Professional Documents
Culture Documents
Class 17 - Dabhol Case Study
Class 17 - Dabhol Case Study
Power Plant
Agenda
1.
Case Facts
Demand for power in India was set to grow in 1995
Growth of the Indian Power Sector
Capacity (MW)
160000
140000
120000
100000
80000
60000
40000
20000
0
2007
2002
1997
1995
1947
Time
Case Facts
State
65%
Capacity additions
Pricing/Tariffs
Power-related investments
State
Government
State
Government
Central/State
Government
State
Government
Relatively Autonomous
Executive
Legislative
Bodies
Bodies
(Administrative
(Politicians)
Service etc)
Judicial
Bodies
(Courts)
Constitutionally Independent
Reforms in India
More Reforms
Enron
Enron
EOC
ECT
EOG
EPP
EDC
Enrons Approach
To provide power
To earn profits
To obtain more projects if they were successful with their
first one
Enrons Approach
The contract
Risk Analysis
Risk
1. Economic/
Demand
2. Currency
3. Financial
4. Technical
5. Political
6. Social
7. Environ.
Mitigation
Strategy
Borne By
Ability to
bear
Magnitude
Through
MSEB
Contract -PPA
Through
MSEB/GoM/
Contract
GoI
Leverage Good
DPC
Credit Rating
Partner with
DPC
GE and Bechtel
PRI, Govt
OPIC/GoM/
Guarantees
GoI
DPC/MSEB/
GoM
Questionable
High
Questionable
Medium
Good
Low
Good
Low
Good
Low
Questionable
Medium-High
Questionable
Medium
Lobby GoI, WB
DPC
The Response
New Contract
Power Tariff
Rs 2.4/KwH
Rs 2.03/KwH in Ph
1 and Rs 1.84 in Ph
2
Capital Costs
Rs 90.6 Billion
Ownership
Enron-80;GE-10,
Bechtel-10
Enron-65;MSEB10%, GE,Bechtel 10
Fuel
LNG
Environment
Enron agrees to
manage this
The conclusion
June 2001 Phase 2 was in Progress and phase 1
was completed
MSEB defaulted on a payment
Counter guarantees provided by the
government in the contract did not work
Recourse to arbitration was taken once again
At this point Enron wanted to pull out of the
project
Economic Uncertainty
Strategies
Comprehensive Contracts
PPA
Payment Guarantee
International Arbitration
Enron followed most
Of these
Obsolescing Bargain
Strategies
Stagger Technology transfer
Undertake investments in
several stages
Enron followed few
Of these
Political Change
Strategies
Build support among public
Build support among media
Transparent bidding process
Bilateral ties with home countr
Invest WB, IMF have leverage
Enron followed none
Of these
Conclusion
Enron had initiated this project since it was in line with its
strategy
Enron had structured the project as a PPP very carefully,
building in guarantees into the contract, signing PPAs that
would ensure that the power that they generated would be
bought etc. Yet the project failed.
They may have benefited by slowing down their investment
strategy
They should have been more transparent in their approach
Enron should have made more attempts to garner political and social
support since these were the key elements that led to project failure
Thank you!