Professional Documents
Culture Documents
Construction Monthly Report: Project Title ABC - Qatar University Doha, State of Qatar
Construction Monthly Report: Project Title ABC - Qatar University Doha, State of Qatar
Contractor
Logo
Prepared by :
Contractor Name
Prepared for :
Qatar University
Consultant :
Contractor Name
March 2008
Contractor
Logo
Qatar University
Doha, State of Qatar
Table of Contents
1.
CONTRACT PARTICULARS
2.
EXECUTIVE SUMMARY
3.
4.
SCHEDULE
5.
SUBMITTALS
6.
7.
PROCUREMENT
8.
CONSTRUCTION
9.
COMMISSIONING
10.
QUALITY ASSURANCE
11.
FINANCIAL SUMMARY
12.
ATTACHMENTS
a. 4-Week Rolling Schedule
b. Contract Schedule
c. Change Order Log
d. Overall Progress S-Curve
e. Billings to Date versus Planned
f.
g. Trend Register
h. Drawing Release Curve by Facility
i.
j.
m. Progress Photos
Page 1 of 15
Project Title
1.
Contract Particulars
Client name
Consultant name
Contractor name
Original contract value
Revised contract value
Original Contract Period (days)
Revised Contract Period (days)
Percentage Time Elapsed
Amount of Penalty for Delay
Validity of Performance Bond
Validity of Contractors All Risk Policy
Page 2 of 15
Project Title
2.
Executive Summary
Summary
Describe the overall contract status during the current reporting period.
Include statements on safety, percent complete and significant
achievements. Describe major elements of work completed and near term
goals.
Critical Issues
Highlight any critical issues impacting the Contract Schedule and provide an
explanation of the positive actions being undertaken by the Contractor to
mitigate these issues.
Page 3 of 15
Project Title
3.
a.
Safety Statistics
Describe any Safety incidents that have occurred during the current month.
This Month
Year to date (2008)
Inception to date
Accident Free Man-Hours
Contractor
Lost
Restricted
First
Major
Minor
Near Miss
Statistics
Workday
Workday
Aid
Property
Property
Incidents
Cases
Cases
(FA)
Damage
Damage
(LWDC)
(RWDC)
(MAJPD)
(MINPD)
This Month
Year
to
date
(2008)
Inception to date
b.
Toolbox Topics:
Week 1: [Insert Topic Here]
Week 2: [Insert Topic Here]
Week 3: [Insert Topic Here]
Week 4: [Insert Topic Here]
Page 4 of 15
Project Title
c.
Environmental
Describe any Environmental incidents that have occurred during the current
month.
Previous
Report
Major
Environmental
This Report
Total to
Date
Incident
(MAJENV)
Minor
Environmental
Incident
(MINENV)
Page 5 of 15
Project Title
4.
Schedule
a.
Page 6 of 15
Contract
Schedule
Forecast/ Actual
Date
Delta
Contract
15-Mar-06
15-Mar-06
16-May-06
16-May-06
15-Jul-06
15-Jul-06
14-Sep-06
14-Sep-06
14-Feb-07
14-Feb-07
15-Jul-06
15-Jul-06
15-Jul-06
15-Jul-06
15-Jul-06
15-Jul-06
15-Jul-06
15-Jul-06
13-Aug-06
13-Aug-06
15-Oct-06
15-Oct-06
12-Dec-06
12-Dec-06
7-Nov-06
7-Nov-06
21-Feb-07
21-Feb-07
14-May-06
14-May-06
18-Feb-07
18-Feb-07
14-Sep-06
14-Sep-06
5-May-07
5-May-07
22-Jul-07
22-Jul-07
22-Sep-07
22-Sep-07
22-Sep-07
22-Sep-07
22-Jan-08
22-Jan-08
22-Jun-08
22-Jun-08
31-Jul-08
31-Jul-08
22-Aug-07
22-Aug-07
19-Aug-07
19-Aug-07
21-Oct-07
21-Oct-07
20-Nov-07
20-Nov-07
Project Title
A = Actual
b.
17-Jan-08
17-Jan-08
31-Jul-08
31-Jul-08
22-Jul-08
22-Jul-08
22-May-08
22-May-08
22-May-08
22-May-08
22-May-08
22-May-08
F = Forecast
Schedule Analysis
Provide a schedule analysis with reference to:
contract percent complete
status against contract milestones
critical status against path
any deviations from the agreed manpower and equipment
utilization curves
c.
Critical Issues
List of critical issues impacting the Contract Schedule and mitigation
measures being adopted to recover any schedule slippages
Page 7 of 15
Project Title
5.
Material Submittals
Civil
Architectural
Electrical
Mechanical
Total
Civil
Architectural
Electrical
Mechanical
Total
Civil
Architectural
Electrical
Mechanical
Total
Drawings
Total Drawing Submittals
Submitted for Approval
Approved
Design Calcs/Specs
Total Specs Submittals
Submitted for Approval
Approved
Page 8 of 15
Project Title
6. Critical Issues
Describe (using bullets) the critical issues / Action needed :
Page 9 of 15
Project Title
7. Procurement
Describe (using bullets) the procurement status under the following
headings:
Accomplished this month
Areas of Concern
Award Date
Planned
Actual
[Insert Name]
[Insert Name]
[Insert Name]
[Insert Name]
Page 10 of 15
Project Title
8. Construction
Describe (using bullets) the construction status under the following
headings:
Accomplished this month
Areas of Concern
Page 11 of 15
Project Title
9. Commissioning
Describe (using bullets) the commissioning status under the following
headings:
Accomplished this month
Areas of Concern
Page 12 of 15
Project Title
Areas of Concern
Page 13 of 15
Project Title
Item
QAR
Page 14 of 15
Project Title
12. Attachments
General
Contract Schedule
Trend Register
Construction
Progress Photos
Page 15 of 15
Project Title