. While running the
project analysis, Alternatives 1 to 4 are compared against the Base Alternative,
and the pavement deterioration, and M&R works reports are generated.
6.2.8. Pavement deterioration: Various pavement distresses such as
roughness, cracking, ravelling, and potholing etc. progress over the analysis
period as per the respective deterioration models incorporated in HDM-4, have
been calibrated for local conditions. The deterioration summary of the pavement
section under various M&R Alternatives over the analysis period of 10 years is
shown in Table 10. The effect of M&R intervention on different deterioration
parameters is also shown in this Table.

MT
(AADT)

15134
16383
17736
19200
20787
22505
24365
26380
28562
30925

15134
16383
17736
19200
20787
22505
24365
26380
28562
30925

Year

2003
2004
2005
2006
2007
2008
2009
2010
2011
2012

2003
2004
2005
2006
2007
2008
2009
2010
2011
2012

1.64
1.78
1.93
2.09
2.26
2.45
2.66
2.88
3.12
3.38

1.64
1.78
1.93
2.09
2.26
2.45
2.66
2.88
3.12
3.38

ESAL
per
lane

5.22
5.93
5.93
5.92
5.92
5.91
5.89
5.86
5.70
6.46

5.22
5.47
5.47
5.46
5.71
5.71
5.70
5.95
5.95
5.94

Adjusted
Strctural
Number
(SNP)

3.47
2.05
2.10
2.17
2.24
2.32
2.43
2.56
2.72
1.75

3.47
3.59
3.68
3.81
3.93
4.03
4.16
4.29
4.40
4.54

Roughness
IRI
(m/km)

7.40
0.00
1.11
1.88
4.48
9.53
17.81
30.41
24.25
0.60

Alternative 3

7.40
0.00
2.54
5.98
0.00
2.54
5.98
0.00
2.54
5.98

All
Structural
Cracks
(%)

Alternative 1

TABLE 10. D ETERIORATION SUMMARY

1.84
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.87
0.00

1.84
0.00
1.86
3.53
0.00
3.74
5.57
0.50
3.99
5.81

Ravelled
Area
(%)

OF THE

0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0

No. of
Potholes

1.84
0.65
0.82
0.99
1.17
1.35
1.53
1.72
1.11
0.45

3.20
3.38
3.57
3.76
3.94
4.12
4.31
4.49
4.67
4.85

Mean
Rut
Depth
(mm)

5.22
5.15
4.90
4.66
4.53
4.53
4.53
4.52
4.51
4.48

5.22
5.93
5.93
5.92
6.17
6.17
6.16
6.41
6.41
6.40

Adjusted
Structural
Number
(SNP)

3.47
3.66
4.06
5.57
2.05
2.15
2.26
2.38
2.52
2.69

3.47
2.05
2.10
2.17
2.23
2.29
2.38
2.47
2.54
2.64

14.80
37.04
71.82
40.49
0.50
0.00
1.27
3.51
7.82
15.08

Alternative 4

7.40
0.00
1.11
0.94
0.00
1.82
4.90
0.00
2.54
5.98

RoughAll
ness
Structural
IRI
Cracks
(m/km)
(%)

Alternative 2

3.67
7.85
9.91
0.00
0.00
0.00
0.00
0.00
0.00
0.65

1.84
0.00
0.00
0.00
0.00
3.74
5.64
0.50
3.99
5.81

Ravelled
Area
(%)

P AVEMENT S ECTION UNDER V ARIOUS M&R ALTERNATIVES

0
0
18
35
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0

No.
of.
Potholes

3.20
3.40
3.64
1.97
0.24
0.47
0.72
0.96
1.21
1.46

1.84
0.65
0.82
0.57
0.32
0.48
0.38
0.26
0.43
0.34

Mean
Rut
Depth
(mm)

294
AGGARWAL, PROF. JAIN & DR. PARIDA ON

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

295

6.2.9. Description of works: The timing of works report indicates the


works that would be implemented in each analysis year for each project
alternative along with the costs involved in the same. The various works items
resulting from all the M&R alternatives specified, as triggered by the respective
intervention parameters and timings of their application are shown in Table 11.
The total cost to be incurred by the highway agency on maintenance management
of the pavement section under each M&R alternatives, over the whole analysis
period of 10 years is also shown in Table 11.
6.2.10. Roughness progression: Roughness is the most useful indicator
of the pavement deterioration or average condition of the pavement section at
any given point of time. The effect of the works to be carried out under each
alternative, on average roughness of the pavement section is shown in Fig. 2.
The progression of roughness can be tracked to check that the works are correctly
triggered according to the specified intervention criteria.
6.0

Average Roughness Value


(m/km IRI)

5.5
5.0
4.5
Base Alternative
Alternative1
Alternative2
Alternative3
Alternative4

4.0
3.5
3.0
2.5
2.0
1.5
2012

2011

2010

2009

2008

2007

2006

2005

2004

2003

1.0

Year

Fig. 2. Progression of Roughness Under Various Alternatives

6.2.11. Economic analysis summary: The economic analysis summary


as shown in Table 12 gives a comparison of the present value of total agency
costs and reduction in the road user costs for each M&R alternative when
compared against the Base Alternative. The economic indicators such as Net
Present Value (NPV) and Internal Rate of Return (IRR) are also provided for
comparison purposes.
6.2.12. Selection of optimum M&R strategy: On the basis of the
economic analysis summary the Alternative 3 has been selected as the optimum
M&R strategy, having the maximum NPV/Cost of 6.123. This choice is further
substantiated by the fact that this alternative also has the highest IRR of 96.3.

2012

2011

2010

2009

2008

2007

2006

2005

2004

2003

Year

Patch &
Crack Seal
Patch &
Crack Seal
Patch &
Crack Seal
Patch &
Crack Seal
Patch &
Crack Seal
Patch &
Crack Seal
Patch &
Crack Seal
Patch &
Crack Seal
Patch &
Crack Seal
Patch &
Crack Seal

Base Alt

DBSD 25 mm

*****

*****

DBSD 25 mm

DBSD 25 mm

*****

*****

DBSD 25 mm

*****

BC 40 mm

*****

*****

*****

*****

*****

*****

*****

BC 40 mm

Alt3

Total Capital Cost in Million Indian Rupees

*****

*****

DBSD 25 mm

*****

*****

BC 40 mm

Alt2

*****

*****

DBSD 25 mm

*****

*****

DBSD 25 mm

Alt1

M&R Works

*****

*****

*****

*****

*****

1.978

0.219

0.217

0.215

0.213

0.207

0.204

0.204

Mill & Rep


80 mm
*****

0.182

0.000

0.313

Base Alt

*****

*****

*****

Alt4

TABLE 11. DESCRIPTION OF M&R WORKS AND ASSOCIATED COSTS

53.998

13.499

*****

*****

13.499

*****

*****

13.499

*****

*****

13.499

Alt1

71.314

13.499

*****

*****

13.499

*****

*****

13.499

*****

*****

30.816

Alt2

Cost of Works

61.632

*****

30.816

*****

*****

*****

*****

*****

*****

*****

30.816

Alt3

59.850

*****

*****

*****

*****

*****

*****

59.850

*****

*****

*****

Alt4

296
AGGARWAL, PROF. JAIN & DR. PARIDA ON

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

297

TABLE 12. E CONOMIC ANALYSIS SUMMARY


Alternative

Total
Agency
Costs

Increase Decrease
Net
in Agency in Road Present
Costs
User Costs Value

NPV/Cost Internal
Ratio
Rate of
Return

Base Alt.

1.312

0.000

0.000

0.000

0.000

0.0

Alternative1

36.987

35.675

51.739

16.064

0.434

21.9

Alternative2

54.304

52.992

324.866

271.875

5.007

92.1

Alternative3

45.192

43.880

320.569

276.689

6.123

96.3

Alternative4

44.966

43.654

194.492

150.838

3.354

43.3

6.3. PROJ2- Determination of an Optimum Improvement Strategy


for a Pavement Section
This case study presents the economic analysis of alternative maintenance
and improvement standards for a single lane pavement section. Applicable
maintenance and improvement works and the corresponding application years
are defined and the optimum Improvement strategy is selected on the basis of
economic indicators.
6.3.1. Selected section: The pavement section NH-72 [km 105-118], of
the NH-72 has been selected for this study. This is a single-lane section situated
on the Paontasahib Dehradun segment of the highway. Some general details
and pavement characteristics of the selected section are given in
Table 13.
TABLE 13. DETAILS

OF THE

SELECTED PAVEMENT SECTION

General Details

Pavement Characteristics

Section Name

NH-72 [km 105-118]

Material Type

SBSD

Section ID

NH-7201

Surface Thickness

15 mm

Section Length

13.00 m

Roughness

5.90 m/km IRI

Cway Width

3.70 m

Cracked Area

7%

Number of Lanes

Ravelled Area

10%

Flow Direction

Two-way

No. of Potholes

Motorised AADT

3650

Mean Rut Depth

5 mm

Climate Zone

N. India Plains

Texture Depth

2.0 mm

Altitude

285 m

Skid Resistance

0.50

298

AGGARWAL, PROF. JAIN & DR. PARIDA ON

6.3.2. Pavement history: For the pavement section under study, the last
reconstruction was done in 1990, setting the pavement type to AMGB (Asphaltic
Mix on Granular Base). After the application of overlay in 1995, the pavement
type resets to AMAP (Asphaltic Mix on Asphaltic Pavement), and after the
application of surface dressing in 1999, the pavement type has got reset to STAP
(Surface Treatment on Asphaltic Pavement).
6.3.3. Proposed improvement alternatives: The three improvement
alternatives of lane addition considered for this case study are defined in the
Table 14. Each improvement alternative is defined in terms of width of new
lane, type of new surfacing, resurfacing of existing pavement, costs involved
and effects of improvement works on overall pavement condition. All these
improvement standards will be applicable only in the respective years. A base
alternative of carrying out scheduled routine maintenance is also defined.
TABLE 14. P ROPOSED MAINTENANCE

AND

I MPROVEMENT ALTERNATIVES

Alternative

Works
Standard

Description of
Work

Application Year

Base Alternative

Routine
Maintenance

Crack Sealing and


Pothole Patching

Scheduled annually

Alternative1

Widening

Lane Addition after 4 years

2007

Alternative2

Widening

Lane Addition after 2 years

2005

Alternative3

Widening

Lane Addition immediately

2003

6.3.4. Project analysis: In set up to the analysis, discount rate of 10 per


cent is specified as it was done in the previous case study. While running the
project analysis, the three Improvement Alternatives are compared against the
Base Alternative of carrying out the annual routine maintenance only.
6.3.5. Description of works and costs: The various works items resulting
from the improvement alternatives specified, as applicable in the pre-defined
application years are shown in Table 15. The total cost to be incurred by the
highway agency on improvement of the pavement section under each
improvement alternatives, over the whole analysis period of 10 years is also
shown in Table 15.
6.3.6. Roughness progression: The progression of roughness over the
analysis period of 10 years, under the base alternative and the three improvement
alternatives is shown in Figure 3. It clearly shows that roughness shoots up to a
very high value, in case improvement works are delayed by four years.

*****

Lane Addition +
Resurfacing of Existing
Pavement

Patch & Crack


Seal

Patch & Crack


Seal

2006

2007

2012

*****

Total Capital Cost in Million Indian Rupees

*****

*****

*****

*****

*****

*****

*****

*****

*****

*****

1.120

0.108

0.107

0.106

0.105

0.104

0.103

0.105

0.107

0.098

39.783

*****

*****

*****

*****

*****

39.783

*****

*****

*****

*****

Alt 1

39.783

*****

*****

*****

*****

*****

*****

*****

39.783

*****

*****

Alt 2

Cost of Works

39.783

*****

*****

*****

*****

*****

*****

*****

*****

*****

39.783

Alt 3

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

*****

*****

*****

*****

*****
*****

*****

*****

0.172

Lane Addition +
Resurfacing of Existing
Pavement

Base Alt

ASSOCIATED COSTS

Alt 3

AND

Lane Addition +
Resurfacing of Existing
Pavement

IMPROVEMENT WORKS

OF

2011

2010

2009

*****

*****

Patch & Crack


Seal

2005

Patch & Crack


Seal
Patch & Crack
Seal
Patch & Crack
Seal
Patch & Crack
Seal
Patch & Crack
Seal

*****

*****

Patch & Crack


Seal

2004

2008

*****

*****

Patch & Crack


Seal

2003

*****

Alt 1

Alt 2

Improvement Works

OF

Base Alt

Year

TABLE 15. DESCRIPTION

DEVELOPMENT
FOR INDIAN

299

300

AGGARWAL, PROF. JAIN & DR. PARIDA ON

6.3.7. Economic analysis summary: The economic analysis summary


as shown in Table 16 gives a comparison of the present value of total agency
costs and reduction in the road user costs for each improvement alternative
when compared against the Base Alternative. The economic indicators such as
Net Present Value (NPV) and Internal Rate of Return (IRR) are also provided
for comparison purposes.
TABLE 16. E CONOMIC ANALYSIS SUMMARY
Alternative

Total Increase Decrease


Agency in Agency in Road
Costs
Costs
User
Costs

Net
Present
Value

NPV/
Cost
Ratio

Internal
Rate
of
Return
0.0

Base Alt.

0.777

0.000

0.000

0.000

0.000

Alternative1

25.745

24.968

338.236

313.268

12.168

68.7

Alternative2

31.451

30.674

491.905

461.231

14.665

152.1

Alternative3

38.356

37.579

499.265

461.686

12.037

120.0

6.3.8. Selection of the optimum improvement strategy: On the basis


of the economic analysis summary, the Alternative2 may be selected as the
optimum improvement strategy having the maximum NPV/Cost ratio of 14.665.
This choice is further substantiated by the fact that this strategy also gives the
highest IRR of 152.1. Therefore, it may be recommended on the basis of the
above economic analysis that there is no immediate need of addition of an extra
lane to the existing pavement section. This improvement work may be deferred
at least for two years to save road agency costs. But this work should not be
postponed further for another two years, as it will result in high road user costs.
6.4. PROJ3 - Determination of Remaining Service Life of Pavement
Sections
This case study presents the methodology of determining Remaining
Service Life (RSL) of some selected pavement sections of the highway network.
RSL of a pavement section is defined as the time left in years, till it will become
imperative to reconstruct the pavement, provided no amount of maintenance or
rehabilitation works are carried out in the intervening period.
6.4.1. Input data: The input data for this case study is included in the
National Highway Network and National Vehicle Fleet databases as defined
earlier. An optimum analysis period of 10 years is chosen considering the fact
that almost all pavement sections will become candidates for reconstruction in
the next ten years in the absence of any other maintenance or rehabilitation

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

301

work. Analysis by Project method is chosen for this case study. All these
project details are specified in the opening screen of the Project Analysis
application of HDM-4.
6.4.2. Selected sections: Five pavement sections, one each on five
National Highways included in the highway network have been selected for
this case study.
6.4.3. Specify alternatives: Since the purpose of this case study is to
determine the time period before reconstruction of the pavement is due, only
one M&R alternative is defined for each of the selected pavement section. The
condition responsive M&R alternative named as Do Nothing Upto
Reconstruction is defined along with intervention criteria.
6.4.4. Analyse project: The application is run for simulating the pavement
condition of the five pavement sections under the defined M&R alternative. No
economic analysis is required to be conducted in this case as there is no other
alternative defined for comparison purposes.
6.4.5. Roughness progression: Since limiting value of roughness has
been selected as the deciding intervention criterion, the progression of roughness
upto the intervention level of IRI>8 shall trigger the reconstruction of the various
pavement sections in a particular year as shown in Fig. 3. The reconstruction of
the pavement is indicated by a sharp fall in the roughness values.
9.0

Average Roughness Value


(m/km IRI)

8.0
7.0
6.0

NH-5807
NH-7205

5.0

NH-72A2
NH-7303

4.0

NH-7402

3.0
2.0

2012

2011

2010

2009

2008

2007

2006

2005

2004

2003

1.0

Year

Fig. 3. Roughness progression for all pavement sections

302

AGGARWAL, PROF. JAIN & DR. PARIDA ON

6.4.6. Determination of RSL: The RSL in respect of all five pavement


sections is determined as the time period left in years before the reconstruction
of pavement is necessitated on the basis of progression of roughness upto the
intervention level. Thus the RSL values for the various pavement sections have
been determined from Figures 16 above and the same have been shown in
Table 17.
TABLE 17. REMAINING SERVICE LIFE

OF

PAVEMENT S ECTIONS

Sl.
No.

Pavement
Section

Reconstruction
Year

Remaining Service
Life (Years)

1.

NH-5807

2007

2.

NH-7205

2005

3.

NH-72A2

2005

4.

NH-7303

2004

5.

NH-7402

2006

It can be concluded from the RSL values shown in the above table that in
the absence of any other maintenance activity, all the pavement sections included
in this case study will become candidate sections for reconstruction with in 1 to
4 years, which is a very costly affair. Hence it may be suggested that these
pavement sections should be provided with suitable maintenance and
rehabilitation works as they become due.
6.5. PROJ4 Comparative Study of Scheduled and Condition
Responsive Maintenance Strategies
This case study presents the comparison of adopting a scheduled type of
M&R strategy against a condition responsive M&R strategy for a pavement
section, over a fixed time period. The scheduled M&R strategy has been selected
as per the current maintenance norms provided in MORT&H [2001b], whereas
the condition responsive M&R strategy has been selected as per the serviceability
levels up to which the respective pavement section is to be maintained.
6.5.1. Input data: The input data for this case study is also included in
the National Highway Network and National Vehicle Fleet databases as
defined earlier. An optimum analysis period of 20 years is chosen to trigger a
number of M&R cycles. Analysis by Project method is chosen for this case
study.
6.5.2. Selected section: The pavement section NH-73 [km 11-25], of

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

303

the NH-73 has been selected for this study. This pavement section is situated
on the Roorkee Saharanpur segment of the highway. This is an important
section of the highway network as node km-25 of this section is a junction point
of NH-73 and NH-72A. In fact NH-72A originates from this section node. Some
general details and pavement characteristics of this section are given in
Table 18.
TABLE 18. DETAILS

OF THE

SELECTED PAVEMENT SECTION

General Details

Pavement Characteristics

Section Name

NH-73 [km 11-25]

Material Type

Asphaltic Concrete

Section ID

NH-7302

Surface Thickness

25 mm

Section Length

14.00 km

Roughness

2.40 m/km IRI

Cway Width

7.00 m

Cracked Area

1%

Number of Lanes

Ravelled Area

1%

Flow Direction

Two-way

No. of Potholes

Motorised AADT 7750

Mean Rut Depth

5 mm

Climate Zone

N. India Plains

Texture Depth

2.0 mm

Altitude

275 m

Skid Resistance

0.50

6.5.3. Specify M&R alternatives: Two types of M&R alternatives are


defined, one is Scheduled Overlay, and the other one is Condition Responsive
Overlay. These two M&R alternatives shall be compared against each other
as well against the third alternative of Routine Maintenance. The details of
these three alternatives are given in Table 19.
TABLE 19. DETAILS

OF

DEFINED A LTERNATIVES

Sl.
No.

M&R Alternative

M&R Work

Intervention Criteria

1.

Scheduled Overlay

Bituminous Concrete
25 mm

Scheduled every
Five years

2.

Condition Responsive
Overlay

Bituminous Concrete
25 mm

Roughness > 4.0


mm/km IRI

3.

Routine Maintenance

Patching and Crack


Sealing

Scheduled annually

6.5.4. Analyse project: The application is run for simulating the pavement
condition of the pavement sections under the three defined M&R alternatives
over the analysis period of 20 years. An economic analysis is also conducted
with a discount rate of 10 per cent.

304

AGGARWAL, PROF. JAIN & DR. PARIDA ON

5.00
4.50
4.00
Scheduled
Overlay

3.50
3.00
2.50

Condition
Responsive
Overlay

2.00
1.50
2021

2019

2017

2015

2013

2011

2009

2007

2005

1.00
2003

Average Roughness Value


(m/km IRI)

6.5.5. Roughness progression: The progression of roughness over the


analysis period of 20 years, under the three alternatives is shown in Fig. 4. In
case of Condition Responsive Overlay alternative, overlay is triggered as soon
as the roughness progresses to IRI = 4 m/km, but in case of Scheduled Overlay
alternative the overlay is triggered every five years, but at roughness value of
IRI = 3 m/km or even less, which is well below the limiting value of IRI = 4 m/
km. It clearly shows that under scheduled maintenance strategy, overlay is being
applied at an earlier stage in comparison to as warranted by the serviceability
requirements, thus causing more expenditure for the road agency.

Year

Fig. 4. Progression of roughness under three alternatives

6.5.6. Description of works: The various work items resulting from the
two M&R alternatives specified, as triggered by the respective intervention
parameters and timings of their application are shown in Table 20. The total
cost to be incurred by the highway agency on maintenance management of the
pavement section under two M&R alternatives, over the whole analysis period
of 20 years is also shown in Table 20.
TABLE 20. DESCRIPTION
M&R
Strategy
Scheduled
Condition
Responsive

M&R
Work

OF

M&R WORKS

Applicable
Years

Bituminous
2006, 2011,
Concrete 25 mm 2016, 2021
Bituminous
Concrete
25 mm

2007, 2015,
2022

AND

ASSOCIATED COSTS

Frequency
of Application

Total Costs
Agency in
Million Rupees

58.447

43.835

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

305

6.5.7. Comparison of M&R strategies: The cost comparison of the two


strategies clearly indicate that the highway agency shall have to dispense with
Rs. 58.447 million over a period of 20 years on overlaying the pavement section
four times, in case they adopt the scheduled maintenance strategy as provided
in the current maintenance norms [MORT&H, 2001b]. However, the agency
may have to spend only Rs. 43.835 million on overlaying the pavement section
three times over the same period, in case they adopt the condition responsive
maintenance strategy. Thus there will be a net saving in cost of about 33 per
cent over the analysis period of 20 years if a condition responsive M&R strategy
is adopted by the highway agency.
6.5.8. Economic analysis summary: The economic analysis summary
as shown in Table 21 gives a comparison of the present value of the total highway
agency costs and reduction in the road user costs for the two M&R strategies
when compared against the base strategy of routine maintenance. A comparison
of the NPV/Cost values indicates that the condition responsive maintenance
strategy gives a higher NPV/Cost ratio of 18.535 as against 15.613 obtained in
case of the scheduled maintenance strategy.
TABLE 21. ECONOMIC ANALYSIS SUMMARY
M&R
Strategy

Present
Value of
Total
Agency
Costs

Increase in
Agency
Costs

Decrease
in Road
User Costs

Net Present
Value
(NPV)

NPV/Cost
Ratio

Routine

0.883

0.000

0.000

0.000

0.000

Scheduled

24.655

23.772

408.709

384.937

15.613

Condition
Responsive

17.025

16.142

331.698

315.556

18.535

Therefore, it may be concluded on the basis of above case study that


condition responsive M&R strategies should be adopted for maintenance
management of pavement sections for an optimum utilization of maintenance
funds.
7. PAVEMENT MANAGEMENT AT NETWORK LEVEL

7.1. Network Level Pavement Management


The network level pavement management analysis has been done using
the Programme Analysis application of the HDM-4. This application deals
primarily with the prioritisation of a defined long list of candidate pavement

306

AGGARWAL, PROF. JAIN & DR. PARIDA ON

section into a multi-year work programme under defined budget constraints.


The selection criteria will normally depend on the maintenance or improvement
standards defined by the road administration. This application is then used to
compare the life cycle costs predicted under the existing regimen of pavement
management that is without project case against with project case.
In the present study, the following four types of case studies have been
undertaken for the network level pavement management, using the Programme
Analysis application of HDM-4.
(i)

PROG1 Life-cycle cost analysis of highway network

(ii)

PROG2 - Determination of requirements of funds for maintaining


the highway network as per three serviceability levels

(iii) PROG3 Determination of effect of budget reduction on highway


network condition
(iv)

PROG4 Determination of effect of deferred maintenance on


highway network condition

7.2. PROG1 - Life Cycle Cost Analysis of Highway Network


This case study demonstrates the development of a maintenance and
rehabilitation programme for the selected highway network and the use of HDM4 in budget forecasting for an analysis period of 10 years. The main objectives
of this study are to prepare an unconstrained works programme, to determine
the required funding levels for defined network performance standards, to
demonstrate the effect of budgetary constraints on the long-term performance
trends, and to prepare a prioritized works programme in the event of constrained
budgets.
7.2.1. Input data: The input data for this case study is included in the
National Highway Network and National Vehicle Fleet databases as defined
earlier. All 22 pavement sections included in the National Highway Network
have been selected for this study. All six types of vehicles included in the
National Vehicle Fleet have been selected for this study. The composition of
traffic and the annual growth rates as applicable to all pavement sections have
been selected appropriately.
7.2.2. Selection of alternative M&R strategies: The life cycle cost
analysis requires a comparison to be made between a base case (do minimum)
alternative against one or more project case (do something) alternatives. For
this case study, two alternatives have been defined for each road section; a
Base Alternative and an M&R Alternative. The Base Alternative comprise
of routine pavement maintenance activities in terms of crack sealing and pothole

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

307

patching only. The M&R Alternative includes resealing, overlays and


reconstruction work activities. The maintenance works included in the Base
Alternative are the same for all pavement sections but in case of M&R
Alternative, the maintenance and rehabilitation works will vary depending upon
the serviceability level, i.e., high, medium or low, as defined earlier, as per the
current traffic volume level of the pavement section. The respective pavement
sections will be entitled to receive the M&R works as per the higher serviceability
level, as and when the traffic volume on them exceed the limiting value, and
goes into the next higher category of serviceability. The selected alternative
M&R strategies, maintenance and rehabilitation works and the corresponding
intervention criteria are shown in Table 22.
7.2.3. Life-cycle cost analysis: After selection of the alternative M&R
strategies, the programme analysis application has been used to compare the
total life-cycle costs including the highway agency costs and road user costs,
predicted under the base alternative of scheduled routine maintenance against
those predicted for the condition responsive M&R alternative. The programme
application is run, for doing the life cycle cost analysis of the whole pavement
network. After this analysis, the options with the highest NPV are assigned for
each pavement section. A summary of the life-cycle cost analysis, showing the
increase in highway agency costs and decrease in road user costs as a result of
selecting the M&R Alternative in comparison to the Base Alternative, is
given in Table 23. All these costs have been discounted to the base year 2003,
with a discount rate of 10 per cent.
7.2.4. Unconstrained works programme: The result of this process is
a tentative unconstrained programme determined by the specified M&R
standards. The unconstrained works programme list as shown in Table 24, gives
details of the optimum M&R work activities for selected pavement sections,
year of their application, corresponding financial costs involved, and the
cumulative budget requirements. The total agency cost required for maintenance
management of the whole highway network for the analysis period of 10 years
comes out to be 1,475.87 million Indian Rupees. If sufficient budget is available,
this unconstrained works programme can be taken up for final application on
the highway network.
7.2.5. Section-wise budget requirements: The section-wise budget
requirements under each alternative for the maintenance management of the
highway network throughout the analysis period of 10 years are shown in Table
25. These budget requirements have also been depicted graphically as shown
in Fig. 5. The budget requirements for maintaining the highway network at an
optimum serviceability level are almost 45 times more than those required for
maintaining it with only routine maintenance type of activities.

Works Standard

Routine
Maintenance

Resealing +
Overlay +
Reconstruction

Alternative
Strategies

Base
Alternative

M&R
Alternative
5,000 to 10,000

< 5,000

Low

> 10,000

All

Traffic Level
(AADT)

Medium

High

Low

Serviceability
Level
High
Medium

TABLE 22. DETAILS


M&R Works

SELECTED M&R STRATEGIES

Roughness > 8 m/km IRI


and
Total Damage Area > 20%
Total Damage Area > 15%
Roughness > 5.2 m/km IRI

Overlay 25 mm Semi Dense Bituminous


Concrete
Wet Mix Macadam 200 mm + Base Course 50
mm Bituminous Macadam + Surface Course 25
mm Semi Dense Bituminous Concrete

Roughness > 10 m/km IRI


and
Total Damage Area > 30%

Roughness > 4 m/km IRI

Roughness > 6 m/km IRI


and
Total Damage Area >10%
Total Damage Area > 10%

Wet Mix Macadam 200 mm + Base Course 50


mm Bituminous Macadam + Surface Course 25
mm Bituminous Concrete
Single Bituminous Surface Dressing

Roughness > 2.8 m/km IRI

Wet Mix Macadam 200 mm + Base Course 50


mm Bituminous Macadam + Surface Course 40
mm Bituminous Concrete
Double Bituminous Surface Dressing
Overlay 25 mm Bituminous Concrete

Total Damage Area > 5%

Overlay 40 mm Bituminous Concrete

Scheduled Annually

Intervention Criteria

Double Bituminous Surface Dressing

Crack Sealing and Pothole Patching

OF

308
AGGARWAL, PROF. JAIN & DR. PARIDA ON

km

309

km

km

km

km

km

km
km

km

km

km

km

km

km

km

km

km

km

km

FOR INDIAN

km

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

km

DEVELOPMENT

Fig. 5. Section-wise Budget Requirements for the Highway Network


TABLE 23. S UMMARY
Pavement
Section ID

NH-5801
NH-5802
NH-5803
NH-5804
NH-5805
NH-5806
NH-5807
NH-7201
NH-7202
NH-7203
NH-7204
NH-7205
NH-72A1
NH-72A2
NH-72A3
NH-72A4
NH-7301
NH-7302
NH-7303
NH-7304
NH-7401
NH-7402

Increase in Road
Agency Costs
Capital

Recurrent

31.06
38.94
72.56
54.30
40.47
48.92
30.50
17.19
32.44
46.04
45.29
42.77
31.66
32.70
29.39
24.67
28.95
35.94
35.35
45.68
31.84
36.56

-0.24
-0.43
-0.98
-1.31
-0.96
-1.19
-0.82
-0.78
-0.99
-0.91
-1.61
-0.29
-1.03
-0.15
-0.17
-0.61
-0.44
-0.54
-0.20
-1.11
-1.30
-1.66

OF

L IFE C YCLE COST A NALYSIS

Savings in Road
User Costs
Vehicle Travel
Operating Time
Costs
Costs
39.38
194.04
562.88
304.77
329.93
341.52
208.86
138.38
159.30
244.70
336.96
743.56
246.11
451.63
476.32
46.64
90.71
63.45
575.74
300.59
150.25
222.67

3.17
15.75
75.39
19.46
30.24
38.82
38.00
6.55
36.63
58.13
90.50
512.70
40.38
222.83
208.31
2.08
9.12
5.25
359.62
98.99
19.39
52.04

Economic Indicators
Net
Economic
Benefit
(NPV)

NPV/
Cost
Ratio

EIRR
(%)

11.72
171.28
566.70
271.24
320.65
332.61
217.18
128.52
164.49
257.70
383.78
1213.78
255.86
641.91
656.30
24.66
71.32
33.30
99.21
355.01
139.10
239.81

0.377
4.399
7.810
4.995
7.923
6.799
7.121
7.479
5.070
5.597
8.474
28.377
8.083
19.629
22.327
1.000
2.464
0.927
25.468
7.772
4.368
6.559

18.1
102.0
180.8
92.0
163.5
157.1
199.0
208.1
139.1
161.2
185.8
258.5
205.1
265.3
255.7
35.5
49.5
31.5
366.2
233.2
133.7
146.3

310

AGGARWAL, PROF. JAIN & DR. PARIDA ON


TABLE 24. SECTION -WISE U NCONSTRAINED WORKS PROGRAMME L IST

Pavement
Section

Traffic Application
(AADT)
Year

NH-58 [km 130-141]

NH-72 [km 105-118]

NH-72A [km 0-11]

NH-73 [km 0-11]

NH-74 [km 0-13]

M&R
Work

Financial Cumulative
Cost
Cost

12394

2003

DBSD

9.771

9.771

14525

2005

BC 40 mm

22.299

32.071

18431

2008

DBSD

9.771

41.842

23392

2011

DBSD

9.771

51.613

3951

2003

SDBC 25 mm

7.638

537.685

5012

2006

DBSD

6.104

543.789

5427

2007

BC 25 mm

8.966

552.755

6887

2010

DBSD

6.104

558.859

7090

2003

BC 25 mm

14.353

868.408

9739

2007

BC 25 mm

14.353

882.761

12359

2010

DBSD

9.771

892.532

13381

2011

BC 40 mm

22.299

914.831

8486

2003

DBSD

9.771

1,093.60

10767

2006

BC 40 mm

22.299

1,115.90

13663

2009

DBSD

9.771

1,125.67

17342

2012

DBSD

9.771

1,135.44

5932

2003

BC 25 mm

14.782

1,367.80

7526

2006

DBSD

10.063

1,377.87

9550

2009

DBSD

10.063

1,387.93

10340

2010

BC 40 mm

22.965

1,410.90

TABLE 25. S ECTION -WISE BUDGET REQUIREMENTS FOR M AINTENANCE M ANAGEMENT


HIGHWAY NETWORK
Section Name

NH-58
NH-58
NH-58
NH-58
NH-58
NH-58
NH-58
NH-72
NH-72
NH-72

[km
[km
[km
[km
[km
[km
[km
[km
[km
[km

130-141]
141-153]
153-173]
173-192]
192-204]
204-218]
218-228]
105-118]
118-132]
132-148]

OF

Budget Requirements (Million Rupees)


Base Alternative

M&R Alternative

0.500
0.829
1.745
2.472
1.732
2.113
1.472
1.400
1.741
1.556

51.613
69.972
116.620
89.149
69.972
81.634
51.086
28.812
59.084
88.402
(Contd.)

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

311

TABLE 25 (Contd.)
Section Name

NH-72 [km 162-180]


NH-72 [km 180-197]
NH-72A [km 0-11]
NH-72A [km 11-22]
NH-72A [km 22-33]
NH-72A [km 33-43]
NH-73 [km 0-11]
NH-73 [km 11-25]
NH-73 [km 25-35]
NH-73 [km 35-47]
NH-74 [km 0-13]
NH-74 [km 13-30]
Total Budget Requirements

Budget Requirements (Million Rupees)


Base Alternative

M&R Alternative

2.801
0.610
1.793
0.319
0.357
1.167
0.813
1.108
0.400
1.948
2.339
3.022
Rs. 32.240 million

75.965
71.745
60.776
61.477
56.432
51.090
51.610
65.690
66.260
85.630
57.880
64.970
Rs. 1475.870 million

7.2.6. Year-wise budget requirements: The year-wise budget


requirements for the highway network under the M&R alternative are shown in
Fig. 6. It is quite clear from this figure that more than one-fourth (26 per cent)
of the total budget requirements need to be met with in the very first year (2003)
of the analysis period itself, as majority of the pavement sections (20 sections)
become candidate sections for M&R works to be undertaken in that year. The
remaining 2 sections become candidates in the second year (2004) of the analysis
period. Thereafter, there will be no immediate budget requirements for carrying
out M&R works on all but one pavement section in the year 2005. However,
the need for M&R works on most of the sections appears again in the following
years 2006 and 2007 as indicated by almost 30 per cent of the total fund
requirements during these two years. Some leftover pavement sections become
candidates for M&R in the next year 2008. Thereafter, from year 2009 onwards,
the yearly fund requirements show a variable trend till the end of the analysis
period, depending upon the number of pavement sections becoming candidate
sections for maintenance and rehabilitation.
7.2.7. Condition of the highway network: As a result of the above
analysis, the predicted average roughness progression of the highway network
as a whole, under the Base Alternative and the M&R Alternative is shown in
Fig. 7. The average roughness keep on increasing in case of Base Alternative
because the routine maintenance operations do not help in reducing roughness,
though it retards the rate of progression of roughness somewhat. In case of
M&R alternative, the average roughness value for the highway network remains
at an optimum level because of timely application of M&R works.

312

AGGARWAL, PROF. JAIN & DR. PARIDA ON

350
300
250
200
150
100

2012

2011

2010

2009

2008

2007

2006

2005

2004

50
2003

Budget Requirements (Million


Rupees)

400

Year
Fig. 6. Year-wise budget requirements

9.0
8.0

Base
Alternative

7.0
6.0

M&R
Alternative

5.0
4.0
3.0
2.0
2012

2011

2010

2009

2008

2007

2006

2005

2004

1.0
2003

Average Roughness Value


(m/km IRI)

10.0

Year
Fig. 7. Average roughness value for the highway network

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

313

7.2.8. Budget optimisation: In the unconstrained works programme, if


the budget required for each budget period is below the given budget constraints,
no further economic analysis is necessary and the unconstrained works
programme can be adopted as such. However, if the budget needs are higher
than the available budgets, two options are available:
(i)

Revise maintenance and improvement standards and run the lifecycle analysis again. This will essentially include lowering the
intervention criteria for each M&R works to be applicable.

(ii)

Execute budget optimisation since the maintenance/improvement


standards have already been fixed, keeping in view the minimum
requirements of the candidate pavement sections, very little scope
exists for their revision. Hence, under most of the circumstances,
the second option of budget optimisation would usually be selected.
The budget optimisation provides a facility to select road sections
that can be included within a specified budget in order to maximize
the economic benefits. After performing the budget optimisation, a
revised work programme is produced. This works programme has
a total cost that is within the specified budget.

7.2.9. Optimized works programme: The budget optimisation provides


a facility to select pavement sections that can be included with in a specified
budget in order to maximize the economic benefits. In case, sufficient funds are
not available to carry out all the M&R activities as shown in the unconstrained
works programme list, the works programme need to be optimized depending
upon the available budget. Since the usual level of fund allocations for the
maintenance management of National Highways in India is of the order of 60
per cent only [MORT&H, 2001a], therefore the budget optimisation process is
also run with 60 per cent (885.5 million Rupees) budget availability as against
the requirement of 1,475.87 million Rupees over the analysis period of 10 years.
The optimisation process is set up by specifying the minimum incremental value
for NPV and the budget optimisation is performed using the Incremental
Analysis Method. This process results in an optimized works programme list
as shown in Table 26. This optimized works programme has total budget
requirements of 885.49 million Rupees that is with in the specified budget.
7.2.10. Prioritization: As a result of the budget optimisation process,
the yearly M&R works have also been prioritized on the basis of decreasing
NPV/cost ratio. A list of prioritized M&R works for the year 2007 is shown in
Table 27. The works shall be taken up for execution as per the indicated priority
ranking.

314

AGGARWAL, PROF. JAIN & DR. PARIDA ON


TABLE 26. SECTION -WISE O PTIMIZED WORKS P ROGRAMME L IST

Pavement
Section
NH-58 [km 153-173]

NH-58 [km 192-204]

NH-58 [km 204-218]

NH-58 [km 218-228]

NH-72 [km 105-118]

NH-72 [km 118-132]

NH-72 [km 162-180]

NH-72 [km 180-197]

NH-72A [km 0-11]

Traffic Application
(AADT)
Year

M&R
Work

Financial Cumulative
Cost
Cost

13304

2003

BC 40 mm

40,544

16879

2006

DBSD

17,766

40,544
58,31

18273

2007

BC 40 mm

40,544

98,854

23190

2010

DBSD

17,766

116,62

15003

2003

BC 40 mm

24,326

140,946

19035

2006

DBSD

10,66

151,606

24155

2009

BC 40 mm

24,326

175,932

30659

2012

DBSD

10,66

186,592

12189

2003

BC 40 mm

28,381

214,973

15464

2006

DBSD

12,436

227,409

18125

2008

BC 40 mm

28,381

255,79

23004

2011

DBSD

12,436

268,226

9244

2003

BC 25 mm

13,048

281,274

11729

2006

DBSD

8,883

290,157

12698

2007

BC 40 mm

20,272

310,429

16114

2010

DBSD

8,883

319,312

3951

2003

SDBC

7,638

326,95

5012

2006

DBSD

6,104

333,054

5427

2007

BC 25 mm

8,966

342,02

6887

2010

DBSD

6,104

348,124

6192

2003

BC 25 mm

18,267

366,391

9207

2008

DBSD

12,436

378,827

10793

2010

BC 40 mm

28,381

406,308

7880

2003

BC 25 mm

23,486

430,695

10824

2007

BC 40 mm

36,49

467,184

13737

2010

DBSD

15,989

483,174

7404

2003

BC 25 mm

22,182

505,355

10170

2007

BC 40 mm

34,462

539,818

12906

2010

DBSD

15,101

554,919

7090

2003

BC 25 mm

14,353

569,271

9739

2007

BC 25 mm

14,353

583,624

12359

2010

DBSD

9,771

593,396

13381

2011

BC 40 mm

22,299

615,695
(Contd.)

DEVELOPMENT

Pavement
Section

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

Traffic Application
(AADT)
Year

NH-72A [km 11-22]

NH-72A [km 22-33]

NH-73 [km 25-35]

NH-73 [km 35-47]

2007

315

Financial Cumulative
Cost
Cost

6830

2003

BC 25 mm

12,507

628,202

8666

2006

DBSD

8,515

636,717
649,225

9382

2007

BC 25 mm

12,507

11906

2010

DBSD

8,515

657,74

12891

2011

BC 40 mm

19,432

677,172

6765

2003

BC 25 mm

13,328

690,499

9293

2007

BC 25 mm

13,328

703,827

11793

2010

DBSD

9,073

712,9

12769

2011

BC 40 mm

20,706

733,607

8302

2003

BC 25 mm

12,116

745,723

10534

2006

DBSD

8,249

753,971
772,795

11404

2007

BC 40 mm

18,824

14472

2010

DBSD

8,249

781,044

15670

2011

BC 40 mm

18,824

799,868

8281

2003

BC 25 mm

15,658

815,525

10506

2006

DBSD

10,66

826,185

11374

2007

BC 40 mm

24,326

850,511

14435

2010

DBSD

10,66

861,171

15629

2011

BC 40 mm

24,326

885,497

TABLE 27. PRIORITIZED LIST


Year

M&R
Work

FOR INDIAN

Pavement Section

OF

M&R W ORKS
Traffic
(AADT)

FOR THE

M&R
Work

YEARS 2003-2012
NPV/CAP

Priority
Ranking

NH-72 [km 180-197]

10170

BC 40 mm

28.377

NH-73 [km 25-35]

11404

BC 40 mm

25.468

II

NH-72A [km 22-33]

9293

BC 25 mm

22.327

III

NH-72A [km 11-22]

9382

BC 25 mm

19.629

IV

NH-72 [km 162-180]

10824

BC 40 mm

8.474

NH-72A [km 0-11]

9739

BC 25 mm

8.083

VI

NH-58 [km 153-173]

18273

BC 40 mm

7.81

VII

NH-73 [km 35-47]

11374

BC 40 mm

7.772

VIII

NH-72 [km 105-118]

5427

BC 25 mm

7.479

IX

NH-58 [km 218-228]

12698

BC 40 mm

7.121

316

AGGARWAL, PROF. JAIN & DR. PARIDA ON

7.2.11. Inclusion of Must Do works in the optimized programme:


One of the key aspects of pavement management is the ability to intervene and
select projects that should be carried out for reasons other than the economic
priority alone (committed road works). But such projects should meet the
minimum criterion of a positive economic return in order to qualify for selection.
When the budget allocations are very low, it may be possible to take up only a
few M&R works included in the unconstrained works programme. Most of the
other M&R works may have to be excluded because of budgetary limitations.
In such a scenario, necessity may arise for including some Must Do M&R
works in the optimized works programme, which are scheduled to be carried
out on some very prominent sections of the highway network, but they might
have been otherwise excluded from the optimized works programme because
of low values of NPV/Cost ratio.
One such kind of pavement sections is NH-58[km 173-192] situated on
the RoorkeeHaridwar segment of the highway network. This is the most
important segment of the highway network, because of its proximity to the holy
city of Haridwar. Moreover, this section carries the maximum amount of traffic
volume on whole of the highway network. Therefore, it is quite imperative that
all M&R works scheduled for this pavement section, as per the unconstrained
works programme, are taken up despite the budgetary constraints. This pavement
section does not figure in the optimized works programme as is apparent from
the section-wise optimized works programme list shown in Table 26. In order
to include this section in the optimized works programme, this section is selected
with Manual Assignment in the unconstrained works programme. The
optimization process is run again with the same budget level of 885.5 million
Rupees, to obtain a revised optimized works programme.
All the M&R works scheduled on this pavement section, as per the
unconstrained works programme, throughout the analysis period of 10 years,
now appear in the revised optimized works programme list. A portion of this
list is shown highlighted in Table 28. Since the limiting budget remains the
same, this section has to be accommodated in the optimized works programme
only by excluding some other sections having marginally higher NPV/Cost ratio.
7.3. PROG2 - Determination of Requirements of Funds for
Maintaining the Highway Network as per Three
Serviceability Levels
This case study demonstrates the determination of funds requirements
for maintaining the whole of the highway network as per the three levels of
serviceability as defined earlier. The main objective of this analysis is to show

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

317

TABLE 28. YEAR -WISE OPTIMIZED WORKS P ROGRAMME L IST W ITH MANUAL ASSIGNMENTS
Year

Pavement Section

M&R Work

2004

NH-72A [km 33-43]

DBSD

8.883
8.249

2006

2007

NPV/CAP Financial Cost

NH-73 [km 25-35]

DBSD

25.468

NH-72A [km 11-22]

DBSD

19.629

8.515

NH-58 [km 192-204]

DBSD

7.923

10.66

NH-58 [km 153-173]

DBSD

7.81

17.766

NH-73 [km 35-47]

DBSD

7.772

10.66

NH-72 [km 105-118]

DBSD

7.479

6.104

NH-58 [km 218-228]

DBSD

7.121

8.883

NH-58 [km 173-192]

DBSD

4.995

16.878

NH-72 [km 180-197]

BC 40 mm

28.377

34.462

NH-73 [km 25-35]

BC 40 mm

25.468

18.824

NH-72A [km 22-33]

BC 25 mm

22.327

13.328

NH-72A [km 11-22]

BC 25 mm

19.629

12.507

NH-72 [km 162-180]

BC 40 mm

8.474

36.49

NH-72A [km 0-11]

BC 25 mm

8.083

14.353

NH-58 [km 153-173]

BC 40 mm

7.81

40.544
24.326

NH-73 [km 35-47]

BC 40 mm

7.772

NH-72 [km 105-118]

BC 25 mm

7.479

8.966

NH-58 [km 218-228]

BC 40 mm

7.121

20.272

NH-72A [km 33-43]

DBSD

8.883

2008

NH-72A [km 33-43]

BC 25 mm

13.048

2009

NH-58 [km 192-204]

BC 40 mm

7.923

24.326

NH-58 [km 173-192]

DBSD

4.995

16.878

how the funds requirements vary with changing the serviceability level from
High to Medium, and to Low. How these fund requirements compare with the
requirements, when the highway network is maintained as per an optimum level
of serviceability, is also shown in this case study.
7.3.1. Input data: The input data for this case study is also included in
the National Highway Network and National Vehicle Fleet databases. All
22 pavement sections included in the national highway network have been
selected for this study.
7.3.2. Selection of alternative M&R strategies: For this case study,

318

AGGARWAL, PROF. JAIN & DR. PARIDA ON

four alternative M&R strategies have been defined for each road section on the
basis of desired level of serviceability to which the road network is to be
maintained. All these M&R strategies are effective from the start year of the
analysis period i.e. 2003. The selected alternative strategies, maintenance and
rehabilitation works involved and the corresponding intervention criteria are
shown in Table 29.
TABLE 29. D ETAILS

OF

SELECTED M&R S TRATEGIES

Alternative
Strategies

M&R Works

Intervention Criteria

M&R Optimum
Serviceability

Applicable to pavement
sections as per their
respective serviceability
levels

Applicable to respective M&R works

M&R High
Serviceability

Resealing with DBSD


Overlay with 40 mm BC
Reconstruction with
200 mm WMM + 50 mm
BM + 40 mm BC

Total Damage Area > 5 per cent


Roughness > 2.8 m/km IRI
Roughness > 6 m/km IRI and
Total Damage Area >10 per cent

M&R Medium
Serviceability

Resealing with DBSD


Overlay with 25 mm BC
Reconstruction with
200 mm WMM + 50 mm
BM + 25 mm BC

Total Damage Area > 10 per cent


Roughness > 4 m/km IRI
Roughness > 8 m/km IRI and
Total Damage Area > 20 per cent

M&R Low
Serviceability

Resealing with SBSD


Overlay with 25 mm SDBC
Reconstruction with
200 mm WMM + 50 mm
BM + 25 mm SDBC

Total Damage Area > 15 per cent


Roughness > 5.2 m/km IRI
Roughness > 10 m/km IRI and
Total Damage Area > 30 per cent

7.3.3. Fund requirements: After selection of the alternative M&R


strategies, the programme application is run and the road works summary, as
applicable under each M&R strategy, is obtained along with the costs for the
same. The total year-wise fund requirements as obtained from this analysis are
shown in Table 30. A graphical representation of total fund requirements, under
each M&R strategy, over the analysis period of 10 years is shown in Fig. 8.
7.3.4. Comparison of fund requirements: The above results indicate
that the funds requirements for maintaining whole of the highway network at
the highest level of serviceability is about 27 per cent more than those required
for maintaining it at the optimum level of serviceability. It would be possible to
maintain the same highway network at a medium level of serviceability at about

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

TABLE 30. FUND REQUIREMENTS

FOR

FOR INDIAN

319

E ACH MAINTENANCE S TRATEGY

Fund Requirements in Million Rupees


Year

M&R Optimum
Serviceability

M&R - High
Serviceability

M&R - Medium
Serviceability

M&R - Low
Serviceability

2003

383.193

831.747

315.953

207.803

2004

21.310

34.734

36.970

34.513

2005

22.300

22.301

0.000

0.000

2006

184.688

211.425

127.929

83.154

2007

253.835

244.885

184.306

52.581

2008

63.632

38.152

50.267

60.854

2009

103.451

128.292

93.057

71.734

2010

175.648

151.999

99.425

56.326

2011

160.237

114.631

107.102

38.285

107.494

93.639

74.055

74.890

Total

1475.870

1871.809

1089.068

681.042

Budget Requirements (Million Rupees)

2012

2000
1800
Optimum Fund Requirements

1600
1400
1200
1000
800
600
400
200
0
Optimum
Serviceability

High
Serviceability

Medium
Serviceability

Low
Serviceability

Level of Serviceability
Fig. 8. Fund requirements for each serviceability level

320

AGGARWAL, PROF. JAIN & DR. PARIDA ON

74 per cent of funds required for obtaining optimum serviceability. The funds
requirement for maintaining the whole highway network at the lowest level of
serviceability would only be of the order of about 46 per cent. But as per the
prevalent practice of allocation of funds in India, only 50-60 per cent funds are
available for maintenance management of National Highways [MORT&H,
2001a]. With such kind of fund allocation, it would not be possible to maintain
whole of the highway network either at high or even at medium level of
serviceability. However, the available funds would be sufficient enough to
maintain the highway network at the lowest level of serviceability.
7.3.5. Highway network condition: The average condition of the
highway network has been represented by the average roughness value (in terms
of IRI m/km) under the different M&R strategies as shown in Fig. 9. The
roughness progression is showing quite an expected trend with the various
maintenance strategies.

Average Roughness Value


(m/km IRI)

7.0

High
Serviceability
Medium
Serviceability
Low
Serviceability
Optimum
Serviceability

6.0
5.0
4.0
3.0
2.0

2012

2011

2010

2009

2008

2007

2006

2005

2004

2003

1.0

Year

Fig. 9. Highway network condition under each M&R serviceability level

7.4. PROG3 - Determination of Effect of Budget Reduction on


Highway Network Condition
This case study demonstrates the effect of reduction in budget allocations
on the condition of highway network as a whole. The main objective of this
analysis is to compare the average condition of the highway network in terms of
pavement roughness under various levels of budget allocations.

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

321

7.4.1. Input data: The input data for this case study is also included in
the National Highway Network and National Vehicle Fleet databases. All
22 pavement sections included in the national highway network have been
selected for this study.
7.4.2. Selection of alternative M&R strategies: The alternative M&R
strategies in this case have been selected to be the same as those selected for
the life cycle cost analysis of highway network in PROG1.
7.4.3. Budget optimisation: To do the budget optimisation, the
optimisation process is run with various budget allocations. The total budget
requirement is of 1475.9 million Rupees for undertaking the unconstrained works
programme, as determined in case of life cycle cost analysis of highway network.
The various levels of budget allocation for which optimisation process has been
done are shown in the Table 31.
TABLE 31. BUDGET ALLOCATION LEVELS
Sl. No.

Budget Allocation (%)

Budget Allocation (Million Rupees)

1.

100%

1475.9

2.

90%

1328.3

3.

80%

1180.7

4.

70%

1033.1

5.

60%

885.5

6.

50%

738.9

7.4.4. Effect on highway network condition: The effect of various


budget levels on average condition of the highway network can be expressed
by the average roughness value in terms of IRI (m/km), as shown in Fig. 10.
It is quite clear from the above figure that the average roughness value of
the highway network keep on increasing with gradual reduction in budget levels,
which in turn may lead to very high road user cost values. Thus reduced budget
levels have a very detrimental impact on the condition of the highway network.
7.5. PROG4 - Determination of Effect of Deferred Maintenance on
Highway Network Condition
This case study demonstrates the effect of not taking up the maintenance
when it is due, may be because of unavailability of funds altogether and thereby
deferring the maintenance to subsequent years. The main objective of this

322

AGGARWAL, PROF. JAIN & DR. PARIDA ON


6

Roughness (m/km IRI)

5.5
5
100% Budget
4.5

90% Budget
80% Budget

70% Budget
60% Budget

3.5

50% Budget
3
2.5

2012

2011

2010

2009

2008

2007

2006

2005

2004

2003

Year

Fig. 10. Average Roughness Value Under Varying Levels of Budget Allocations

analysis is to show how the condition of the highway network will get affected
because of this postponement in taking up the requisite maintenance and
rehabilitation activities.
7.5.1. Input data: The input data for this case study is also included in
the National Highway Network and National Vehicle Fleet databases. All
22 pavement sections included in the national highway network have been
selected for this study.
7.5.2. Selection of alternative M&R strategies: For this case study,
four alternatives M&R strategies have been defined for each road section on
the basis of their start year of application. In each alternative, the M&R works
and the intervention criteria is such as to maintain the various pavement sections
included in the highway network at their respective levels of serviceability, but
the start year of application in each case is different.
7.5.3. Highway network condition: The average condition of the highway
network has been represented by the average roughness value (in terms of IRI
m/km) under the different alternative strategies as shown in Fig. 11.
It is quite evident from the above figure that the average roughness value
of the highway network will not change much if the maintenance is delayed by
one year, but this value will rise very sharply, in case the application of
maintenance activities is deferred by two years or more, resulting in very high
road user costs. Thus, it may be concluded that the M&R activities should not
be delayed much from the time they have been triggered by the respective
intervention levels.

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

323

Average Roughness Value


(m/km IRI)

9.00
8.00
7.00
M&R-2003

6.00

M&R-2004
5.00

M&R-2005

4.00

M&R-2006

3.00
2.00

2012

2011

2010

2009

2008

2007

2006

2005

2004

2003

1.00

Year

Fig. 11. Highway network condition under each M&R strategy


8. APPLICATIONS OF THE STUDY

The work carried out under this study may find numerous applications
for the purpose of maintenance management of various highway networks. Some
of the potential applications are outlined below:

The National Highway Authority of India (NHAI) is contemplating


the development of a Road Information Management System (RIMS)
for the National Highway (NH) network in the country using HDM-4.
The methodology adopted in this study may be extended to include
whole of the NH network to achieve this objective.

The highway agencies, in-charge of maintenance management of


various highway networks under their jurisdiction may develop and
implement a pavement management system for their respective highway
network as per the methodology presented in this study.

The concerned field engineers may be suitably trained to understand


and put into practice the various aspects of PMS, such as pavement
sectioning, data collection, database management, and economic
analysis for optimization and prioritization of pavement maintenance
activities under constrained budget.

The highway agencies should collaborate with the specialist research


institutions to calibrate and further refine the pavement performance
models incorporated into HDM-4, to suit to their local climatic and
pavement conditions.

The condition responsive maintenance strategies may be adopted for

324

AGGARWAL, PROF. JAIN & DR. PARIDA ON

the prestigious projects such as the National Highway Development


Project (NHDP), instead of scheduled maintenance strategies for
rational utilization of limited maintenance funds.
9. CONCLUSIONS

The following conclusions have been drawn on the basis of this study:

The practice of pavement management is absolutely essential on the


part of highway agencies, especially in developing country like India,
because of paucity of available maintenance funds. But the process of
development of PMS need to made simpler so that the field engineers
may be able to understand and utilize it effectively.

Internationally recognised HDM-4 system has been used for the


development of pavement management programmes for the National
Highway network in the country.

The pavement deterioration models incorporated into HDM-4 have


been calibrated using the pavement condition data collected on the
pavement sections and calibration factors for various deterioration
models such as cracking, ravelling, potholing and roughness models
have been obtained.

The validity of these models has been checked to test the efficacy of
these models, by comparing the distress predictions made by the
calibrated deterioration models with those actually observed on the
selected pavement sections.

The R 2 values obtained for cracking progression (0.98), ravelling


progression (0.79), and roughness progression (0.97) model show very
good agreement between observed and predicted values. Therefore,
these models have been used for prediction of distresses and the
development maintenance management strategies for the highway
network

Under project level PMS analysis, the optimum M&R strategy for a
pavement section has been determined on the basis of highest NPV/
Cost ratio, amongst a number of pre-defined M&R strategies. Similarly,
an optimum improvement strategy for another pavement section has
been determined.

The remaining service life for a number of pavement sections has been
determined which varies from 1 to 3 years, indicating that
reconstruction on most of the pavement sections would be inevitable
in the near future, in the absence of any sound maintenance management
policy.

DEVELOPMENT

PAVEMENT MANAGEMENT SYSTEM


NATIONAL HIGHWAY NETWORK

OF

FOR INDIAN

325

The adoption of condition responsive maintenance strategies in


comparison with the scheduled type of maintenance strategies indicate
a saving of more than 33 per cent in highway agency costs over an
analysis period of 20 years.
Under network level PMS analysis, an unconstrained works programme
has been prepared for a period of 10 years and the total budget
requirements for maintenance management of the whole highway
network at a pre-defined optimum serviceability level have been
determined, which comes out to be 1475.87 million Indian Rupees.
The budget requirements for maintaining the highway network at an
optimum serviceability level are almost 40 times more than those
required for maintaining it with only routine maintenance type of
activities.
Since the usual level of fund allocations for the maintenance
management of National Highways in India is of the order of 60 per
cent of the requirements only, therefore an optimized and prioritized
works programme has been prepared for 60 per cent budget availability.
The funds requirements for maintaining whole of the highway network
at the highest level of serviceability (Rs. 1871.8 million) is about 27
per cent more than those required for maintaining it at the optimum
level of serviceability. However, it would be possible to maintain the
same highway network at a medium level of serviceability at about 74
per cent of funds (Rs. 1089.1 million). But since the budget availability
is normally 60 per cent, it would just be possible to maintain this
highway network at the lowest level of serviceability.
The average roughness value of the highway network keep on
increasing with gradual reduction in budget levels, which in turn may
lead to very high road user cost values. The same is also true when the
maintenance activities are increasingly deferred beyond the year in
which they become due. Both these scenarios have a very detrimental
impact on the overall health of the highway network.
REFERENCES

1.

Aggarwal, S., Jain S.S., and M. Parida (2002) A Critical Appraisal of Pavement
Management Systems Vol. 63 No.2, IRC Journal, Indian Roads Congress, New Delhi,
pp 327-403.

2.

Bennet, C.R., and W.D.O. Paterson (2000) A Guide to Calibration and Adaptation,
HDM-4 Documentation Series, Volume-5, The World Road Association (PIARC), Paris,
France.

3.

Chakrabarti, S., Rawat, M.S., and B. Mondal (1995) Highway Design and
Maintenance Standards Model (HDM): Calibration and Adaptation to Indian
Conditions IRC Journal, Vol. 56, No. 1, pp 75-101.

326
4.
5.

6.
7.
8.
9.
10.

11.

12.

13.

14.
15.

16.

17.
18.
19.

20.
21.

AGGARWAL, JAIN & PARIDA ON DEVELOPMENT OF PAVEMENT MANAGEMENT


SYSTEM FOR INDIAN NATIONAL HIGHWAY NETWORK
CRRI (1994) Pavement Performance Study on Existing Pavement Sections, Final
Report, Central Road Research Institute, New Delhi.
Dattatreya, J.K., Veeraragavan A., Murthy, K., and C.E.G. Justo, (1992) A Suggested
Simplified System for Pavement Maintenance Management of Road Network, IRC
Journal, Vol. 53, No. 2, pp 217-273.
Fwa, T.F., and K.C. Sinha (1986) Routine Maintenance and Pavement Performance,
ASCE Journal of Transportation Engineering, Vol. 112, No. 4, pp 329-344.
George K.P., and A. Rajashekhran (1995) Future Directions in Pavement
Management, Proceedings, ICORT-95, University of Roorkee, Roorkee, pp 437-447.
Haas, R.C.G., and W.R. Hudson (1978) Pavement Management System, McGrawHill Book Company, New York, 1978
IRC: 81 (1997) Guidelines for Strengthening of Flexible Road Pavement using
Benkelman Beam Deflection Technique, Indian Roads Congress, New Delhi.
Jain S.S., and A.K. Gupta (1994) Development of Pavement Management System for
Indian Highway Network, Final Report of the R&D Project, Submitted to AICTE,
New Delhi by COTE, Department of Civil Engineering, UOR, Roorkee.
Jain, S.S., Gupta, A.K., Khanna, S.K., and E. Safa (1994) Development and
Application of Deterioration Models for Maintenance Management of Flexible
Pavements, An Invited Paper Published in the Proceedings of the Conference on Traffic
Safety of Two Continents and Strategic Highway Research Program (SHRP), Hague,
Netherlands.
Jain, S.S., Gupta, A.K., and S.K. Khanna (1996) Development of Maintenance and
Rehabilitation Investment Strategy for Flexible Pavements, IRC Journal, Vol. 57, No.
2, pp 367-418.
Jain, S.S., Parida, M., and M.M.S. Rawat (1999) A Rational Approach for Pavement
Management System for Urban Roads Highway Research Bulletin, IRC, No. 61, pp
69-99.
Kadyali, L.R. (1992) Study for Updating Road User Cost Data, L.R. Kadyali and
Associates, New Delhi.
Kennedy, C.K., Young, A.E., and I.C. Butler (1990) Measurement of Skidding
Resistance and Surface Texture and the Use of Results in the United Kingdom, Surface
Characteristics of Roadways: International Research and Technologies, ASTM STP
1031, American Society for Testing and Materials, Philadelphia, pp 87-102.
Kerali, H.R., McMullen, D., and J.B. Odoki (2000) HDM-4 Applications Guide,
HDM-4 Documentation Series, Volume-2, The World Road Association (PIARC), Paris,
France.
MORT&H (2001a) Report of the Committee on Norms for Maintenance of Roads in
India, Ministry of Road Transport & Highways, Government of India, New Delhi.
MORT&H (2001b) Road Development Plan Vision: 2021, Ministry of Road Transport
& Highways, Government of India, New Delhi.
MORT&H (2001c) Updation of Road User Cost Data, Final Report prepared by
Central Road Research Institute for Ministry of Road Transport & Highways,
Government of India, New Delhi.
Sharma, S.C. (1995) Recent PMS Studies in India, Indian Highways, May, 1995,
Indian Roads Congress, pp 21-29.
Snaith, M.S. (2002) Pavement Management, Presentation made at 62nd Annual
Session of the Indian Roads Congress, Kochi, India.

You might also like