You are on page 1of 80

STANDARDS PUBLICATION

QP TECHNICAL SPECIFICATION FOR


PAINTING AND WRAPPING
OF METAL SURFACES
(NEW CONSTRUCTION & MAINTENANCE)

DOC NO: QP-SPC-L-002


(FORMERLY QGPC ES-Q-12)

REVISION 1

STANDARDS PUBLICATION

QP TECHNICAL SPECIFICATION FOR PAINTING


AND WRAPPING OF METAL SURFACES
(NEW CONSTRUCTION & MAINTENANCE)

DOC NO: QP-SPC-L-002


(FORMERLY QGPC-ES-Q-12)

15/1/2002

Date

Rev.

Issued as
Revised QP
Standard
Specification

Description

Doc. File No.: SPC.L002.R1

QAM/1
Prepared
By

QAM
Reviewed
By

Page 1 of 79

QA
Approved
By

SQ

DT

DO

Corporate Endorsement

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE OF CONTENTS
Page No.
FOREWORD

1.0

OBJECTIVE

2.0

SCOPE

3.0

APPLICATION

4.0

TERMINOLOGY
4.1 Abbreviations
4.2 Definitions

7
7
7

5.0
5.1
5.2
5.3
5.4
5.5
5.6
6.0
7.0
7.1
7.2
7.3
7.4
7.5
7.6

REFERENCE STANDARDS AND CODES


Painting and Coating General
Surface Preparation
Inspection and Testing
Colour Coding
Health, Safety and Environment
Priority of Reference Standards and Codes

10
10
11
12
13
13
14

GENERAL CONTRACTOR REQUIREMENTS

14

HEALTH, SAFETY AND ENVIRONMENTAL REQUIREMENTS


General Health and Safety Considerations
Access Facilities and Scaffolding
Blasting and Spray Painting Equipment
Paints, Solvents and Abrasives
Personnel Protective Equipment
Paint, Solvent, Chemical and Waste Material Disposal

15
15
16
17
17
18
19

8.0

PAINTING OF NEW EQUIPMENT AND STRUCTURES


8.1 General Requirements
8.2 Vendor Standard Coating Systems
8.3 Materials and Equipment Not to be Painted

19
19
20
21

9.0

PAINTING OF EXISTING EQUIPMENT AND STRUCTURES


9.1 General Requirements

21
21

Doc. File No.: SPC.L002.R1

Page 2 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

Page No.
10.0 SURFACE PREPARATION
10.1 Preparatory Grinding and Degreasing
10.2 General Blast Cleaning Requirements
10.3 Dry Blast Cleaning
10.4 Wet Abrasive Blast Cleaning and Water Jetting
10.5 Power Tool Surface Preparation
10.6 Mechanical Hand Tool Surface Preparation
10.7 Chemical Pickling

22
22
23
25
26
27
28
28

11.0 PAINT APPLICATION


11.1 Paint Suitability, Storage and Mixing
11.2 Paint Application Equipment
11.3 Paint Application Methodology
11.4 Repair of Damaged Paintwork

28
28
29
30
32

12.0 WRAPPING TAPE APPLICATION


12.1 Tape Suitability and Storage
12.2 Surface Preparation
12.3 Tape Application Methodology
12.4 Repair of Damaged Wrapping Tape
12.5 Protection of Threaded Connections and Flanged Joints

32
32
33
34
35
35

13.0 INSPECTION DURING SURFACE PREPARATION AND COATING


13.1 General Inspection Requirements
13.2 Inspection System Requirements
13.3 Inspection of Equipment, Materials and Access
13.4 Inspection Equipment Requirements

36
36
37
39
42

14.0

QUALITY ASSURANCE REQUIREMENTS

43

15.0

DOCUMENTATION

44

16.0

PROTECTIVE SYSTEM CLASSIFICATION BY AREA, SERVICE


AND MATERIAL

45

17.0

COATING AND WRAPPING SCHEDULES

18.0

COLOUR CODING AND IDENTIFICATION SCHEDULES

Doc. File No.: SPC.L002.R1

Page 3 of 79

46-63
64

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

Page No.
19.0

APPENDICES

19.1

APPENDIX A. TABLES
Corresponding Degrees of Paint Rusting Standards
Corresponding Surface Preparation Standards
Painting and Wrapping Quality Inspection and Test Plan Checklist
Painting and Wrapping Daily Inspection Report
Painting and Wrapping Close Out Inspection Report
Colour Coding Scheme for Equipment
Colour Coding Scheme for Pipework, Valves and Fittings
Colour Coding Scheme for Hazards and Fire and Safety Signs
Colour Coding Scheme or Industrial Gas Cylinders
Respiratory Personnel Protective Equipment
Eye and Face Personnel Protective Equipment
Foot and Body Personnel Protective Equipment

1
2
3
4
5
6
7
8
9
10
11
12

19.2
1
19.3

65
65
66
66
67-68
69
70
71
72
73
73
74
74
74

APPENDIX B. FIGURES
Zones of Offshore Structures for Corrosion Protection

75
75

APPENDIX C.
MINIMUM FORCED VENTILATION REQUIREMENTS

76

REVISION HISTORY LOG

Doc. File No.: SPC.L002.R1

77-79

Page 4 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

FOREWORD
This document has been developed by Facilities Quality Assurance Department (FQAD),
reviewed by QP User Departments and endorsed by QP Management for use as the QP
Technical Specification for the Painting and Wrapping of Metal Surfaces (New
Construction and Maintenance).
The document is published for QP Departments, Contractors and Consultants utilization for the
painting and wrapping of metallic equipment, structures and components other than subsea
pipelines and the Splash Zone section of riser lines. It is emphasised that the requirements of
the document should be adopted and utilised in their entirety for all such work undertaken for
QP whenever applicable and appropriate.
This document is the first revision of former QP Standard ES-Q-12, the original version of
which was issued in April 1996. It supersedes that document and has been renumbered in line
with the present Standards Numbering System. The document in its present form reflects as
far as possible the current QP requirements for this type of work, taking account of the present
industrial practices, materials and technology and the latest applicable National and
International Standards and Codes. It will be subject to further periodic review, to re-affirm its
adequacy, conform to any changes in QP requirements and include new developments in the
field.
It is recognised that there will be situations where addenda, data sheets or points of
clarification require to be attached to the document, in order to suit a specific application or
service environment. In such situations, the contents shall not be changed or re-edited by any
user but any addenda or clarifications that would entail major changes shall be brought to the
attention of the Custodian Department. Any proposed exceptions or deviations from this
Specification shall also be submitted, together with justification, to the Custodian Department
for review and consideration.
The Custodian of this document is Facilities Quality Assurance Department. All technical
comments, opinions and recommendations on the contents should therefore be sent to:
Facilities Quality Assurance Department Manager
Building No 5, Ras Abu Aboud
P.O. Box No 47
DOHA, Qatar
Tel: 4402205
Fax: 4402207

Doc. File No.: SPC.L002.R1

Page 5 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

1.0

OBJECTIVE

1.1

The objective of this Specification is to define the QP requirements for the protective
painting and wrapping of all new and existing metallic equipment, structures and
components and the specific requirements for different types of equipment, service
environment and constructional material.

1.2

It provides a technical basis for developing individual painting and wrapping project
specifications, coating schedules and purchase requisitions. It also enables the
painting and wrapping work carried out by Contractors to be monitored for compliance
with specification requirements.

2.0

SCOPE

2.1

This document specifies the minimum QP standards for the surface preparation,
painting and wrapping of metallic equipment, structures and components, including
inspection, testing and reporting, for corrosion protection and aesthetic purposes during
new construction and maintenance.

2.2

It covers the general, safety, environmental and quality control requirements for the
materials used and the surface preparation of, and application of paint and wrapping
tape to, the exterior of vessels, tanks, process equipment, pipework and structural
steelwork and the interior of vessels and tanks.

2.3

It identifies the specific painting and wrapping system requirements for items to be
painted for individual applications, based upon the nature of the service conditions and
environment and the constructional materials involved. It details the specific surface
preparation and paint system and wrapping tape requirements, including the standard
of surface cleanliness and roughness, the number of coats of each type of paint or tape
and their film thickness.

2.4

The following items are outside the scope of this document:


(a)
External coating of sub-sea pipelines, which is covered in QP-SPC-L-004.
(b)
External coating of the Splash Zone section of riser lines, which is covered in
QP-SPC-L-003.
(c)
Internal cement-based lining of pipework and vessels.

3.0

APPLICATION

3.1

This Specification shall be used for all painting and wrapping of newly constructed
equipment and structures, including repair during and after installation, and for the field
maintenance painting and wrapping of existing equipment, from local touch up work to
total refurbishment.

3.2

All surface preparation, paint application and wrapping shall be carried out in
accordance with this Specification and the Paint Manufacturers' recommendations. In
the case of conflict between this Specification and the Paint Manufacturer's
recommendations, the latter shall apply.

Doc. File No.: SPC.L002.R1

Page 6 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

4.0

TERMINOLOGY

4.1

ABBREVIATIONS
The following abbreviations shall apply.
COSHH

Control of Substances Hazardous to Health

DFT

Dry Film Thickness

FBE

Fusion Bonded Epoxy Coating

LEL

Lower Explosive Limit

MIO

Lamellar Micaceous Iron Oxide Pigment

MSL

Mean Sea Level

PPE

Personnel Protective Equipment

QA/QC

Quality Assurance/Quality Control

QP

Qatar Petroleum

TEL

Threshold Exposure Limit

TDFT

Total Dry Film Thickness

WFT

4.2

REVISION 1

Wet Film Thickness

DEFINITIONS
The following definitions shall apply.
Amplitude

The average peak to trough height of the profile of a steel surface after
preparation by abrasive blast cleaning (see Profile).

Applicator

A party to a contract who is responsible for the application of paint


coatings and wrappings, including all surface preparation. An Applicator
may be a Contractor or nominated Sub-contractor

Atmospheric The part of an onshore structure or facility that is above ground


Zone
level and the part of a marine structure above the Splash Zone that is
subject solely to atmospheric exposure during service.
Coating

A continuous film or layer of a suitable substance that is applied to the


surfaces of an item for protective or aesthetic purposes.

Consultant

A party to a contract who is responsible for providing design engineering


and other consultancy services under the contract.

Doc. File No.: SPC.L002.R1

Page 7 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

Contractor

The party, firm or company with whom QP enters into a contract to


perform the work to which this Specification applies.

Degree of
Paint
Rusting

The quantity and size of the areas of a painted steel surface in which
deterioration of the paint film by rust breakthrough and underrusting is
evident, expressed as a percentage of the total surface area.

Dewpoint

The temperature at and below which aqueous condensation formation


from the air starts to occur as a result of it becoming supersaturated with
water vapour. It will be governed by the Relative Humidity of the air,
higher values of which produce an increase in the dewpoint temperature

Dry Film
Thickness

The thickness of a coat of paint, layer of tape or coating system in


its fully cured condition.

Dry Abrasive A cleaning procedure in which a suitably sized and shaped dry metallic
Blast
or non-metallic abrasive is mixed with compressed air and fired at metal
Cleaning
surfaces at a pressure of around 100 psig to remove corrosion
products, paint and other surface residues.
Elevated
Surface of
the equipment or facility
Temperature temperature in excess of 120C during service.

that

will

attain

Fusion
Bonded
Epoxy

An epoxy coating that is applied to preheated pipe as a powder by


electrostatic spray, rapidly cured by the controlled heat from the pipe and
water quenched to give a fusion bonded coating.

Fabricator

Organization responsible for the construction or fabrication of new


facilities and the installation of items of equipment therein.

Hold Points

Steps within the surface preparation and application procedure beyond


which the applicator shall not proceed without formal authorization via
an inspection report from the QP Engineer or Authorised Representative

Holidays

Discontinuities such as pinholes and small sized defects in the paint or


wrapping film that significantly lower the dielectric strength of the coating

Hot Dip
A process by which steel articles are coated with zinc by controlled
Galvanising immersion in a molten zinc bath.
Hot Surfaces Metal surfaces on the equipment or facility that will normally attain a
temperature in excess of 65C and can therefore be injurious to
personnel touching them.
Inspector

The QP Engineers Appointed Representative delegated to witness


QA/QC requirements and report on the compliance or non-compliance
with these requirements.

Doc. File No.: SPC.L002.R1

Page 8 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

Lining

REVISION 1

A protective coating on the internal surface of a vessel or pipe.

Manufacturer A party responsible for manufacture of equipment or materials to


perform duties specified by QP or its nominated consultants.
May

An acceptable option or options under the contract.

Microns

One thousandth of a mm (expressed as m).

Mouse Hole

A small hole cut in a steel plate or section to either bridge a weld or


provide a drainage point.

Paint
System

The number and type of coats of paint to be applied to a substrate to


provide a required level of corrosion protection.

Painting

The application to a substrate of one or more layers of a pigmented


coating material, in liquid, paste or powder form, which forms an opaque
film having protective properties.

Pigment

Solid filler or colouring agent in a paint.

Potlife

The length of time that a single pack or mixed two-pack paint will remain
in a usable condition at a given temperature.

Profile

The roughness or contour of a steel surface after preparation, also


known as the Anchor Pattern (see also Amplitude).

Qatar
Petroleum

The Corporation. Any actions taken by QP shall be taken to include


actions taken by an Appointed Agent of Qatar Petroleum.

Qatar Petroleum The Appointed QP Representative under the conditions of the


Engineer
contract.
Relative
Humidity

The mass of water vapour in the air expressed as a percentage of the


mass of water vapour that is required to saturate the same volume of air
at the same temperature.

Shall

A mandatory requirement to be strictly followed under the contract.

Shelf Life

The Manufacturers recommended maximum storage time for a given


product under recommended storage conditions.

Shop

The Vendors, or Sub-contractors, factory location for surface


preparation and painting operations.

Should

A strong but non-mandatory recommendation to comply with the


contract requirements.

Doc. File No.: SPC.L002.R1

Page 9 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

Site

REVISION 1

The field location for surface preparation and painting operations


approved by QP.

Splash Zone The portion of a partially immersed marine structure or pipeline that is
subject to both wetting by seawater or sea spray and drying by the
marine atmosphere. It is to be taken as being from 3.00m (10 feet)
below MSL to +4.5m (15 feet) above MSL (see Figure 1).
Submerged
Zone

The immersed portion of a marine structure from the seabed up to


3.00m (10 feet) below MSL (see also Splash Zone and Figure 1).

Substrate

The metal surface to be prepared and coated.

Thinner

An approved liquid added to a paint to reduce the viscosity and ease its
application.

Total Dry
The thickness of the complete fully cured coating or wrapping system.
Film Thickness
Vendor

The Organization responsible for manufacturing, fabricating or supplying


any items for delivery to the Fabricator or QP.

Wet Abrasive A cleaning procedure in which a mixture of a suitable abrasive in fresh


Blast
water is fired at metal surfaces at a pressure of up to 2000 psig to
Cleaning
remove corrosion products, paint and soluble salts.

5.0

Water
Cleaning /
Jetting

Cleaning procedures in which fresh water, which may contain a corrosion


inhibitor, is fired at surfaces at a pressure of from less than 5,000 psig to
over 25,000 psig to remove scale, corrosion products and soluble salts.

Wet Film
Thickness

The thickness of a paint film immediately after application when little


or no solvent evaporation has occurred.

Will

An essential action or need to meet the mandatory requirement.

Wrapping

The application to a component of a continuous strip of plastic-backed


self-adhesive tape that is wound on in a helical manner for protective
purposes.

REFERENCE STANDARDS AND CODES


The latest editions of the following Standards, Codes and Specifications shall apply.

5.1

PAINTING AND COATING - GENERAL


ASTM A123/M Standard Specification for Zinc (Hot Galvanized) Coatings on Iron and
Steel Products.

Doc. File No.: SPC.L002.R1

Page 10 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

ISO 1461

REVISION 1

Hot-Dip Galvanized Coatings on Fabricated Iron and Steel Articles


Specifications and Test Methods.

ISO 12944-1-8 Paints and Varnishes Corrosion Protection of Steel Structures by


Protective Paint Systems.
ISO 14713

Protection Against Corrosion of Iron and Steel in Structures Zinc and


Aluminium Coatings.

BS EN 22063 Metallic and Other Inorganic Coatings - Thermal Spraying.


SSPC Manual Vol. 1. Good Painting Practice.
Vol. 2. Systems and Specifications.

5.2

SURFACE PREPARATION
ASTM D2092 Standard Guide for Preparation of Zinc Coated (Galvanized) Steel
Surfaces for Painting.
ISO 8501-1 /
SIS 055900 /
BS 7079-A1
& Supp.

Preparation of Steel Substrates Before Application of Paints and


Related Products - Visual Assessment of Surface Cleanliness. Part 1:
Rust Grades and Preparation Grades of Uncoated Steel Substrates
and Steel Substrates After Removal of Previous Coatings.

ISO 8503-1-4 / Preparation of Steel Substrates Before Application of Paints and


BS 7079-C1-4 Related Products Surface Roughness Characteristics of Blast
Cleaned Steel Surfaces.
ISO 8504-2 /
BS 7079-D2

Preparation of Steel Substrates Before Application of Paints and


Related Products Surface Preparation Methods. Part 2: Abrasive
Blast Cleaning.

ISO 8504-3 /
BS 7079-D3

Preparation of Steel Substrates Before Application of Paints and


Related Products Surface Preparation Methods. Part 3: Hand and
Power Tool Cleaning.

ISO 11124-1-4 / Preparation of Steel Substrates Before Application of Paints and


BS 7079-E1-E4 Related Products -Specifications for Metallic Blast Cleaning Abrasives
ISO 11126-1-10 / Preparation of Steel Substrates Before Application of Paints and
BS 7079-F1-F10 Related Products Specifications for Non-Metallic Blast Cleaning
Abrasives.
SSPC Vis 1

Visual Standard for Blast Cleaned Steel.

SSPC Vis 3

Visual Standard for Power- and Hand-Tool Cleaned Steel

SSPC SP 1-3, 5-8, Steel Structures Painting Council and National Association of
10&11 / NACE 1-4 Corrosion Engineers Surface Preparation Standards.
Doc. File No.: SPC.L002.R1

Page 11 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

SSPC SP12 / Surface Preparation and Cleaning of Steel and Other Hard Materials by
NACE 5
High- and Ultrahigh- Pressure Water Jetting Prior to Recoating.
NACE RP 0178 Fabrication Details, Surface Finish Requirements and Proper Design
Considerations for Tanks / Vessels to be Lined for Immersion Service.

5.3

INSPECTION AND TESTING


ASTM D610 / Standard Test Method for Evaluating Degree of Rusting on
SSPC Vis 2
Painted Steel Surfaces.
ASTM D1186

Standard Test Methods for Non-Destructive Measurement of Dry Film


Thickness of Non-Magnetic Coatings Applied to a Ferrous Base.

ASTM D1212 Standard Test Methods for Measurement of Wet Film Thickness of
Organic Coatings.
ASTM D3276

Standard Guide for Painting Inspectors (Metal Substrates).

ASTM D3359

Standard Test Methods for Measuring Adhesion by Tape.

ASTM D4228 Standard Practice for Qualification of Coating Applicators for Application
of Coatings to Steel Surfaces.
ASTM D4285

Standard Test Method for Indicating Oil or Water in Compressed Air.

ASTM D4414 Standard Practice for Measurement of Wet Film Thickness by Notch
Gages.
ASTM D4417 Standard Test Methods for Field Measurement of Surface Profile of
Blast Cleaned Steel.
ASTM D4541

Standard Test Method for Pull-Off Strength of Coatings Using Portable


Adhesion Testers.

ASTM E337

Standard Test Method for Measuring Humidity with a Psychrometer


(Wet and Dry Bulb Temperatures).

ASTM F21

Standard Test Method for Hydrophobic Surface Films by Atomiser Test.

ISO 4628-1-6 / Evaluation of Degradation of Paint Coatings - Designation of Intensity,


BS3900-H1-4 Quantity and Size of Common Defects - Blistering, Rusting, Cracking,
Flaking and Chalking.
ISO 8502-1-10/ Preparation of Steel Substrates Before Application of Paint and
BS7079-B2-10 Related Products Tests for Assessment of Surface Cleanliness.
ISO 9001

Quality Management Systems Requirements.

Doc. File No.: SPC.L002.R1

Page 12 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

SSPC PA 2

REVISION 1

Measurement of Dry Paint Thickness with Magnetic Gauges.

NACE RP0188 Discontinuity (Holiday) Testing of Protective Coatings.


NACE RP0287 Surface Profile Measurements of Abrasive Blast Cleaned Steel
Surfaces Using a Replica Tape.
NACE RP0490 Holiday Detection of Fusion Bonded Epoxy External Pipeline Coatings
of 10-30 Mils.
QSP-QC-09

5.4

Quality Requirements for Projects.

COLOUR CODING
BS EN 1089-3 Identification of Contents of Industrial Gas Containers.
BS 381C

Colour for Identification, Coding and Special Purposes.

BS 1710

Identification of Pipelines and Services.

BS 4800

Paint Colours for Building Purposes.

BS 5378-1 & 3 Safety Signs and Colours : Colour and Design.

5.5

HEALTH, SAFETY AND ENVIRONMENT


OSHA 29 CFR Regulation Pertaining to Work in Confined Areas.
API 2217A

Guidelines for Work in Inert Confined Spaces in the Petroleum Industry

BS 5973

Code of Practice for Access and Working Scaffolds and Special


Scaffold Structures in Steel.

QP-PHL-S-001 Corporate Fire and Safety Philosophy.


QP

Safety Regulations for Contractors.

QP

Onshore and Offshore Safety Standards.

QP-SPC-V-001 EMS Specification for Waste Management.


QP-GDL-V-001-5 EMS Guidelines: Waste (Solid and Liquid) Management.
NIOSH (U.S.A.) Occupational Safety and Health Guidelines for Chemical Hazards.
HSE (U.K.)

Control of Substances Hazardous to Health Regulations, 1999.

Paint Manufacturer Product and Material Safety Data Sheets


Doc. File No.: SPC.L002.R1

Page 13 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

5.6

REVISION 1

PRIORITY OF REFERENCE STANDARDS AND CODES


In the event of conflict arising between this Specification and the National and
International Standards and Codes referenced herein, the requirement of this
Specification shall apply, unless otherwise specified.

6.0

GENERAL CONTRACTOR REQUIREMENTS

6.1

The Contractor shall, unless otherwise formally instructed by QP, supply all required
materials, such as approved blast cleaning abrasives for preparing surfaces and
approved paints, thinners and wrapping tapes for coating and wrapping them in
accordance with this Specification.

6.2

The Contractor shall, unless otherwise formally instructed by QP, provide all
equipment and tools necessary to carry out the surface preparation and coating
work in an effective and efficient manner. All equipment and tools shall arrive in
good working order and in a sufficiently clean condition that they do not cause
contamination of the coating. They shall be maintained in good working order at all
times. The Contractor shall supply all materials, such as oils, greases, cleaners and
spare parts, that are required for equipment maintenance purposes.

6.3

The Contractor shall provide and maintain on site in good condition for the duration of
the work all inspection equipment that is required to carry out the painting and wrapping
fully in accordance with the Specification.

6.4

The Contractor shall provide the required number of experienced and skilled personnel,
together with experienced, competent and qualified supervision, to carry out the work to
the required standard and within schedule, using good general painting practices as
laid down in Volume 1 of the SSPC Manual.

6.5

At QPs discretion, the Contractor shall:


(a)

Submit documentation of his previous experience with the application of the


same or similar coatings or wrappings.

(b)

Before starting any coating work under the contract, prepare test panels of the
design specified in ASTM D4228 for the evaluation of the proposed application
personnel and equipment capabilities and paint them with the specified coating
system in the proposed manner.

(c)

Have the test panels evaluated in accordance with ASTM D4228 to qualify such
personnel that are considered to have applied the specified coating to an
acceptable standard.

(d)

Ensure that all required testing and qualification work is witnessed and evaluated
by the QP Engineer and, if appropriate, the Paint Manufacturers Representative.

Doc. File No.: SPC.L002.R1

Page 14 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

6.6

Prior to commencement of the work, the Contractor shall submit for the QP Engineers
approval a detailed procedure showing how he intends to carry out the work in
accordance with this Specification. He shall provide full details of any Sub-contractor
that he intends to use, the location of each part of the work, the preparatory and coating
materials that he intends to use and any other information that QP may require to clarify
his work intentions.

6.7

The required standard of workmanship shall be achieved strictly in accordance with this
Specification and other relevant documents, such as site and safety regulations and
applicable Standards and Codes. Deviations from the Specification and documents are
not allowed, unless formally authorised by QP.

6.8

The Contractor shall be responsible for protecting all adjacent equipment, structures
and surrounding facilities that are not to be coated from mechanical damage, blasting
abrasive, paint splashes and overspray during the surface preparation and coating
work. Instruments, equipment identification plates, electrical and isolating flange
components and machined surfaces are especially important in this respect. The
Contractor shall take particular care to mask these components against such damage
and contamination.

6.9

The Contractor shall maintain at each job site a log which shall consist of Daily
Progress Forms. These forms could be a management summary or the Daily
Inspection Report Forms for the contract, the required contents of which are detailed in
Sub-clause 13.2.5 and a typical format of which is shown as Table 4. They shall be
signed on a daily basis by the Site Supervisor or Engineer-in-Charge and submitted to
the QP Engineer. In the event that the work is carried out at an approved offsite location
or outside of Qatar, the Daily Progress Report Forms shall form part of the required
project documentation.

6.10

No surface preparation and/or coating application work shall be carried out in the
absence of the QP Engineer or without his knowledge or consent. Any such work shall
be considered not to meet the Specification.

6.11

The Contractor shall be directly responsible to QP for completion of all work. No


distinction is made between the responsibilities and liabilities of the Fabricator, Vendor
or Contractor. This Specification shall be equally binding on all parties. The Contractor
is liable for his actions and those of his Sub-contractors.

6.12

Any prepared, coated or wrapped areas that are considered to be defective or in any
way not to conform with this Specification shall be rectified by the Contractor. Any
instruments, components or adjacent equipment that is damaged or coated shall be
cleaned or replaced at the discretion of the QP Engineer.

7.0

HEALTH, SAFETY AND ENVIRONMENTAL REQUIREMENTS

7.1

GENERAL SAFETY AND HAZARD CONSIDERATIONS

7.1.1 The Contractor shall be responsible for carrying out all surface preparation, painting
and wrapping work in a completely safe and professional manner, in addition to
Doc. File No.: SPC.L002.R1

Page 15 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

meeting all QP technical and quality control standards. This will require him to provide
good and safe access facilities and working conditions, appropriate preparatory, coating
and inspection equipment in good working order and suitable personnel protective
equipment and safety devices.
7.1.2. The Contractor shall fully comply with QP health, safety and environmental
requirements specified in the QP Safety Regulations for Contractors, Corporate Fire
and Safety Philosophy and QP Onshore and Offshore Safety Standards. These cover
working conditions, scaffolding and access, protective clothing, safety equipment, fire
and explosion hazards, solvents, lighting, ventilation and earthing of equipment and
components.
7.1.3 The Contractor shall prepare a detailed Safety Assessment Report for the job at the
worksite at the outset. This shall identify all potential safety, health and environmental
hazards that could arise and ensure that all necessary preventive measures and
equipment to avoid each potential hazard are adopted and made available. The Safety
Assessment Report shall be approved by the QP Safety Officer before starting work.
7.1.4 The Contractor shall ensure that all fire fighting equipment required is in position at all
times in all identified hazardous areas, such as paint mixing locations, at vessel entries
and close to approved diesel-driven equipment.
7.1.5 The Contractor shall carry out documented Safety Audits of the access facilities,
preparatory and painting equipment and materials, personnel protective equipment and
surface preparation, painting and wrapping practices used at an agreed frequency,
which should be at least monthly. He shall maintain a Log in which he records the
findings and actions taken, for review by the QP Safety Officer.

7.2

ACCESS FACILITIES AND SCAFFOLDING

7.2.1 The Contractor shall provide safe and easy access to all areas of surfaces of
components and equipment that are to be prepared and coated. This shall enable the
specified method and standard of surface preparation, painting and wrapping to be
achieved and confirmed by inspection. The access arrangement shall be such that
operators are able to stand up with body and arms free of scaffolding or staging. None
of the scaffolding or staging members shall be in direct contact with the component that
is being worked on and masking of any area of the component shall be minimised.
7.2.2 The access facility may be permanent or temporary but shall in all cases be subject to
approval by the QP Safety Officer. Scaffolding shall comply with the QP Safety
Regulations. The Contractor shall supply and maintain rigging and scaffolding
equipment capable of enabling completion of the work in accordance with the
requirements of BS 5973. Its safety and security shall be regularly checked and
recorded in accordance with a recognised scaffolding safety inspection and auditing
system, such as the Scafftag System.

Doc. File No.: SPC.L002.R1

Page 16 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

7.3

REVISION 1

BLASTING AND SPRAY PAINTING EQUIPMENT

7.3.1 Air hoses, blasting hoses, spray lines and any other hoses that are subjected to any
internal pressure shall be marked with identification numbers showing the dates when
they were manufactured and first used. All such hoses, blasting pots any other
pressurized equipment shall be provided with valid dated pressure test certificates
stating the test pressures used and the safe working pressures that must not be
exceeded. The Contractor shall ensure that all hoses and pressurised components are
carefully inspected for signs of wear and the presence of defects prior to each use and
that no hoses are used for more than six months after their last test date. They shall
then be fully inspected and retested at their design pressure before being remarked and
certified for a further period of use. All compressor air and blasting hose couplings shall
be secured using approved stainless steel snatch wires.
7.3.2 Blast cleaning and spray painting equipment shall be used fully in accordance with
Manufacturers recommendations. The air feed, blasting and spray painting hoses shall
incorporate a suitable anti-static material in their construction. The guns shall be fully
earthed and spark proofed on each occasion when they are used. All other precautions
shall be taken to prevent any build up of electrostatic charge, particularly when they are
to be used in confined spaces. The Contractor shall check all such items for electrical
conductivity and replace any items showing signs of breakdown that could give rise to
static electrical discharges during service.
7.3.3 Blasting nozzles shall be fitted with a Deadmans Handle located as close to the blast
nozzle as practical. Its design must ensure that the Handle cannot, in any
circumstances, be held in the ON position by any means other than hand pressure.
Paint spray guns shall be fitted with effective Manufacturers trigger lock and tip guards.
7.3.4 Areas in which blast cleaning is carried out shall be sheeted in and cordoned off as
necessary for safety purposes and to minimise contamination of adjacent areas.
Warning signs shall be erected as requested by the QP Engineer. This shall exclude all
unauthorised personnel that could be injured by stray spent abrasive or harmful dust
from old paintwork. Where power tools are being used to remove old paint or rust,
precautions shall also be taken to exclude unauthorised personnel from the work area
and minimise contamination.

7.4

PAINTS, SOLVENTS AND ABRASIVES

7.4.1 The Contractor shall ensure that the Manufacturers Material Safety Data Sheets and
NIOSH(USA) / COSHH(UK) Statements are available for all paints, solvents, chemicals
and abrasives used throughout the work period. Compliance with Manufacturers safety
precautions for products shall be an essential element in meeting the job specification.
In cases of conflict, the most stringent safety requirements and precautions shall apply.
7.4.2 All paints, solvents, equipment cleaners and other chemicals used shall be stored in
closed, clearly labelled original containers. The containers shall be stored in secure
enclosed, sheltered and well-ventilated storage areas or structures, where they are
protected from direct sunlight, open flames and electrical discharges. They must be
maintained at temperatures well below the Manufacturers maximum recommended
Doc. File No.: SPC.L002.R1

Page 17 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

storage temperature for the products. The use of air-conditioned storage areas shall be
considered for situations where excessive ambient temperatures are expected. The
storage conditions shall meet all Manufacturer requirements and QP Fire and Safety
Regulations for the types of chemical involved.
7.4.3 Abrasives used shall be free from toxic or harmful substances such as arsenic, lead,
cyanide and free silica. They shall not produce excessive quantities of fine dust that
could cause environmental damage.
7.4.4 Handling and mixing of all paints, solvents and chemicals shall be carried out strictly in
accordance with the Manufacturers recommended procedures and safety and health
precautions, to ensure personnel safety. Safety precautions shall be clearly detailed on
the relevant product technical data sheets, as well as on the product containers. Where
a specification indicates restrictions on the use of certain chemicals, adherence to these
restrictions is considered mandatory.
7.4.5 The Contractor shall apply the products strictly in accordance with the Manufacturers
safety recommendations, which shall also be clearly detailed on the relevant Product
Technical Data Sheets. Application of solvent-borne paints in restricted areas or inside
vessels or tanks requires particularly careful planning and attention. Good ventilation
through such vessels is essential, to ensure that the threshold exposure limit (TEL) and
lower explosive limit (LEL) of the vapour is not exceeded at any time. The Contractor
shall ascertain the TEL and LEL of the solvents contained in all paint products used, to
establish the level of ventilation that he is required to provide. Where this cannot be
achieved by natural ventilation, a forced ventilation system using a suitable air eductor
and incorporating equipment for measuring the air flow shall be installed. A method for
calculating the minimum forced air ventilation requirement for an enclosed space is
given in Appendix C. Good ventilation is generally required in paint mixing and thinning
areas, if these are enclosed.
7.4.6 The Contractor shall take care when spray applying a paint that contains a highly
volatile solvent or a thinner in close proximity (within one metre) of a gas, smoke of fire
detector on QP facilities. Such detectors are extremely sensitive to vapours from certain
types of solvents and alarms can be activated by their presence.
7.4.7 Where paints containing over 1% lead in the dry paint film are proposed, the Contractor
shall make this fact known to the QP Engineer and be able to demonstrate that he is
able to apply the paint within the requirements of the QP Safety Regulations.

7.5

PERSONNEL PROTECTIVE EQUIPMENT

7.5.1

All personnel involved in site work, from materials handling to access


construction, preparatory cleaning, paint mixing and application and waste material
handling and disposal, shall wear appropriate personnel protective equipment (PPE) for
their work. The minimum level of PPE required for lung, eye, face, hand, foot and body
protection for each type of work is indicated in Tables 10-12 but this should not be taken
as a comprehensive guide. The PPE requirements for each activity shall be specified on
the QP Work Permit. The Contractor shall be responsible for providing the PPE that is
required for all activities under a contract. The requirements shall be established from

Doc. File No.: SPC.L002.R1

Page 18 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

his Safety Assessment Report on each type of work (see Sub-clause 7.1.3), which
should identify all possible safety and health hazards to be addressed.
7.5.2 All personnel employed in blast cleaning and the spray application of paints and
solvents shall wear air-fed masks. They shall be coupled to a clean air supply fed by an
independent filtered source. The masks shall be ventilated by clean, cool air served
through a regulator filter to prevent abrasive dust and paint solvents from being inhaled
by the operators. These masks shall be cleaned and disinfected daily and a record of
their usage maintained and verified by the Safety Officer or his appointed representative
7.5.3 The Contractor shall be responsible for ensuring that suitable types of protective
footwear, handwear, headwear and overalls are used for the appropriate hazards
identified for each activity.

7.6

PAINT, SOLVENT, CHEMICAL AND WASTE MATERIAL DISPOSAL

7.6.1

During and upon completion of preparatory and painting work, facilities shall be
arranged by the Contractor to effectively and safely collect and manage all waste
materials. These shall include spent abrasive, old paintwork and unwanted or spoilt
paints, solvents and chemicals, plus used equipment such as brushes, rags, hoses,
scaffold components and other waste materials. The Waste Management System used
shall fully comply with QP Environmental Regulations and all necessary precautions
shall be taken to safeguard the surrounding environment.

7.6.2 The Contractor shall arrange to dispose of all waste materials and unwanted
consumables in an acceptable manner at Government-approved disposal sites He shall
maintain a formal record of the materials disposed of, the disposal dates and the
disposal sites used, in accordance with QP Regulations.

8.0

PAINTING OF NEW EQUIPMENT AND STRUCTURES

8.1

GENERAL REQUIREMENTS

8.1.1

All surface preparation and painting or wrapping of newly constructed equipment and
structures shall be completed in the Contractors, or his Sub-Contractors, workshop or
fabrication yard, unless otherwise specified within the relevant contract drawings or
tender documents or approved in writing by the QP Engineer. Individual items of
equipment may be delivered to site in only the primed or partly painted condition, with
the written agreement of the QP Engineer. In such situations, the application of the
remaining coats of paint shall be carried out on site after installation of the equipment.

8.1.2 The partly or fully fabricated items of equipment and structures that have been
completely prepared and painted prior to transportation to site shall be carefully packed,
secured and handled to provide maximum protection against mechanical damage of the
paint coating during transportation and installation on site. The Contractor shall
subsequently make good any damage to the paintwork on the equipment incurred up to
the point of commissioning.

Doc. File No.: SPC.L002.R1

Page 19 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

8.1.3 Partially fabricated and non-fabricated items, including steel plate and structural
members, may with the QP Engineers approval, be prepared, primed and, where
necessary, partially painted prior to transportation to site. In such cases, the Contractor
shall ensure that the paint coating applied in the workshop has sufficient durability to
prevent the onset of corrosion during transportation and throughout the storage and
construction period on site. The Contractor shall make good any damage to the
paintwork incurred up to the point of delivery.
8.1.4 All surfaces of components that will be inaccessible after site assembly shall be fully
prepared and painted prior to assembly, irrespective of the painting arrangement
agreed for the remainder of the equipment. Pipework shall be fully coated in the area of
pipe supports, together with the supports themselves, before being installed. A thin
layer of Teflon should then be fitted between the pipe and the supports, to minimize
subsequent damage to the paint coating at these contact points.
8.1.5 Equipment and components that require to be stress relieved after manufacture shall
not be painted until all heat treatment has been satisfactorily completed.
8.1.6 Equipment that is to be hydrotested shall, unless otherwise formally agreed, not be
painted until this activity has been completed, apart from pipework which is to be site
welded prior to line pressure testing. Workshop hydrotested pipe spools may be fully
painted prior to site hydrotesting but any site welds shall be left uncoated prior to such
testing. The whole paint coating shall be applied to welded areas after site hydrotesting.
8.1.7 All local welding of equipment and drilling of holes for attachments shall be completed
before cleaning and coating begins. This includes the fitting of wear pads or doubler
plates to pipework at support and anchor points.
8.1.8 QP may require painted items to be transported before the Paint Manufacturers
specified minimum coating cure time has been reached. In such cases, the QP
Engineer shall verify the request in writing to the Contractor and the liability for the
repair of any damaged areas of paintwork shall be agreed.
8.1.9 All preparatory and coating work carried out at the Contractors or Sub-Contractors
premises shall be subject to planned inspection, as detailed in Clause 13.0. The
Contractor shall carry out documented inspection at every stage of the activity. Prearranged inspections shall be carried out with the QP Engineer at specified hold points.

8.2

VENDOR STANDARD COATING SYSTEMS

8.2.1 The coating systems and finishes applied by Vendors of specially designed items of
equipment, such as pumps and compressors, are expected to be in accordance with
the relevant Schedule of this Specification. Standard coating systems offered may be
acceptable to QP but full details shall be provided at the outset for evaluation and
approval by the QP Engineer.

8.2.2 Vendors supplying


packaged or skid-mounted units shall ensure the
compatibility and specificational compliance of their overall coating system with
that applied to the individual items of equipment by Sub-vendors. The Vendor shall
Doc. File No.: SPC.L002.R1

Page 20 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

be responsible for co-ordinating the inspection of all the Sub-vendors surface


preparation and painting work.
8.3

MATERIALS AND EQUIPMENT NOT TO BE PAINTED

8.3.1 Unless otherwise specified by the QP Engineer or in the contract documentation,


the following materials and equipment components shall not be prepared or painted:
(a)
(b)

Aluminium, unweathered zinc and copper alloy surfaces.


Stainless steel or nickel alloy surfaces, other than pressure-retaining components
exposed to marine or heavily polluted environments or when hot insulated.
(c) Greased nipples and fittings and lubricated surfaces.
(d) Machined and close working tolerance surfaces.
(e) Gasket contact surfaces and exposed seals, bearings and glands.
(f) Threaded connections (but see Clause 12.5).
(g) Friction grip surfaces.
(h) Equipment identification plates and information and warning signs.
(i) Valve stems, movable linkages, compressor or pump shafts.
(j) Heat tracing equipment and electrical cables.
(k) Instruments and gauges, especially glass components.
(l) Essential equipment openings, such as vents, drains and air intakes.
(m) Areas of components to be site welded or welds subsequently to be hydrotested.
(n) Exposed parts of electrically insulating flange kit components.

9.0

PAINTING OF EXISTING EQUIPMENT AND STRUCTURES

9.1

GENERAL REQUIREMENTS

9.1.1 All surface preparation and maintenance painting of existing equipment and structures
shall be completed at the relevant QP site, unless otherwise specified in the relevant
contract drawings or tender documents or approved in writing by the QP Engineer.
Individual items of equipment may be removed from site for preparation and painting at
the QP workshop or fabrication yard, with the written agreement of the QP Engineer.
9.1.2 A detailed survey shall be carried out by or on behalf of the QP Engineer at the outset,
to establish the condition of the existing paintwork on the equipment and structures to
be painted. The findings of this survey shall be used to determine the nature and scope
of the maintenance preparation and painting work required, in accordance with the
guidelines given in the individual Painting Schedules.
9.1.3 The degree of rusting and extent of coating breakdown on each area and component
shall be established in accordance with the standards specified in ISO 4628 Part 3 or
ASTM D610 and these standards shall be used to determine the type of surface
preparation and extent of painting required. The equivalent ISO and ASTM degrees of
paint rusting are given in Table 1. It may be necessary to dislodge areas of loose and
underrusted paint, to establish the full extent of the coating breakdown. If the
boundaries of such areas of paint breakdown cannot be reliably determined, the whole
surface shall be fully prepared.
Doc. File No.: SPC.L002.R1

Page 21 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

9.1.4 Heavily corroded areas of equipment and structures shall be reported to the QP
Engineer for review, to avoid possible perforation of thin walled areas occurring during
preparatory cleaning prior to repainting. Drainage holes should, where possible, be
drilled at traps and water accumulation points prior to painting.
9.1.5

At the outset, attention shall be paid to the provision of suitable access to all areas of
existing equipment or structure for painting. The underside of pipework at and around
support points and the areas between closely-spaced structural members may present
particular problems. Access difficulties shall not be considered acceptable as a basis
for poor workmanship. Any specific concerns in this regard shall be raised in writing
with the QP Engineer prior to or at the start of the contract, to reach mutual agreement.

9.1.6 Areas of sound existing paintwork may require to be repainted for aesthetic or other
reasons. All such areas shall be cleaned as required for the paint system that is
subsequently to be applied. Particular attention shall be paid to cleaning out and
preparing crevices, traps and other details at which dirt and wash water can accumulate

9.1.7 The preparation of existing painted surfaces shall ensure that all loosened and
underrusted paintwork is removed back to a firm edge with suitable feathering of sound
paint to give a smooth chamfered profile and that all other surface irregularities such as
sags and runs are removed prior to overcoating.
9.1.8 Sweep blast cleaning shall only be carried out for the preparation of existing
paintwork with the QP Engineers agreement after an assurance has been provided
that the use of this technique will not be detrimental to the sound coating. This
cleaning technique requires a high level of operator skill, the use of a low nozzle
pressure and fine abrasive and a low angle of abrasive impingement (typically 30)
on the surface from an increased nozzle to surface distance of around one metre. A
sample area of the coated surface should be test prepared by this technique and
the required quality agreed before any sweep blast cleaning is permitted.

10.0 SURFACE PREPARATION


10.1

PREPARATORY GRINDING AND DEGREASING

10.1.1 Unless otherwise specified, steelwork to be painted and/or wrapped shall be


pretreated as follows prior to any preparatory cleaning being carried out.
10.1.2 All metal surfaces to be painted and/or wrapped shall initially be carefully visually
inspected for the presence of surface-breaking defects, such as laminations and cold
lap. All such defects shall be reported for evaluation. Shallow defects in non-critical
components shall be fully ground out to give a smooth rounded surface profile. Defects
which extend more deeply into the metal and all defects in pressure-retaining
components shall be referred back to the QP Engineer for possible rejection.
10.1.3 All sharp and rough edges, mechanical indentations and other surface
irregularities shall be ground off to give gently rounded contours. All burrs and metal
protrusions, such as weld spatter and slag, shall be ground off to give a smooth profile.
Doc. File No.: SPC.L002.R1

Page 22 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

For the treatment of similar surface details inside vessels to be lined, the requirements
of NACE RP 0178 shall apply. Any irregularities which become apparent after blast
cleaning shall be treated similarly.
10.1.4 All metal surfaces shall be examined and tested as necessary for the presence of oil,
grease and drawing and cutting fluids. Thick grease and heavy oil deposits shall be
removed from the metal surfaces by light scraping and any loose surface residues by
scraping or brushing, preferably followed by wiping with solvent or detergentimpregnated rags. Particular attention shall be paid to bolt holes and drainage holes.
10.1.5 Those surfaces that are, or are likely to be, contaminated with oil or grease shall be
solvent cleaned with a suitable water-soluble biodegradable solvent using rags (for
small areas), an immersion tank (for small items) or a spray gun (for large areas), in
accordance with SSPC-SP1 requirements. The solvent-cleaned surfaces shall then be
thoroughly washed down with fresh water (containing less than 50ppm chlorides),
ensuring that the oil-water emulsion formed is completely removed from the metal.
10.1.6 In situations where fresh water washing is not possible, subject to approval by the QP
Engineer, solvent cleaning may be carried out with an appropriate non-filming solvent.
10.1.7 Metal surfaces to be painted and/or wrapped that do not require to be blast cleaned
shall be thoroughly washed with fresh water containing a suitable water-soluble
biodegradable degreasing agent, at a minimum pressure of 3,000 psig, to remove all
oil, grease and other contamination. Galvanised steel surfaces that are not sweep blast
cleaned shall be similarly water washed, using a stiff bristle brush to remove all watersoluble zinc salts.
10.1.8 Similar washing with fresh water containing a suitable degreasing agent and even
solvent washing of partially painted components shall take place between coats of paint
or layers of tape at the discretion of the QP Engineer. This is particularly important in
offshore situations or in onshore situations where either overcoating has been delayed
for more than 72 hours or the partially painted or wrapped surfaces are seen to be
contaminated with oil, grease or particulate matter.
10.1.9 Degreased and water washed surfaces shall be checked for residual oil and grease
using the atomized water spray test as per ASTM F21 (Sub-clause 13.4.1.4) and further
degreasing carried out if residual oil or grease is found to be present.

10.2

GENERAL BLAST CLEANING REQUIREMENTS

10.2.1 The preferred method of surface preparation for all metal surfaces is dry blast cleaning.
This preparatory technique shall be used wherever possible for the painting and/or
wrapping of all newly constructed equipment and the maintenance repainting of existing
equipment, except when limited breakdown of the existing coating dictates the use of
other methods of surface preparation. In situations where it is considered impractical or
unsafe to carry out blast cleaning, the matter shall be referred to the QP Engineer for
his approval to use an alternative cleaning method.

Doc. File No.: SPC.L002.R1

Page 23 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

10.2.2 For high fire risk situations, where spark production during blast cleaning is considered
unacceptable, the use of approved fully shielded vacuum dry blast cleaning equipment
with standard abrasives, conventional blast cleaning with non-sparking expendable
abrasives such as chalk, water abrasive blasting or water blasting shall be required.
10.2.3 Prior to the commencement of blast cleaning, the Contractor shall ensure that all
adjacent surfaces and equipment that could be damaged by stray abrasive, including
flanges, valves, exposed parts of electrically insulating flange kits and instruments, are
adequately protected against such mechanical damage.
10.2.4 At the outset, the surfaces of each component shall be examined and their original
condition categorized. For unpainted steelwork, it will be a rust grade from A to D, as
specified in ISO 8501 Part 1. For painted steelwork, it will be a degree of rusting, as
specified in ISO 4628 Part 3 or ASTM D610.
10.2.5 Each component shall then be fully blast cleaned to produce a surface appearance that
conforms to the requirements designated and illustrated in ISO 8501 Part 1 and
Supplement for the relevant standard of surface cleanliness, original rust grade and
type of abrasive used. This shall generally be to Sa 3 standard (visually clean/white
metal finish) for newly constructed equipment and at least Sa 2.5 standard (very
thorough/near white metal finish) for maintained equipment. Equivalent SSPC and
NACE standards to the ISO standards are given in Table 2. If the specified standard of
surface preparation cannot be achieved after repeated blast cleaning, because of the
original steel condition, the matter shall be referred to the QP Engineer for arbitration.
10.2.6 The selection and particle size and shape of the abrasive used for blast cleaning shall
be such as to give the metal surfaces a uniform profile or anchor pattern that is suitable
for the coating to be applied with minimum abrasive usage. The required profile height
of the surfaces will be related to the total dry film thickness of the specified paint coating
Coating Total Dry Film Thickness
Up to and incl. 120 microns
150 up to and incl. 300microns
400 microns and above

Average Peak to Trough Profile Height


35-50 microns
50-75 microns
75-100 microns

10.2.7 At the discretion of the QP Engineer, tests may require to be carried out on selected
areas of the blast cleaned surfaces, to ensure that they are free from residual millscale,
oil and grease, abrasive and particulate matter, chlorides and, for non-ferrous
substrates, iron salts.
10.2.8 Once metal surfaces have been blast cleaned to the required standard, no solvents,
cleaning solutions or inhibitive or acid washes shall be used on them
10.2.9 At the start of the contract, two small sections of plate shall be blast cleaned using the
specified abrasive under the agreed blast cleaning conditions and with the appropriate
air blowdown. The blast cleaned plates shall be checked by the Contractor and the QP
Engineer for surface cleanliness, profile height and residual particulate matter, in
accordance with the relevant standards. Once it has been agreed that these plate
sections meet the specified blast cleaning requirements of the contract, the Contractor
Doc. File No.: SPC.L002.R1

Page 24 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

shall put them into transparent, hermetically sealed plastic wallets. One plate shall be
retained by each party. In the event of subsequent disputes arising regarding the
standard of blast cleaning achieved, they shall be used for arbitration purposes.

10.3

DRY BLAST CLEANING

10.3.1 Dry blast cleaning shall be carried out with an approved type, brand, grade and batch of
abrasive. For environmental reasons, only garnet abrasive shall be used for offshore
blast cleaning. Expendable abrasives, such as platinum slag, copper slag and coal
slag, and recyclable abrasives, such as garnet and steel grit, may be considered for
onshore work. If a recyclable abrasive is proposed, the recycling equipment, procedure
and quality control testing measures to be employed shall be reviewed and approval by
the QP Engineer before its use can be sanctioned. Neither sand nor contaminated
recycled abrasive will under any circumstances be allowed for blast cleaning.
10.3.2 The selection of abrasives for the dry blast cleaning of corrosion resistant ferrous alloys
and non-ferrous metals and alloys shall be subject to the approval of the QP Engineer.
10.3.3 The air compressor used for dry blast cleaning shall be fitted with adequately sized
after-coolers, to ensure that the compressed air supplied is completely dry. It shall also
be fitted with suitable traps, separators and filters, which shall be regularly emptied of
water and oil. Any accumulated moisture and oil in the air receiver vessel shall be
removed by regular air purging. The air compressor shall under no circumstances be
allowed to operate at temperatures in excess of 110C. The air supply shall be checked
for water and oil contamination as per the procedure specified ASTM in D4285 prior to
blast cleaning and regularly throughout blast cleaning operations.
10.3.4 The compressed air supply used for dry blast cleaning shall be of sufficient pressure
and volume to enable rapid and efficient cleaning rates to be achieved. Blast cleaning
shall always be carried out at a minimum nozzle air pressure of 100 psig (7 barg), as
measured with a hypodermic needle gauge.
10.3.5 Blast cleaning shall not be carried out in the vicinity of recent surface preparation and
painting locations, where dust or spent abrasive from this operation could contaminate
either freshly cleaned metal surfaces or a wet or tacky paint film.
10.3.6 The weather conditions shall be monitored prior to and constantly throughout the work
period. No dry blast cleaning shall be carried out when the relative humidity of the air
exceeds 85% or the metal temperature is within 3C of the dewpoint temperature. No
dry blast cleaning other than preliminary scale removal shall be carried out outside
daylight hours at external locations. Surface preparation may also be suspended at the
QP Engineers discretion when he considers that adverse weather conditions are likely
to develop before priming of the blast cleaned surfaces can be satisfactorily completed.
10.3.7 Upon achieving the required level of surface cleanliness by dry blast cleaning, the
abrasive supply shall be shut off and as much spent abrasive and dust as possible shall
be removed from the cleaned metal surfaces by either thoroughly blowing them down
with compressed air at the full blasting air pressure or vacuum cleaning them. Brushing
the surfaces is also beneficial in removing embedded particulate matter. Vacuum
Doc. File No.: SPC.L002.R1

Page 25 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

cleaning shall be used for the removal of abrasive and dust from the internal surfaces of
vessels and tanks prior to lining them. The surfaces shall be tested for the presence of
residual particulate matter as per the procedure specified in ISO 8502 Part 3. The
maximum acceptable size and quantity of retained matter shall be Class 2 Rating 2.
10.3.8 Surfaces on which locally corroded areas display evidence of staining after blast
cleaning, indicative of salt contamination, shall be thoroughly washed down with fresh
water and allowed to dry before being reblasted to the specified standard.
10.3.9 All dry blast cleaned surfaces shall be primed or painted before any visible rerusting
occurs and certainly within at most four hours of cessation of blast cleaning. The work
must be planned to ensure that this requirement is always met.

10.4

WET ABRASIVE BLAST CLEANING AND WATER JETTING

10.4.1 Wet abrasive blast cleaning and water jetting are more specialised cleaning techniques
that shall only be considered for use on wet, damp or salt-contaminated surfaces, under
wet and high humidity ambient conditions, at high fire risk locations where spark
formation is considered unacceptable, and when water-dispersing, moisture-tolerant
and moisture-curing primers are to be used.
10.4.2 Free water shall be removed from the metal surfaces using compressed air, squeegees
or mops immediately upon completion of cleaning until no visual signs of water remain.
10.4.3 The metal surfaces shall be cleaned by wet abrasive blasting or water jetting to produce
a finish complying with the appropriate visual and nonvisual surface preparation
standards specified in SSPC-SP 12 / NACE 5 for the primer that is to be applied.
Evaluation of the visual surface condition may be complicated if rust blooming occurs
during the drying cycle. A corrosion inhibitor that is compatible with the primer may by
agreement be added to the final wash water, to minimize rust formation during drying.
10.4.4 The acceptance criteria for the cleanliness of wet abrasive blasted and water jetted
metal surfaces shall be based upon their visual appearance and an absence of soluble
iron salts when tested with potassium ferricyanide, as specified in ISO 8502 Part 1.
10.4.5 The cleaned metal surfaces shall be coated with the appropriate water-dispersing,
moisture-tolerant and moisture-curing primer as soon as all free water has been
removed from them. No Schedule for the use of this type of primer is given in this
document. Paint Manufacturers recommendations must be sought regarding the
selection and use of such primers for any application.
10.4.6 Wet blast cleaning and water jetting techniques and the application of water-dispersing,
moisture-tolerant and moisture-curing primers may be carried out under wet and high
humidity conditions. Subsequent paint application shall, however, be carried out under
the ambient conditions required for conventional painting, i.e. maximum relative
humidity 85% and metal surface temperature at least 3C above dewpoint temperature.

Doc. File No.: SPC.L002.R1

Page 26 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

10.4.7 Contractors proposing to use water abrasive blast cleaning shall provide the QP
Engineer with a plan for the safe disposal of the expendable wet abrasive, stating the
measures that are to be taken to ensure that it does not cause blockage of site drains.
10.4.8 Contractors shall also provide the QP Engineer with detailed method statements for the
use of these wet cleaning techniques, stating the safety precautions that they intend to
take in handling these dangerous high pressure water streams. These shall comply, as
a minimum, with the operating and safety requirements of SSPC SP-12 / NACE 5.

10.5

POWER TOOL SURFACE PREPARATION

10.5.1 It is stated above that metal surfaces shall be prepared by blast cleaning wherever
possible. There are, however, situations where components or areas of components
cannot realistically be blast cleaned, because of their shape, complexity or remote
location. In such situations, these components or areas may with the prior approval of
the QP Engineer be cleaned as thoroughly as possible using power-driven tools, fitted
with approved discs and wire brushes.
10.5.2 The minimum preparatory standard required for power tool cleaned surfaces shall be St
3 standard in accordance with ISO 8501 Part 1 or SP3/SP11 standard in accordance
with SSPC-Vis 3. Care shall be taken to ensure that the metal does not become
polished during cleaning.
10.5.3 Power tool cleaning shall continue for a minimum distance of 25mm into the adjoining
blast cleaned surfaces or, when the prepared areas continue up to existing painted
areas, the interface area shall be feathered back for a minimum distance of 25mm into
the sound coating, to prevent lifting of the old coating and provide a smooth sound
base for the new paint.
10.5.4 With recessed welds that occur in areas which cannot be blast cleaned and are also
inaccessible for power disc and power wire brush cleaning, the use of power-driven
impact tools, such as vibratory and rotary hammers and needle guns, may with the
agreement of the QP Engineer be considered for primary surface preparation, followed
by manual wire brush cleaning.
10.5.5 All power-driven preparatory equipment shall be of a type and quality and be used in a
manner that avoids creating indentations, grooves, burrs or sharp edges in existing
coatings and metal substrates. The use of orbital and/or orbital sanders fitted with
suitably graded abrasive discs or sheets is preferred for existing sound coatings.
Smudges and surface contamination left by wire brushes or discs shall be removed with
a water-soluble solvent. The areas shall then be rinsed with fresh water and dried. In
areas where fresh water washing is not possible, with the approval of the QP Engineer,
solvent cleaning in accordance with SSPC-SP1 requirements shall be performed.
10.5.6 In high fire risk locations where power or even hand tool cleaning is required, the items
of equipment used shall be of a non-sparking type that is approved by the QP Engineer.

Doc. File No.: SPC.L002.R1

Page 27 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

10.6

REVISION 1

MECHANICAL HAND TOOL SURFACE PREPARATION

10.6.1 Mechanical hand tool surface preparation shall only be permitted in areas that cannot
be blast or power tool cleaned, because of their inaccessibility or isolation.
10.6.2 Details of the proposed cleaning method to be adopted and the tools to be used for
hand tool preparation shall be submitted to the QP Engineer for approval. These may
include hand wire brushes, scrapers, pneumatic needle guns and chipping hammers.
10.6.3 All loose rust, mill scale, paint, welding flux and weld spatter shall be removed from the
surfaces by hand brushing, scraping, chipping, hammering or a combination of these
methods and stratified rust and scale shall be removed by chipping or hammering. The
surfaces shall then be thoroughly cleaned to St 3 standard in accordance with ISO
8501 Part 1 or SP2 standard as per SSPC-Vis 3.
10.6.4 In areas where the coating has been locally damaged or the prepared surfaces are
taken back to an existing painted surface, the substrate may be prepared by
mechanical hand tool cleaning but the edges of the prepared area must be carefully
feathered back a minimum distance of 25mm into the adjacent sound coating, to
prevent it lifting and provide a smooth sound base for the new paint.

10.7

CHEMICAL PICKLING

10.7.1 Chemical pickling to white metal in accordance with the requirements of SSPC-SP8
may, with the agreement of the QP Engineer, be considered as an alternative to blast
cleaning in situations and for components where it is a more practically and
economically viable preparatory technique.
10.7.2 The pickling solution used shall be approved by the QP Engineer as being suitable for
treating the constructional material used for the component or equipment involved and
shall contain a suitable inhibitor to prevent localised or excessive general corrosion of
the treated component surfaces.

11.0 PAINT APPLICATION


11.1

PAINT SUITABILITY, STORAGE AND MIXING

11.1.1 Unless otherwise specified, all the paint products comprising a coating system for a
component shall be technically acceptable and approved products that are purchased
from the same Paint Manufacturer with his assurances that:(a)
All products are fully compatible with each other.
(b)
The primer is suitable for the standard of surface preparation specified.
(c)
The complete coating system is suitable for the intended service environment,
temperature and conditions to which it will be subjected.
11.1.2 Particular care is required in the selection of primers and paints for maintenance
painting. Specific assurance shall be sought from the Paint Manufacturer regarding the
compatibility of maintenance primers and paints with existing paint and coating
Doc. File No.: SPC.L002.R1

Page 28 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

systems. Where doubts exist regarding paint compatibility, field trials shall be carried
out on selected areas of the paintwork to be overcoated.
11.1.3 Batches of paint received shall be checked for correct labeling and stored under
secure, sheltered and temperature-controlled conditions. Batches shall be used in the
order in which they are received. The paint identification and storage system must
ensure that this is the case. Prior to use, each batch shall be checked to ensure that it
is still in the original, sealed and properly labeled manufacturers containers and is
marked with its shelf life date.
11.1.4 Paints which are not contained in original, fully sealed manufacturers containers and
batches that have exceeded their shelf life date shall be discarded. Paints which are
found to have gelled or thickened to such an extent that they cannot be easily mixed,
irrespective of their shelf life date, shall also be discarded.
11.1.5 Paints shall be thoroughly mixed in accordance with Manufacturers data sheets, using
suitable rotary stirrers wherever possible, immediately prior to and regularly during use.
Care shall be taken to ensure that all settled material at the bottom of containers has
been fully dispersed and solvated to produce a liquid of uniform consistency. Five litre
and larger sized containers of paint shall always be mixed using rotary stirrers.
11.1.6 When multi-pack paints are used, the separately packaged curing agent or hardener
shall only be added to the base paint after the latter has been thoroughly mixed. Good
working practice would dictate that only a sufficient quantity of paint that can be used
within its pot life under the prevailing climatic conditions and within the current working
period should be mixed. Whenever possible, small units of paint materials shall be used
for performing minor repairs, so as to avoid incorrect part mixing and paint wastage.
11.1.7 Standard units of multi-pack paints shall not be broken down to provide smaller
quantities without the prior agreement of the QP Engineer. Such agreement shall only
be given if it can be procedurally shown and practically demonstrated that accurate
measurements of the quantities of the components to be mixed can be made.

11.2

PAINT APPLICATION EQUIPMENT

11.2.1 Airless spray and conventional air spray equipment used for paint application shall
be of suitable design for the specific paint to be applied. Plural spray pumps shall be
used for paints with a short pot life at high temperatures. Equipment shall be used in
accordance with the Manufacturers operating instructions and recommendations for
the application of that paint. It shall be fitted with suitable pressure regulators and
gauges, to enable the operating conditions to be controlled and monitored.
11.2.2 The air pressure to the paint pump for airless spray paint application shall be
adjusted to be sufficiently high to properly atomise the paint for optimum spraying
effectiveness but should not be significantly higher than this value.
11.2.3 The pressure and volume of air used for conventional air spray paint application shall
be sufficiently high at the spray gun to atomise the applied paint to the degree and at
the rate required. It shall not, however, be so high that it will cause excessive solvent
Doc. File No.: SPC.L002.R1

Page 29 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

evaporation or paint loss by overspray. The air supply shall be maintained dry and
uncontaminated by fitting the compressor with suitable water traps, separators and
filters. The requirements for their maintenance and testing shall be as specified in Subclause 10.3.3.
11.2.4 The fluid tips of airless spraying guns shall be of the orifice size and fan angle and the
fluid control gun shall be of the construction recommended by the Paint and Equipment
Manufacturers. Fluid tips shall be of the shielded type, to prevent skin penetration by
the high pressure paint. The air caps, nozzles and needles of air spraying guns shall be
those recommended by the relevant Paint and Spray Equipment Manufacturers.
11.2.5 The spraying equipment shall be fitted with suitable filters and maintained clean
throughout the working period, to ensure that no dirt, dry paint or other foreign material
is deposited in the paint film. The equipment shall be thoroughly washed out with
solvent to remove all residual paint at the end of each working period but all solvent left
in the equipment shall be completely removed before applying any further paint.
11.2.6 Brushes used for paint application shall be of good quality and of a style that is suitable
for the paint to be applied and the components to be painted. Round or oval brushes
are most suitable for rivets, bolts and irregular or heavily roughened surfaces, whilst
wide flat brushes are most suitable for large flat areas.
11.2.7 Neither brushes over five (5) inches wide nor rollers shall be used for paint application,
other than for the final smoothing of high volume solids paints.

11.3

PAINT APPLICATION METHODOLOGY

11.3.1 Prior to the commencement of paint application, particularly by spraying, the Contractor
shall ensure that all adjacent surfaces and equipment that could be adversely affected
by paint, including flanges, valves and instruments, are protected against paint
overspray and contamination.
11.3.2 All metal surfaces shall be primed as soon as possible after surface preparation has
been completed. For dry blast cleaned surfaces, this shall be before any visible
rerusting of the metal occurs and certainly within four hours of blast cleaning cessation .
For power cleaned surfaces, it shall be the same working day as they are prepared.
11.3.3 The preferred methods for the application of paints to prepared metal surfaces are,
airless spray or conventional air spray, due to the superior paint thickness control and
coating appearance that can be achieved. Brush and other application methods shall
only be used, with QP Engineer approval, for small and isolated areas, such as during
stripe or patch repair painting, or where the Paint Manufacturers recommendations
dictate their use. The number of coats and types of paint and the surfaces to be painted
shall be as specified in the contract documents. The applicators shall be familiar with
the Paint Manufacturers data and instruction sheets for each paint and shall ensure
that they are applied in accordance with these recommendations. Each product and the
individual coats of multi-layer products shall be tinted a different colour, to aid
identification during paint application and coating inspection. The colour of the final coat
shall meet the requirements of Tables 6-9 for the component and service involved.
Doc. File No.: SPC.L002.R1

Page 30 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

11.3.4 The weather conditions and the metal temperature shall be monitored at the start of,
and regularly throughout, the working day. No paint application shall be carried out
when the relative humidity is greater than 85% or the metal surface temperature is less
than 3C above the ambient dewpoint temperature, except with the prior written
approval of the QP Engineer. The maximum and minimum surface temperatures at
which a paint can be applied will depend upon its nature and curing temperature. The
Manufacturers recommendations shall be used as the definitive guide but no paint shall
be applied at surface or ambient temperatures below 5C or above 50C without
Manufacturers approval. No external spray paint application shall be carried out when
the wind speed exceeds 15 knots other than with the agreement of the QP Engineer.
No painting shall be carried out outside daylight hours at external locations, unless
specifically approved in writing by the QP Engineer.
11.3.5 Prior to the application of the full coat of primer and each succeeding coat of paint by
whatever method, all edges, corners, crevices, welds, holes, bolts, rivets and pitted
areas shall be stripe painted with the appropriate paint material by brush, ensuring that
the material is worked firmly into the metal surfaces. These stripe coated areas shall
extend a minimum of 25mm from the relevant feature.
11.3.6 The full coat of primer or paint shall be applied to the component as soon as possible
after stripe painting. Stripe painting after application of the full coat may only be carried
out by exception with the formal agreement of the QP Engineer. In this eventuality, the
stripe paint shall be tinted a slightly different colour to the full coat material to aid
identification. In either situation, care shall be taken to avoid solvent entrapment.
11.3.7 Where paint application is carried out by brush, the brushing shall be done in such a
way that a smooth coat of as uniform a thickness as possible is obtained. All runs and
sags shall be brushed out and the paint shall be as free as possible from pores,
discontinuities and brush marks. Paint shall be worked into all crevices and corners.
11.3.8 Where paint is applied by spray, the spraying technique used shall ensure that a
uniform layer of wet paint of the required thickness is deposited on all surface areas. All
runs and sags shall be brushed out immediately. If there are an excessive number of
runs, the paint shall be removed and the surfaces repainted using either a more
suitable paint mix for the climatic conditions or a modified spraying technique or
equipment. When applying high build coatings, a cross hatch spraying technique is
considered beneficial in producing uniform paint films. Areas that are inaccessible or
unsuitable for effective spray painting, such as crevices, cracks and blind areas of bolts
and rivets, shall be locally painted by brush.

11.3.8 Each coat of paint shall be allowed to cure for at least the minimum period of time at the
prevailing temperature recommended by the Manufacturer before being overcoated.
However, its recommended maximum overcoating period at this temperature shall not
be exceeded. The work must be planned to ensure that this requirement is met. Where
overcoating of a partly painted component is delayed for more than 72 hours, after a
dust storm or strong wind or at the discretion of the QP Engineer, the painted surfaces
shall be solvent cleaned and/or fresh water washed as necessary to remove surface
contamination before being overcoated. They shall also be lightly abraded when the
Doc. File No.: SPC.L002.R1

Page 31 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

overcoating period has been exceeded. After application of the complete paint system,
it shall be allowed to fully cure as per the Manufacturers recommendations before the
component is handled or moved. If the paint does not cure within the recommended
period, at the discretion of the QP Engineer, a sample shall be removed to ascertain the
cause of the problem.

11.4

REPAIR OF DAMAGED PAINTWORK

11.4.1 All areas of paintwork that are locally damaged during transportation, handling or
erection shall be fully repaired to the QP Engineers satisfaction.
11.4.2 When the coating is damaged but the metal substrate is not exposed, the damaged
areas of paintwork shall be gently abraded back to the sound coating using emery
paper or a fine grinder. These areas shall then be wiped with a suitable solvent, to
remove all debris. This technique is especially preferred for the preparation of damaged
vessel and tank linings. The periphery of the repair areas shall be feathered back for a
minimum distance of 25mm into the adjacent undamaged coating by light abrasion or
grinding, to produce a smooth chamfered surface profile for the repair coating. Sweep
blast cleaning shall only be used for the preparation of damaged coatings with the QP
Engineers agreement, subject to the conditions stated in Sub-clause 9.1.8.
11.4.3 When the coating is damaged back to the base metal such that areas of the metal
substrate are exposed, the exposed metal shall be cleaned to the original specified
standard prior to repainting it. For larger areas of exposed metal, local dry blast
cleaning, using a small vacuum blast cleaning unit, shall be used wherever possible.
For small and isolated areas or where the use of blast cleaning is not practical, power
tools may have to be used, with the approval of the QP Engineer, to obtain the required
preparatory standard. As with partially damaged coatings, the periphery of the repair
areas shall be feathered back for at least 25mm into the adjacent undamaged coating,
to produce a smooth chamfered surface profile for the repair coating.
11.4.4 The prepared partially or completely damaged areas of the coating shall then be
repaired by the local application of the requisite number of coats of paint to obtain the
original coating system and thickness.

12.0 WRAPPING TAPE APPLICATION


12.1

TAPE SUITABILITY AND STORAGE

12.1.1 Prior to the commencement of any wrapping work, the Contractor shall submit details of
the type and brand of cold-applied wrapping tape and the primer or adhesive that it is
proposed to apply plus a detailed application method statement, for approval by the QP
Engineer. The document shall be accompanied by the Tape Manufacturers data sheets
for the products involved, confirming their suitability for the expected service conditions
and environment. The wrapping tape should be a heavy-duty tropical grade material.
12.1.2 The product data sheets shall include as a minimum the following details:-

Doc. File No.: SPC.L002.R1

Page 32 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

(a) Service temperature limits and chemical resistance of the wrapping tape and its
adhesive or primer.
(b) Type and recommended minimum wet film thickness of the primer or adhesive.
(c) Minimum and maximum recoating interval of the primer or adhesive prior to tape
application.
(d) Whether the tape requires a special application machine or is suitable for hand
application.
(e) Manufacturers recommended voltage to use for holiday detection testing.
12.1.3 Unless otherwise specified, the filler, primer, adhesive and wrapping tape used shall be
purchased from the same manufacturer with his assurances that:(a) All products are all fully compatible with each other.
(b) The tape primer or adhesive is compatible with the paint coating over which it
will be applied.
(c) The complete wrapping system is suitable for the intended service environment,
temperature and conditions to which it will be subjected.
12.1.4 As with paints, the containers of primer, adhesive and putty filler and the rolls of
wrapping tape shall be individually identified and stored under secure, sheltered and
temperature-controlled conditions. Each roll of tape should ideally have the product
name, batch number and production date stamped on or embossed in the back of the
tape for easy field identification. The containers and rolls shall be used in the order
received. Those which have been opened or damaged or have exceeded their shelf life
date shall be discarded. The handling, mixing and application of primers and adhesives
shall be as detailed in Clause 11.0.

12.2 SURFACE PREPARATION


12.2.1 Component surfaces that are to be wrapped shall have been coated with part of the
paint system that has been specified for the appropriate service environment prior to
being primed and wrapped. The paint coating is required to guard against the
occurrence of general and localized corrosion of the metal beneath the layer of tape by
water that gains access though local points of tape damage and poorly adherent
overlaps and joints.
12.2.2 The surfaces to be wrapped shall have been degreased, prepared and partially coated
with the paint system specified for the relevant service environment and conditions by
the methods and to the standards specified in Clauses 10.0 and 11.0.
12.2.3 Subsequent surface preparation for tape primer or adhesive application shall be in
accordance with the Wrapping Tape Manufacturers recommendations. It may simply
require the paint coating to be water washed or degreased and lightly abraded to obtain
a suitably roughened surface profile for good primer adhesion. If the recommended
overcoating period of the previously-applied paint has been exceeded, it may even be
necessary to apply an additional tie-coat of a suitable paint.

Doc. File No.: SPC.L002.R1

Page 33 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

12.3

REVISION 1

TAPE APPLICATION METHODOLOGY

12.3.1 As with the application of paints, the weather conditions and the metal
temperature shall be monitored at the start of and regularly throughout the working day.
No primer or wrapping tape shall be applied when the relative humidity is greater than
85% or the metal surface temperature is less than 3C above the ambient dewpoint
temperature. The maximum and minimum surface temperatures at which a tape can be
applied will depend upon the nature of the adhesive and carrier materials. The
Manufacturers recommendations shall be used as the definitive guide. No wrapping
shall be carried out outside daylight hours at external locations unless approved in
writing by the QP Engineer.
12.3.2 Pipe flanges and fittings shall be protectively wrapped in the same manner as the
adjacent pipework, unless otherwise specified.
12.3.3 Deeply pitted or uneven surface areas and components with irregular shaped surfaces
that are difficult to wrap, such as areas of flanges, tees and valves, shall be filled with
the Manufacturer-approved putty filler.
12.3.4 The primer or adhesive shall be applied to the painted component surfaces by brush or
spray, as recommended by the Manufacturer, to give the required wet film thickness.
12.3.5 When the primer or adhesive is at the required stage of drying, the protective waxed
paper shall be pulled back from the adhesive side of the wrapping tape and it shall be
slowly wound onto the component surface in a spiral arrangement with moderate
tension using either the approved tape applicator tool or by hand. Gentle uniform
pressure shall be applied to avoid any creases or wrinkles and ensure that it is in firm
contact with the primer or adhesive.
12.3.6 The tape shall be wound in such an arrangement that there is 55% minimum overlap of
one layer of tape onto the previous layer, ensuring double layer coverage on all areas.
12.3.7 When a new roll of tape is started, the new tape shall be overlapped a minimum
circumferential length of 150 mm onto the end of the old tape. When a surface adjacent
to a previously wrapped surface is wrapped, the new tape should overlap a minimum
distance of 150mm back onto the existing tape.
12.3.8 Wrapping tape that is permanently exposed to sunlight shall be overwrapped with a
light-reflecting tape to prevent degradation of the original wrapping by ultraviolet
radiation. Tape that is considered at risk from stone or mechanical handling damage
shall be overwrapped with a physically protective tape.

12.3.9 Welded and flanged pipe joints shall be left uncoated and unwrapped until all pressure
testing has been completed, unless otherwise specified in writing by the QP Engineer.

Doc. File No.: SPC.L002.R1

Page 34 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

12.4

REVISION 1

REPAIR OF DAMAGED WRAPPING TAPE

12.4.1 All areas of wrapping tape that are found to have physical defects, such as creases,
wrinkles, poor adhesion or mechanical damage, or to be below the required thickness
or to contain pinholes shall be rejected.
12.4.2 Locally damaged areas of tape and holidays shall be repaired to the satisfaction of the
QP Engineer by peeling the tape from the affected area, repriming or reapplying the
adhesive to the exposed metal and rewrapping the metal as previously, ensuring a
150mm minimum overlap onto intact wrapping tape on either side of the damaged area.
12.4.3 If the tape is extensively damaged or contains extensive pinholes, it shall be completely
removed back to bare metal and the component surfaces fully reprepared, reprimed
and rewrapped to the required standard.

12.5

PROTECTION OF THREADED CONNECTIONS AND FLANGED JOINTS

12.5.1 It is stated in Sub-clause 8.3.1 that threaded connections shall not be painted unless
otherwise specified. This is due to the periodic need to dismantle such joints and the
fact that the components involved are difficult to paint or wrap by conventional means.
Threaded components, such as bolts and nuts, shall be given some form of protective
coating, which shall be specified in the contract and approved by the QP Engineer.
12.5.2 The use of ultra violet (UV)-resistant plastic caps filled with a suitable corrosion inhibited
grease may be considered for the in-situ protection of assembled nuts, washers and the
end sections of bolts. The cap design shall be such that, once attached, they are firmly
locked in place and cannot be inadvertently removed. The Contractor shall submit
details of the design and material of the caps and the nature of the grease that are
proposed to be used, for approval by the QP Engineer.
12.5.3 The sections of bolts and other fastener components inside the flange faces of flanged
joints may be protected by fitting a proprietary clamped stainless steel band having an
internal rubber sealing membrane and a drain nipple at its low point or by sealing the
periphery of the flanged joints with a suitable mastic sealant after fitting a drain nipple.
12.5.4 The use of field-applied thermoplastic encapsulation may also be considered for the insitu protection of assembled threaded components, flanged joints, machined surfaces
and other similar features. This special type of wrapping should be thought of as a
strippable temporary protective system, because of the ease with which the material
can be removed from the surfaces rather than longevity of the protection provided.
12.5.5 As with other types of wrapping, the Contractor shall submit details of the encapsulation
material and any primer or adhesive that are proposed to be applied, plus a detailed
application method statement, for approval by the QP Engineer. The document shall be
accompanied by the Encapsulation Manufacturers Data Sheet for the product to be
applied, confirming its suitability for the expected service conditions and environment.
12.5.6 This type of wrapping system is generally applied by specialist Contractors or using
specialised proprietary equipment. Full details of the application system and equipment
Doc. File No.: SPC.L002.R1

Page 35 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

involved shall be made available to the QP Engineer for approval before any
encapsulation work is allowed to take place.

13.0 INSPECTION DURING SURFACE PREPARATION AND COATING


13.1

GENERAL INSPECTION REQUIREMENTS

13.1.1 All surface preparation, painting and wrapping work carried out under or to the intent of
this Specification shall be subject to systematic inspection at each stage of prepreparation, surface preparation, painting/wrapping and repair by the QP Engineer. In
addition, the work shall be subject to random inspection as and when the QP Engineer
deems it necessary.
13.1.2 The basic inspection requirements and system shall be detailed in a formal Quality
Inspection and Test Plan and presented by the Contractor as part of the contract
documentation for approval by the QP Engineer. A typical Q.I. & T. Plan Checklist is
shown as Table 3. Such a Plan shall not relieve the Contractor from his responsibility to
carry out all work in a safe and timely manner using skilled personnel and good
practices to achieve a high quality product meeting all other specification requirements.
13.1.3 All defective or non-conforming work identified at each stage shall be rectified to the
required standard by the Contractor. Any preparatory, painting or wrapping work carried
out to this Specification that is not systematically inspected and approved by the QP
Engineer at each stage shall be deemed not to meet the Specification. The coating or
wrapping shall be removed from all affected areas and they shall be reprepared and
recoated or rewrapped to the approval of the QP Engineer by the Contractor.
13.1.4 The Contractor shall provide an authorised person who is a qualified Painting Inspector
to the minimum standard specified below to coordinate the inspection work carried out
and report the results obtained. The proposed Contractor employee, who may be a
Supervisor or Manager, shall also be individually acceptable to the QP Engineer.
Additionally, either an appointed QP Painting Inspector or an approved qualified Third
Party Painting Inspector shall act on behalf of the QP Engineer under the contract, to
ensure that the required inspection work is being carried out in a satisfactory and
effective manner to consistently give a good quality product.
13.1.5 All proposed Painting Inspectors shall be qualified to at least TWI (ex-ERS) Level 1, I
Corr Level 2 or NACE Level 2 and shall have at least five years approved experience of
industrial painting of oil and gas facilities at inspector or supervisor level. The
certification and resume of each Inspector shall be submitted to the QP Engineer for
approval and they shall be interviewed at the start of each contract to confirm their
technical capability. The Inspectors shall consult the Paint Manufacturer to obtain the
necessary technical support to ensure compliance with product recommendations.
13.1.6 The Contractor shall provide a comprehensive range of approved inspection equipment
at each site of any work that is in progress, to enable all inspection work that is required
under the approved Inspection and Test Plan and Work Specification to be carried out.
He shall provide sufficient sets of commonly used inspection equipment to avoid any
delays in carrying out the required inspection at all work sites.
Doc. File No.: SPC.L002.R1

Page 36 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

13.2

REVISION 1

INSPECTION SYSTEM REQUIREMENTS

13.2.1 The proposed inspection system for all preparatory, painting and wrapping work shall
operate via a series of Hold Points in the work schedule, from which the Contractor
shall not proceed until he is given formal clearance by the QP Engineer. This does not
mean that these are the only points at which inspection shall be carried out. It is
intended that the Inspection and Test Plan will ensure that relevant inspection is carried
out prior to, during and after each activity in the work schedule.
13.2.2 The relevant Hold Points, which shall be considered as mandatory under all
contracts, are as follows. These items are also identified as Hold Points in Table 3.
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)

Approval of working procedures, safety precautions and QA/QC system.


Authorisation of Permit to Work.
Acceptance of preparatory, painting, wrapping and inspection tools and
equipment type and condition.
Acceptance of primary metal surface or coating condition.
Acceptance of the climatic conditions prior to and during all activities.
Acceptance of surface preparation standards.
Acceptance of primer stripe painting and full primer coat.
Acceptance of complete paint coating or wrapping.
Acceptance of remedial coating and wrapping repairs.

13.2.3 All Hold Points shall be strictly observed and recorded. Any surface preparation or
painting or wrapping work undertaken without Hold Point clearance shall be re-worked
by the Contractor.
13.2.4 The QP Engineer shall be given at least 48 hours notice of any Hold Point
inspections that require to be carried out. Whilst work is in progress the QP Engineer
shall be given at least 24 hours notice of any change in the inspection schedule. All
parts of the work shall be made accessible for the inspection in good lighting, with all
areas evenly illuminated to a level of not less than 500 lux daylight or artificial light. In
the event of the Contractor wishing to cancel a prearranged inspection, he is required to
give the QP Engineer at least one hours notice, unless otherwise formally agreed.
13.2.5 Full details of the inspection work carried out and the results obtained shall be reported
by the authorised Contractor Painting Inspection on a daily basis in a standard Daily
Inspection Report Form, the format of which shall be approved at the outset by the QP
Engineer. This Form may also be used as a daily progress report. A typical Daily
Inspection Report format is given in Table 4 but it shall as a minimum contain the
following information.
(a) Contractor and client name, project title and reference number and work location.
(b) Date.
(c) Nature and sizes of items undergoing preparation and painting or wrapping, areas
worked on and constructional materials involved.
(d) Areas not painted or wrapped and protective measures taken.
(e) Original condition of metal substrate or coated surface.
Doc. File No.: SPC.L002.R1

Page 37 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

(f)
(g)
(h)
(i)
(j)
(k)
(l)

(m)
(n)
(p)

REVISION 1

General weather conditions, relative humidity, dewpoint and air and metal
temperatures at start of each shift and every two hours throughout the working day.
Preliminary cleaning and degreasing carried out, including solvents used.
Method of surface preparation and equipment used, including abrasive type,
product brand name, particle size range and batch number.
Standard of surface preparation and cleanliness and surface profile height obtained
Manufacturer, product name and number and batch number of all paints and
wrapping tapes applied.
Number of coats of each product applied to each area of each item and application
method used.
Specified dry film thickness (D.F.T.) of each coat of paint and complete paint
coating (T.D.F.T.) and measured wet film thickness (W.F.T.) of each coat and
D.F.T. of each coat and complete paint coating.
Areas wrapped by each tape and tape thickness obtained.
Locations and sizes of areas of paintwork and wrapping repaired.
Any comments relating to the work that the Contractor feels are relevant.

13.2.6 These Daily Inspection Report Forms shall be completed, signed and dated by the
authorised Contractor Painting Supervisor/Inspector on a daily basis at least in triplicate.
One copy shall be submitted to the Contractors Engineer for review, one copy sent to
the Contractor management and the third copy retained in the site working file. At the
end of the Contract, a summary Close Out Inspection Report, a typical format for which
is shown as Table 5, shall be completed, signed and dated and sent for the QP
Engineers approval.

13.3

INSPECTION OF EQUIPMENT, MATERIALS AND ACCESS FACILITIES

13.3.1 The QP Engineer shall have the right to inspect all tools, equipment, plant, instruments,
materials, and access scaffolding and facilities that are used or to be used in the
performance of the preparatory, coating application, wrapping and inspection work at
the start of and at all times during the contract. The Contractor shall make all parts of
the worksites accessible for these inspections.
13.3.2 QP reserves the right to reject any tools, equipment, plant, instruments, materials or
access facilities which are considered either unsuitable, unserviceable, inadequate or
unsafe for the proposed work or not to fully meet the contract requirements. All rejected
items and materials shall be reported as such and replaced or rectified as instructed by
the QP Engineer.
13.3.3 The Contractor shall provide recent calibration certificates for all equipment and
instrumentation used for the contract, where appropriate and as requested by the QP
Engineer. Equipment and instrumentation which cannot be calibrated shall be replaced
by the Contractor, if considered to be unserviceable or unsuitable by the QP Engineer.
13.3.4 Upon request, the Contactor shall permit the QP Engineer or his Appointed Painting
Inspector to use any item of inspection equipment, to assess its reliability, accuracy and
suitability for the proposed inspection activity. If any item is deemed to be inadequate
to carry out an inspection activity, an alternative item that is acceptable to the QP
Engineer shall be provided by the Contractor.
Doc. File No.: SPC.L002.R1

Page 38 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

13.4 PREPARATORY AND COATING INSPECTION AND TEST WORK


13.4.1

PRIOR TO SURFACE PREPARATION

13.4.1.1

Presence of surface-breaking laminations and sharp edges. All


shall be visually inspected.

13.4.1.2

Presence of gross oil, grease and particulate matter contamination. Surfaces


shall be visually inspected.

13.4.1.3

Basic rust grade of uncoated metal surfaces or degree of coating breakdown


of coated metal surfaces. Shall be assessed by visual inspection in conjunction
with Standard ISO 8501 Part 1 or SSPC-Vis 1 for uncoated metal surfaces and ISO
4628 Part 3 or ASTM D610 (SSPC-Vis 2) for coated metal surfaces.

surfaces

13.4.1.4 Presence of residual oil or grease contamination on solvent washed


and fresh water rinsed surfaces. Shall be tested with atomised water spray from
a spray gun containing fresh water in accordance with ASTM F21. A clean dry rag
shall be used for subsequently drying the metal.
13.4.1.5

Presence of residual chlorides on surfaces, especially stainless steel.


(Subsidiary test that shall be carried out at the discretion of the QP Engineer). Shall
be tested with silver nitrate solution using a small dropper bottle containing acidified
silver nitrate solution. If a white precipitate is formed, indicating the presence of
chlorides, the matter shall be referred back to the QP Engineer for quantitative
assessment. A wash bottle and dry rag shall be used for removing the test solution.

13.4.2

THROUGHOUT THE WORKING DAY

13.4.2.1

Relative humidity and dewpoint of the atmosphere. Shall be measured in


accordance with Method B of ASTM E337 using a whirling psychrometer (wet and
dry bulb thermometers) in conjunction with Hydrometric Tables.

13.4.2.2

Metal surface temperature. Shall be measured using a suitable contact


thermometer.

13.4.3

BEFORE AND DURING SURFACE PREPARATION

13.4.3.1

Type, grade and cleanliness of abrasive used for blast cleaning. The
information
marked on the labels of the bags of abrasive shall be recorded.
Recycled abrasive and, at the discretion of the QP Engineer, expendable abrasive
shall be tested for oil, grease and salt contamination. For oil and grease
contamination, the abrasive shall be agitated in a 1:1 ratio with fresh water for two
minutes in a vial, left stand for 10 minutes and then agitated for a further two
minutes. The surface of the water shall then be checked for floating oil. For salt
contamination, the abrasive shall be agitated in a set ratio with deionised water for
five minutes in a container and the solution electrical conductivity measured in
accordance with ISO 8502 Part 9. The result shall be approved by the QP Engineer

Doc. File No.: SPC.L002.R1

Page 39 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

13.4.3.2

Presence of oil or water in compressed air used for blast cleaning. A piece of
clean white absorbent paper or cloth shall be held at the air outlet at a suitably low
operating pressure in accordance with ASTM D4285.

13.4.3.3

Air pressure used for blast cleaning. Shall be measured at the blasting nozzle by
inserting a hypodermic needle pressure gauge in the air line adjacent to the nozzle.

13.4.3.4

Standard of surface cleanliness produced. Shall be assessed on blast cleaned,


power tool or mechanically cleaned surfaces by visual inspection using ISO
Standard 8501Part 1 and Supplement or SSPC-Vis 1 or Vis 3.

13.4.3.5

Profile height of blast cleaned surfaces. Shall be measured using a suitable


grade of Testex replica tape plus a portable micrometer gauge or a suitable surface
profile comparator gauge in accordance with NACE RP 0287 or ASTM D4417
Method C.

13.4.3.6

Quantity and quality of residual dust and particulate matter on blast cleaned
surfaces. Shall be assessed using transparent self-adhesive tape, a small pocket
microscope and Standard ISO 8502 Part 3.

13.4.3.7

Presence of residual millscale on steel surfaces. (Subsidiary test which shall


be carried out at the discretion of the QP Engineer). Shall be detected using a small
dropper bottle containing acidified copper sulphate solution. Discontinuities in the
deposited copper layer indicate the presence of residual millscale. The test area
shall be locally reblasted to remove the copper layer and any residual test solution.

13.4.3.8

Presence of iron salts on stainless steel and non-ferrous metal surfaces.


(Subsidiary test which shall be carried out at the discretion of the QP Engineer).
Shall be detected using a small dropper bottle containing potassium ferricyanide
solution. If a bright blue colouration results, indicating the presence of iron salts, the
matter shall be referred back to the QP Engineer for quantitiative assessment. A
wash bottle and dry rag shall be used for subsequently removing the test solution.

13.4.3.9

Presence of residual chlorides on cleaned surfaces. (Subsidiary test that shall


be carried out at the discretion of the QP Engineer). Shall be detected as in Subclause 13.4.1.5. If necessary, quantitative assessment shall be made by obtaining a
sample from the surface in accordance with ISO 8502 Part 6 and either measuring
its electrical conductivity in accordance with ISO 8502 Part 9 or analysing it
titrimetrically for chloride in accordance with ISO 8502 Part 10.

13.4.4

PRIOR TO AND DURING PAINT & WRAPPING APPLICATION

13.4.4.1

Type, brand and condition of primer, adhesive, paint and wrapping tape used.
The information marked on the labels of the primer, paint and tape containers,
including batch numbers and expiry dates, shall be recorded and the product
condition ascertained. Samples may be taken at the discretion of the QP Engineer.

Doc. File No.: SPC.L002.R1

Page 40 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

13.4.4.2

REVISION 1

Presence of rust on blast cleaned surfaces at time of primer application.


Surfaces shall be carefully visually examined in good light, with all areas evenly
illuminated to a level of not less than 500 lux daylight or artificial light.

13.4.4.3 Time between blast cleaning and priming. Shall be established by recording and
reviewing the time at which blast cleaning was started immediately before priming.
13.4.4.4

Primer, undercoat and topcoat paint thickness and uniformity. Shall be


measured by taking random wet film thickness measurements on each coat of paint
immediately after application using a stainless steel comb or wheel gauge.
Systematic dry film thickness measurements shall subsequently be taken on the
paint film after each coat has dried using a QP approved model magnetic or eddy
current dry film thickness gauge in accordance with SSPC-PA 2. All coats shall also
be visually inspected for defects and non-uniformities.

13.4.4.5

Overcoating periods for paints. Shall be established by recording the time at


which each coat of paint was applied and relating this to the Paint Manufacturers
recommended overcoating period for the product at the prevalent metal temperature

13.4.5

AFTER PAINT AND WRAPPING APPLICATION

13.4.5.1

Thickness and uniformity of complete paint coating or wrapping. Shall be


measured by carrying out a detailed systematic dry film thickness measurement
survey on all areas using a QP approved model dry film thickness gauge in
accordance with SSPC-PA 2.

13.4.5.2

Final appearance of paint film or wrapping. Shall be approved by careful visual


inspection of the fully coated or wrapped surfaces, to ensure that they are free from
runs, sags, orange peeling, fish eyes, overspray, dirt and grit entrapment, wrinkles,
open joints and mechanical damage .

13.4.5.3 Curing time for complete paint coating Shall be established by recording the time
at which the topcoat paint was applied and relating this to the Paint Manufacturers
recommended full coating cure period at the prevalent metal temperature.
Supplementary double rub or modified thumb cure tests using a suitable solvent
and/or abrasion with emery paper may be carried out to confirm the degree of cure.
13.4.5.4

Presence of holidays in complete paint film or wrapping tape. (Requirement


for this test shall depend upon the project specification and the nature of the
component being coated or wrapped). Shall be detected by carrying out holiday
testing in accordance with NACE RP 0188 using a QP approved low or high voltage
DC holiday detection equipment, depending upon the coating or wrapping thickness

13.4.5.5

Adhesion of coating. (Subsidiary test that shall be carried out at the discretion of
the QP Engineer). Shall be measured on the dry paint film using a cemented dolly
and a pull-off measurement device in accordance with ASTM D4541. The measured
coating adhesion strengths shall be referred to the Paint Manufacturer for approval.

Doc. File No.: SPC.L002.R1

Page 41 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

13.4.5.6

Identification of areas for repair. Areas of the paint coating or wrapping that
require repair shall be carefully identified on the components themselves and
recorded in the reports so that these can readily be reinspected during and upon
completion of the repair work.

13.5

INSPECTION EQUIPMENT REQUIREMENTS

13.5.1

The following inspection equipment shall be supplied in good working order at


each work site by the Contractor.
(a)
(b)
(c)
(d)
(e)

A whirling or sling psychrometer and hydrometric tables.


A contact thermometer with a suitable temperature range.
A small spray gun containing potable or distilled water.
A hypodermic needle pressure gauge with a suitable pressure range.
Either a suitable grade of Testex tape plus a portable micrometer gauge or an
approved surface profile comparator gauge.
(f) A roll of transparent self-adhesive tape and a pocket microscope.
(g) Sufficient stainless steel combs or wheel type wet film thickness gauges
for all painters and inspectors.
(h) Several approved model magnetic or eddy current dry film thickness gauges
with suitable shims.
(i) ISO Standard 8501 Part 1 plus Supplement, ISO 8502 Part 3 and ISO 4628
Part 3 and/or ASTM D610.
13.5.2

The following inspection equipment shall, as a minimum, be supplied by the


Contractor if the contract or the QP Engineer requires them.
(a)
(b)
(c)
(d)
(e)
(f)
(g)

A small dropper bottle containing acidified silver nitrate solution.


A small dropper bottle containing acidified copper sulphate solution.
A small dropper bottle containing potassium ferricyanide solution.
Standard self-adhesive extraction sample patches.
Electrical conductivity meter.
An approved model high or low voltage D.C. holiday detector.
A set of dollies, a tube of epoxy cement and a pull-off measuring device.

Alternative specialised inspection equipment may be provided for specific types of


inspection and testing, subject to approval by the QP Engineer.
13.5.3

The dry film thickness gauges shall be calibrated using an insulating shim of similar
thickness to that of the partial or complete paint film to be inspected held over a
sample of the same material as that to be painted with a similar blast cleaned
surface profile, in accordance with SSPC-PA 2. The calibration sample could be a
plate of the substrate material blasted to a standard agreed with the QP Engineer.
The gauges shall be calibrated at the start of the working day, at least twice during
each shift when in use and when a change in the coating thickness range occurs.

13.5.4

Holiday Detection shall be carried out when it is required by the project specification
or at the direction of the QP Engineer, to ensure the integrity of a paint coating or
wrapping. It is typically required for tank and vessel linings and buried or immersed
coatings and wrappings. The test voltage used shall be according to NACE RP
0188. All safety guidelines and rules shall be followed when using this equipment.

Doc. File No.: SPC.L002.R1

Page 42 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

14.0 QUALITY ASSURANCE REQUIREMENTS


14.1

The Contractor shall be fully responsible for ensuring that all surface preparation,
painting and wrapping work meets the relevant QP quality control (QC) standards, in
addition to being carried out in a timely and professional manner. This will require him
to use well trained and suitably skilled operators and supervisory staff and good quality,
well maintained preparatory and application equipment and inspection tools.

14.2 The Contractor and his Sub-Contractors shall operate a Quality Management System
meeting the requirements of the relevant parts of EN ISO 9001. Guidance on
Contractor conformance with the requirements of EN ISO 9001 is given in QP Quality
System Procedure QSP-QC-09.
14.3

Prior to placement of the contract, the Contractor and his Sub-Contractors shall
demonstrate the compliance of their Quality Management System with QP
requirements by submit their Quality Assurance (QA) Manual for review and approval.
As a minimum, the QA Manual shall contain:(a) A company profile and Quality Policy Statement.
(b) A management structure organigram and details
of individual managerial
responsibilities.
(c) A detailed list of all the activities carried out by the company with their interactions,
preferably accompanied by a Flowchart.
(d) The Quality Control Plans for each activity from material purchasing and handling
through to final inspection, testing and document control, including the treatment of
non-conformances and corrective actions.
(e) A Document Control System for the review and update of procedures and the
retention of quality control records related to each contract.
(f) Employee training and education system and records.
(g) Auditing methods procedures, including incident/accident investigation.
(h) Safety and environmental policy and assessment of each activity.

14.4

The Contractor and his Sub-Contractors shall be subject to Audit by QP prior to


placement of the contract and during the term of the contract, as is deemed necessary.

14.5

Prior to the commencement of the work, the Contractor shall submit his Quality
Inspection and Test Plan to the QP Engineer for review. This shall detail the individual
preparation, painting and wrapping activities involved and the inspection and test
methods that will be used to ensure that they are carried out to an acceptable standard.
The Plan will generally be in tabular form and will indicate the type and level of
inspection and testing that is required at each stage of the work. It should also contain
references to verifying documents and the personnel responsible for each activity. A
typical Quality Inspection and Test Plan Checklist is shown as Table 3.

14.6

All personnel involved in the preparation, painting and wrapping work and any SubContractor proposed for this work shall be formally approved by the QP Engineer,
possibly as indicated in Sub-clause 6.5, before the work begins.

Doc. File No.: SPC.L002.R1

Page 43 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

14.7

REVISION 1

Prior to commencement of the work, a formal minuted Pre-start Meeting shall be held
between the QP Engineer, Contract Administrator, relevant Contractor management
and supervisory staff and the Painting Inspector. The full scope of the work required
under the contract shall be discussed. All issues relating to the clarity or consistency of
the surface preparation and/or painting and wrapping requirements detailed within the
tender documents and on relevant drawings shall be formally raised and clarified at this
meeting. This will enable the quality requirements for the work to be mutually agreed.

15.0 DOCUMENTATION
15.1

All correspondence, drawings, instructions, data sheets, design calculations and all
other written information shall be in English language. In the case of dual languages,
one language shall be English and the other Arabic.

15.2

All dimensions and measurements shall be in SI units, unless otherwise specified.

15.3

The Contractor shall provide QP with his fully detailed written work proposals,
procedures, material data sheets, material test results and test certificates.

15.4

The Contractor shall maintain a comprehensive recording and reporting system on all
aspects of surface preparation, paint and wrapping application and Quality Assurance
inspection and testing. This shall as a minimum meet all the requirements of this
Specification and QSP-QC-09. A final report shall be submitted to QP, summarising all
the work performed and the inspection and test results for approval.

15.5

All documents, from texts and specifications to data sheets and drawings, shall be
provided with electronic files in the approved software of MS Word, Excel and Auto
Cad. Design calculations shall also be submitted in the approved software system
agreed with QP.

Doc. File No.: SPC.L002.R1

Page 44 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

16.0 PROTECTIVE SYSTEM CLASSIFICATION BY AREA, SERVICE AND


MATERIAL
SCHEDULE NO.
1Un

DESCRIPTION OF AREA, SERVICE AND MATERIAL

General Exposure to Atmosphere


New Construction of Uninsulated Items
General Exposure to Atmosphere
New Construction of Insulated Items
General Exposure to Atmosphere
New Construction of Fireproofed Items
General Exposure to Atmosphere
Maintenance of Uninsulated Items
General Exposure to Atmosphere
Maintenance of Insulated Items
General Exposure to Atmosphere
Maintenance of Fireproofed Items
Uninsulated Steel With a Design Temperature of 120-400C

Insulated Steel With a Design Temperature of 120-250C

Items Exposure to Seawater and Seaspray in Splash Zone

Internal Surfaces of Steel Hydrocarbon and Water Storage Tanks

Underside of Steel Storage Tank Floor Plates

Internal Vessel Surfaces Subject to Pressure and/or Corrosive Service

Zinc Coated Steel Surfaces

10

Helideck and Walkway Non-Skid Surfaces

11

Buried and Fully Immersed Pipelines

12

Stainless Steel and Non-Ferrous Metal Surfaces

13

Self-Adhesive Tape Wrapping for Buried and Immersed Pipelines


and Steelwork

1In
1F
2Un
2In
2F

Doc. File No.: SPC.L002.R1

Page 45 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

17.0 COATING AND WRAPPING SCHEDULES


17.1

The following 17 Coating and Wrapping Schedules are designed to cover all the types
of equipment, exposure locations and conditions and constructional metals that are
likely to be encountered in QP facilities.

17.2

The preparatory and painting or wrapping requirements are shown in sequential order
and require to be fully followed. The only basis for a deviation from a Schedule
requirement is by prior formal written agreement from the QP Engineer.

17.3

Attention is drawn to the Notes at the bottom of each Schedule, which should be
consulted carefully before any paint is purchased or any work is planned or carried out.

Doc. File No.: SPC.L002.R1

Page 46 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 1Un


GENERAL EXPOSURE TO ATMOSPHERE UNINSULATED NEWLY CONSTRUCTED ITEMS
Uninsulated and non-fireproofed new structural steelwork and uninsulated external surfaces of new
carbon steel tanks, vessels, towers, exchangers, heaters, pipework and pipelines located above
ground (onshore) and above the Splash Zone (offshore) with a design temperature of between 0C
and 120C.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water-soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
Blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitably sized abrasive to
give a surface profile amplitude of 50-75 microns.
REPAIR OF DAMAGED COATING (See Clause 11.4)
Vacuum or spot blast clean to Sa 3 standard per ISO 8501-1 plus Supplement. Power tool cleaning
to St 3 standard is only acceptable by agreement for areas that are inaccessible or impractical for
blast cleaning. Abrade with emery paper or lightly grind areas of partial coating damage.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT
Two-component zinc-rich epoxy primer*
MID COAT 1
High-build two-component polyamide-cured micaceous iron oxide (MIO)-pigmented epoxy**
MID COAT 2
High-build two-component polyamide-cured micaceous iron oxide (MIO)-pigmented epoxy**
FINAL COAT
Two-component aliphatic polyurethane high gloss enamel
APPLICATION OF COATING
PRIMER COAT
Apply zinc-rich epoxy primer by airless spray or brush
MID COAT 1
Apply MIO-pigmented epoxy by airless spray or brush
MID COAT 2
Apply MIO-pigmented epoxy by airless spray or brush
FINAL COAT
Apply aliphatic polyurethane enamel by airless spray or brush
TOTAL DRY FILM THICKNESS

MICRONS
@

50

100

100

50

300

NOTES :
1. * Zinc-rich epoxy primer shall contain a minimum of 90% metallic zinc by weight in the dry film.
2. ** The epoxy midcoat paint shall contain a minimum of 80% MIO by weight in dry film.
3. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 47 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 1In


GENERAL EXPOSURE TO ATMOSPHERE INSULATED NEWLY CONSTRUCTED ITEMS
Insulated newly constructed structural steelwork and insulated external surfaces of new carbon
steel tanks, vessels, towers, exchangers, heaters, pipework and pipelines located above ground
(onshore) and above the Splash Zone (offshore) with a lower design temperature of down to -46C
or an upper design temperature of up to 120C.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water-soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
Blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitably sized abrasive to
give a surface profile amplitude of 50-75 microns.
REPAIR OF DAMAGED COATING (See Clause 11.4)
Vacuum or spot blast clean to Sa 3 standard per ISO 8501-1 plus Supplement. Power tool cleaning
to St 3 standard is only acceptable by agreement for areas that are inaccessible or impractical for
blast cleaning. Abrade with emery paper or lightly grind areas of partial coating damage.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT
Two-component zinc-rich epoxy primer*
MID COAT 1
High-build two-component polyamide-cured micaceous iron oxide (MIO)-pigmented epoxy**
MID COAT 2
High-build two-component polyamide-cured micaceous iron oxide (MIO)-pigmented epoxy**
APPLICATION OF COATING
PRIMER COAT
Apply zinc-rich epoxy primer by airless spray or brush
MID COAT 1
Apply MIO-pigmented epoxy by airless spray or brush
MID COAT 2
Apply MIO-pigmented epoxy by airless spray or brush
TOTAL DRY FILM THICKNESS

MICRONS
@

50

100

100

250

NOTES :
1. * Zinc-rich epoxy primer shall contain a minimum of 90% metallic zinc by weight in the dry film.
2. ** The epoxy midcoat paint shall contain a minimum of 80% MIO by weight in dry film.
3. Areas that protrude through the insulation also require a 50 micron thick coat of aliphatic
polyurethane high gloss topcoat paint.
4. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 48 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 1F
GENERAL EXPOSURE TO ATMOSPHERE FIREPROOFED NEWLY CONSTRUCTED ITEMS
Fireproofed newly constructed structural steelwork and fireproofed external surfaces of new carbon
steel vessels, towers, exchangers, heaters, pipework and pipelines located above ground
(onshore) and above the Splash Zone (offshore) with a design temperature of between 0C and
120C.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water-soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
Blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitably sized abrasive to
give a surface profile amplitude of 50-75 microns.
REPAIR OF DAMAGED COATING (See Clause 11.4)
Vacuum or spot blast clean to Sa 3 standard per ISO 8501-1 plus Supplement. Power tool cleaning
to St 3 standard is only acceptable by agreement for areas that are inaccessible or impractical for
blast cleaning. Abrade with emery paper or lightly grind areas of partial coating damage.
GENERIC CLASSIFICATION OF COATING (Please see Note 1*)
PRIMER COAT
Two-component zinc phosphate-pigmented epoxy primer
MID COAT
High-build two-component polyamide-cured micaceous iron oxide (MIO)-pigmented epoxy**
APPLICATION OF COATING
PRIMER COAT
Apply zinc phosphate-pigmented epoxy primer by airless spray or brush
MID COAT
Apply MIO-pigmented epoxy by airless spray or brush

MICRONS
@

50

100

TOTAL DRY FILM THICKNESS

150

NOTES :
1. * Alternative proprietary protective systems may have to be used where the fireproofing
manufacturer considers that the application of the specified coating system will prejudice the
fireproofing guarantee. In such situations, manufacturers requirement shall be mandatory.
2. ** The epoxy midcoat paint shall contain a minimum of 80% MIO by weight in dry film.
3. Areas that protrude through the fireproofing also require to be coated with a second 100
micron thick coat of the specified midcoat paint and 50 micron thick coat of aliphatic
polyurethane high gloss topcoat paint.
4. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 49 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 2Un


GENERAL EXPOSURE TO ATMOSPHERE - UNINSULATED EXISTING ITEMS MAINTENANCE
Uninsulated and non-fireproofed existing structural steelwork and uninsulated external surfaces of
existing carbon steel tanks, vessels, towers, exchangers, heaters and pipework located above the
ground (onshore) and splash zone (offshore) with a design temperature of between 0C and 120C
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water-soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
Dependent upon condition of existing paintwork.
1. No visible coating breakdown Ri 0 (ASTM No 10) level (where overcoating for aesthetic or
other reasons). Abrade pretreated surfaces with emery paper for good topcoat adhesion.
2. Partial or variable coating breakdown with primer intact or localised underrusting to no
more than Ri 3 (ASTM No. 6) level. Locally blast clean degraded areas to Sa 2.5 standard as
per ISO 8501-1 plus Supplement. Power tool clean to St 3 standard if blast cleaning impractical.
3. More extensive coating breakdown to Ri 4 (ASTM No. 4) level or worse. Fully blast clean
surfaces to Sa 2.5 standard per ISO 8501-1 plus Supplement. Power tool cleaning to St 3
standard is only acceptable by agreement for small areas and areas that are impractical for
blast cleaning. Use a suitable blast cleaning abrasive to give a surface profile of 50-75 microns.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT
High-solids two-component polyamide-cured surface-tolerant epoxy primer
MID COAT
High-build two-component polyamide-cured micaceous iron oxide (MIO)-pigmented epoxy*
FINAL COAT
Two-component aliphatic polyurethane high gloss enamel
APPLICATION OF COATING
PRIMER COAT
Apply surface-tolerant epoxy primer by brush (preferably) or airless spray**
MID COAT 1
Apply MIO-pigmented epoxy by airless spray or brush***
FINAL COAT
Apply aliphatic polyurethane enamel by airless spray or brush
TOTAL DRY FILM THICKNESS

MICRONS
@

125

125

50

300

NOTES :
1. *The epoxy midcoat paint shall contain a minimum of 80% MIO by weight in dry film.
2. ** No primer required for Ri 0 condition surfaces. Patch prime locally blast cleaned areas for
Ri 1 to 3 level breakdown and fully prime surfaces with Ri 4 level or worse coating breakdown.
3. ***Apply full midcoat to surfaces with Ri 1 level or worse breakdown after full or patch priming.
4. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 50 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 2In


GENERAL EXPOSURE TO ATMOSPHERE INSULATED EXISTING ITEMS MAINTENANCE
Insulated existing structural steelwork and insulated external surfaces of existing carbon steel
tanks, vessels, towers, exchangers, heaters, pipework and pipelines located above ground
(onshore) and above the Splash Zone (offshore) with a lower design temperature of down to -46C
or an upper design temperature of up to 120C.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water-soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
Dependent upon condition of existing paintwork.
1. No visible coating breakdown Ri 0 (ASTM No. 10) level. No overcoating required.
2. Partial or variable coating breakdown with primer intact or localised underrusting to no
more than Ri 3 (ASTM No. 6) level. Locally blast clean degraded areas to Sa 2.5 standard as
per ISO 8501-1 plus Supplement. Power tool clean to St 3 standard if blast cleaning impractical.
3. More extensive coating breakdown to Ri 4 (ASTM No. 4) level or worse. Fully blast clean
surfaces to Sa 2.5 standard per ISO 8501-1 plus Supplement. Power tool cleaning to St 3
standard is only acceptable by agreement for small areas and areas that are impractical for
blast cleaning. Use a suitable blast cleaning abrasive to give a surface profile of 50-75 microns.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT
High-solids two-component polyamide-cured surface-tolerant epoxy primer
MID COAT
High-build two-component polyamide-cured micaceous iron oxide (MIO)-pigmented epoxy*
APPLICATION OF COATING
PRIMER COAT
Apply surface-tolerant epoxy primer by brush (preferably) or airless spray**
MID COAT 1
Apply MIO-pigmented epoxy by airless spray or brush***

MICRONS
@

125

125

TOTAL DRY FILM THICKNESS

250

NOTES :
1. * The epoxy midcoat paint shall contain a minimum of 80% MIO by weight in dry film.
2. ** Patch prime locally blast cleaned areas for Ri 1 to 3 level breakdown and fully prime
surfaces with Ri 4 level or worse coating breakdown.
3. ***Apply full midcoat to surfaces with Ri 1 level or worse breakdown after full or patch priming.
4. Areas that protrude through the insulation also require a 50 micron thick coat of aliphatic
polyurethane high gloss topcoat paint.
5. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 51 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 2F
GENERAL EXPOSURE TO ATMOSPHEREFIREPROOFED EXISTING ITEMS MAINTENANCE
Fireproofed newly constructed structural steelwork and fireproofed external surfaces of new
carbon steel vessels, towers, exchangers, heaters, pipework and pipelines located above ground
(onshore) and above the Splash Zone (offshore) with a design temperature of between 0C and
120C.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water-soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
Dependent upon condition of existing paintwork.
1. No visible coating breakdown Ri 0 (ASTM No. 10) level. No overcoating required.
2. Partial or variable coating breakdown with primer intact or localised underrusting to no
more than Ri 3 (ASTM No. 6) level. Locally blast clean degraded areas to Sa 2.5 standard as
per ISO 8501-1 plus Supplement. Power tool clean to St 3 standard if blast cleaning impractical.
3. More extensive coating breakdown to Ri 4 (ASTM No. 4) level or worse. Fully blast clean
surfaces to Sa 2.5 standard per ISO 8501-1 plus Supplement. Power tool cleaning to St 3
standard is only acceptable by agreement for small areas and areas that are impractical for
blast cleaning. Use a suitable blast cleaning abrasive to give a surface profile of 50-75 microns.
GENERIC CLASSIFICATION OF COATING (Please see Note 1*)
PRIMER COAT
High-solids two-component polyamide-cured surface-tolerant epoxy primer**
APPLICATION OF COATING
PRIMER COAT
Apply surface-tolerant epoxy primer by brush (preferably) or airless spray
TOTAL DRY FILM THICKNESS

MICRONS
@

150

150

NOTES :
1. * Alternative proprietary protective maintenance coatings may have to be used where the
fireproofing manufacturer considers that the application of the specified coating system will
prejudice the fireproofing guarantee. In such situations, the manufacturers requirement
shall be mandatory.
2. ** Patch prime locally blast cleaned areas with Ri 1 to 3 level breakdown and fully prime
surfaces with Ri 4 level or worse coating breakdown.
3. Areas that protrude through the fireproofing also require to be coated with a 100 micron thick
coat of MIO-pigmented epoxy midcoat paint (containing a minimum of 80% MIO in the dry film)
plus a 50 micron thick coat of aliphatic polyurethane high gloss topcoat paint.
4. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 52 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 3
UNINSULATED STEEL ITEMS WITH A DESIGN TEMPERATURE OF 120C TO 400C
External surfaces of uninsulated carbon steel tanks, vessels, towers, exchangers, heaters and
pipework operating at elevated design temperatures.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitable abrasive to give
a surface profile amplitude of 35-50 microns. Power tool cleaning is not acceptable for this system.
REPAIR OF DAMAGED COATING (See Clause 11.4)
Vacuum or spot blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement.
MAINTENANCE
1. No visible breakdown of primer or topcoat Ri 0 (ASTM No.10) level (where overcoating
required). Lightly abrade pretreated surfaces with emery paper for good topcoat adhesion.
2. Localised or extensive breakdown of primer or topcoat paint to Ri 1 or ASTM No. 8 level
or worse. Blast clean affected areas to Sa 3 standard as per ISO 8501-1 plus Supplement
using a suitable abrasive to give a surface profile of 35-50 microns.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT*
Ethyl-based two-component inorganic zinc silicate primer
MID COAT
Acrylic modified silicone
FINAL COAT
Acrylic modified silicone
APPLICATION OF COATING
PRIMER COAT
Apply zinc silicate primer by air or airless spray
MID COAT
Apply silicone acrylic by air or airless spray
FINAL COAT
Apply silicone acrylic by air or airless spray
TOTAL DRY FILM THICKNESS

MICRONS
@

50**

25

25

100

NOTES :
1. * Locally damaged areas of primer shall be repaired with a 50 micron thick brush-applied coat
of a suitable high temperature resistant zinc-containing primer.
2. ** Zinc silicate coating thickness shall not exceed 75 microns at any point.
3. No primer is required if the intact coating requires to be overpainted for aesthetic reasons.
4. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 53 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 4
INSULATED STEEL ITEMS WITH A DESIGN TEMPERATURE OF 120C TO 250C
External surfaces of insulated carbon steel vessels, towers, exchangers, heaters and pipework
operating continuously at elevated design temperatures.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Blast clean to Sa 3 standard as per ISO 8501-1 and Supplement using a suitably sized abrasive to
produce a surface profile amplitude of 35-50 microns.
REPAIR OF DAMAGED COATING (See Clause 11.4)
Vacuum or spot blast clean to Sa 3 standard as per ISO 8501-1 and Supplement. Power tool
cleaning to St 3 standard is only acceptable by agreement for areas that are impractical for blast
cleaning. Abrade with emery paper or lightly grind areas of partial coating damage.
MAINTENANCE
1. No visible coating breakdown Ri 0 (ASTM No. 10) level. No coating repair required.
2. Partial or extensive breakdown to Ri 1 (ASTM No. 8) level or worse. Blast clean affected
areas to Sa 2.5 standard as per ISO 8501-1 to give a surface profile of 35-50 microns. Power
tool cleaning to St 3 standard only acceptable by agreement for impractical areas to blast clean.
GENERIC CLASSIFICATION OF COATING*
PRIMER COAT
High-temperature resistant aluminium-pigmented oleo-resinous**
FINAL COAT
High-temperature resistant aluminium-pigmented oleo-resinous
APPLICATION OF COATING
PRIMER COAT
Apply aluminium-pigmented oleo-resinous by air or airless spray
FINAL COAT
Apply aluminium-pigmented oleo-resinous by air or airless spray
TOTAL DRY FILM THICKNESS

MICRONS
@

50

50

100

NOTES :
1. Insulated steel surfaces that will be operating continuously at temperatures of over 250C
do not require to be painted unless specified in the Contract or requested by the QP Engineer.
2. *Insulated surfaces of equipment that will be operating only intermittently at temperatures
over 250C shall be prepared as for this Schedule and protected with two spray-applied coats of
a suitable zinc-free inorganic silicate primer, each applied to a dry film thickness of 75 microns.
3. **Written assurance shall be obtained from the Paint Manufacturer that the paint product
offered has acceptable high temperature resistance.
4. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.
Doc. File No.: SPC.L002.R1

Page 54 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 5
ITEMS EXPOSED TO SEAWATER & SEASPRAY IN THE SPLASH ZONE
Areas of steel structures and pipework subject to partial immersion in seawater and seaspray in
the Splash Zone, such as offshore platforms, boat landings and jetties (but excluding riser lines).
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water-soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitably sized abrasive to
give a surface profile amplitude of 75-100 microns.
REPAIR OF DAMAGED COATING (See Clause 11.4)
Vacuum or spot blast clean to ISO 8501-1 plus Supplement using a suitably sized abrasive to give
a surface profile amplitude of 75-100 microns. Power tool cleaning is not acceptable for even local
repair of this coating system when fully cured. Sweep blast cleaning may be used by agreement.
MAINTENANCE
Dependent upon condition of existing paint coating.
1. No visible coating breakdown Ri 0 (ASTM No. 10). No overcoating required.
2. Partial coating breakdown with localized underrusting to no more than Ri 3 (ASTM No. 6)
level. Locally blast clean degraded areas to Sa 2.5 standard as per ISO 8501-1plus Supplement
3. More extensive coating breakdown to Ri 4 (ASTM No. 4) level or worse. Blast clean to Sa
2.5 standard as per ISO 8501-1 plus Supplement using a suitably sized abrasive to give a
surface profile of 75-100 microns. Power tool cleaning to St 3 standard is only acceptable by
agreement for areas that are impractical for blast cleaning.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT
Two-component high solids glassflake-reinforced polyamine-cured epoxy
FINAL COAT
Two-component high-solids glassflake-reinforced polyamine-cured epoxy
APPLICATION OF COATING
PRIMER COAT
Apply glassflake-reinforced epoxy by airless spray*
FINAL COAT**
Apply glassflake-reinforced epoxy by airless spray*

MICRONS
@

500

500

TOTAL DRY FILM THICKNESS

1000

NOTES :
1. * Brush application shall be used for stripe painting and touch-up areas.
2. ** More than two coats may be required to achieve the required total dry film thickness.
3. Full coating shall be confirmed to be free of pinholes by holiday detection testing as practicable.
4. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.
Doc. File No.: SPC.L002.R1

Page 55 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 6
INTERNAL SURFACES OF STEEL HYDROCARBON & WATER STORAGE TANKS
Topside floor surface of hydrocarbon and water tanks, bottom and top 1.8m of internal shell
surface of hydrocarbon tanks and full internal shell and underside roof surface of potable / nonpotable water tanks.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water soluble degreaser, followed by low
pressure fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitably sized abrasive to
give a surface profile of 75-100 microns and remove all abrasive and dust by vacuum cleaner.
REPAIR OF DAMAGED COATING (See Clause 11.4)
Vacuum or spot blast clean to ISO 8501-1 plus Supplement using a suitably sized abrasive to give
a surface profile amplitude of 75-100 microns. Power tool cleaning to St 3 standard is only
acceptable by agreement for areas that are inaccessible or impractical for blast cleaning.
MAINTENANCE
Dependent on the condition of the existing paint coating.
As for Schedule 5 Maintenance Surface Preparation requirements.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT *
Two-component high-build solvent-free polyamide-cured epoxy**/***
FINAL COAT
Two-component high-build solvent-free polyamide-cured epoxy**/***
APPLICATION OF COATING
PRIMER COAT
Apply solvent-free epoxy by airless spray
FINAL COAT
Apply solvent-free epoxy by airless spray

MICRONS
@

300

300

TOTAL DRY FILM THICKNESS

600

NOTES:
1. * Epoxy holding primer may be used on blast cleaned surfaces if authorised by the QP
Engineer. Request with data, confirming its compatibility with the epoxy paint, shall be submitted
2. ** Non-tainting epoxy paint with Health Certification is required inside potable water tanks.
3. ***Alternative pigmented epoxy coatings may be used subject to satisfactory QP field testing.
4. Full coating shall be subjected to high voltage holiday detection to ensure there are no pinholes
5. A cathodic protection system may be installed in water tanks, to guard against premature
coating breakdown. No internal cathodic protection is required for hydrocarbon service tanks.
6. If cathodic protection is installed, the applied coating system must be compatible with C.P.
7. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application and curing, including the provision of adequate ventilation, shall apply.

Doc. File No.: SPC.L002.R1

Page 56 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 7
UNDERSIDE OF STEEL STORAGE TANK FLOOR PLATES
Underside surface of steel storage tank floor plates prior to laying and welded fabrication.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitably sized abrasive to
give a surface profile amplitude of 75-100 microns.
REPAIR OF DAMAGED COATING (See Clause 11.4)
Vacuum or spot blast clean to ISO 8501-1 plus Supplement using a suitably sized abrasive to give
a surface profile amplitude of 75-100 microns.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT
Two-component polyamide-cured surface-tolerant epoxy primer
FINAL COAT
Two-component polyamide-cured surface-tolerant epoxy primer
APPLICATION OF COATING
PRIMER COAT
Apply surface-tolerant epoxy primer by airless spray*
FINAL COAT
Apply surface-tolerant epoxy primer by airless spray*

MICRONS
@

200

200

TOTAL DRY FILM THICKNESS

400

NOTES :
1. *Brush application for touch-up areas only.
2. A cathodic protection system shall be installed beneath the tank floor to protect the underside
surface against soilside corrosion in areas of coating damage due to welding / paint breakdown.
3. Specified coating system must be confirmed by Manufacturer as being compatible with C.P.
4. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 57 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 8
INTERNAL VESSEL SURFACES SUBJECT TO PRESSURE AND/OR CORROSIVE SERVICE
Internal lining of vessels, exchangers and tanks for service at temperatures up to 120C that are
subject to marked pressure/temperature changes and/or acidic or other aggressive chemicals,
including gasohols.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water soluble degreaser, followed by low
pressure fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitably sized abrasive to
give a surface profile of 75-100 microns and remove all abrasive and dust by vacuum cleaner.
REPAIR OF DAMAGED COATING (See Clause 11.4)
Vacuum or spot blast clean to ISO 8501-1 plus Supplement using a suitably sized abrasive to give
a surface profile amplitude of 75-100 microns. Power tool cleaning is not acceptable for even local
repair of this coating. Abrade partially damaged coatings with emery paper and solvent wipe them.
MAINTENANCE
Dependent upon the condition of the existing coating.
As for Schedule 5 Maintenance Preparation requirements, with the exceptions that all blast
cleaning shall be to Sa 3 standard and power tool cleaning is not acceptable.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT
Two component high-build solvent-free modified epoxy*/**
FINAL COAT
Two component high-build solvent-free modified epoxy*/**
APPLICATION OF COATING
PRIMER COAT***
Apply solvent-free modified epoxy by trowel or brush****
FINAL COAT***
Apply solvent-free modified epoxy by trowel or brush****

MICRONS
@

500

500

TOTAL DRY FILM THICKNESS*****

1000

NOTES :
1. * Assurance shall be obtained from Paint Manufacturer that the coating has acceptable
resistance to all the specified chemicals under the stated temperature and pressure conditions.
2. ** Use of glass flake/ceramic filler is acceptable if required for increased strength and rigidity.
3. *** One or more than two coats of epoxy paint may be applied to achieve the required DFT.
4. **** Coating repairs shall also be carried out by trowel or brush application.
5. ***** Total coating DFT could vary from 500 to 2,000 microns, depending upon product used.
6. The full coating shall be confirmed to be free from pinholes by H.V. holiday detection testing.
7. Coating schedule shall ensure fully curing with good ventilation before it is put into service.
8. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application and curing, including the provision of adequate ventilation, shall apply.
Doc. File No.: SPC.L002.R1

Page 58 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 9
ZINC COATED STEEL SURFACES
New and weathered galvanized and zinc spray coated structural steelwork, pipework, ladders,
handrails, gratings, fencing and other components.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water-soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Remove soluble zinc corrosion products by scrubbing with a stiff bristle brush during fresh water
washing. At QP Engineers discretion, lightly sweep blast clean using a fine abrasive. Abrade with
emery paper, if pretreatment primer is to be applied.
REPAIR OF DAMAGED COATING (See Clause 11.4)
If zinc is intact, remove soluble zinc corrosion products by scrubbing with a stiff bristle brush during
fresh water washing. If rusting of the steel is evident, remove the rust by lightly abrading affected
areas with emery cloth before scrubbing with a stiff bristle brush during fresh water washing.
MAINTENANCE
As for Repair of Damaged Coating but lightly sweep blast clean rusted areas to Sa 2.5 standard.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT */**
High-solids two-component polyamide-cured surface-tolerant epoxy primer***
FINAL COAT
Two-component aliphatic polyurethane enamel
APPLICATION OF COATING
PRIMER COAT
Apply surface-tolerant epoxy primer by airless spray or brush
FINAL COAT
Apply aliphatic polyurethane enamel by airless spray or brush
TOTAL DRY FILM THICKNESS

MICRONS
@

125

50

175

NOTES :
1. * Locally damaged areas of the zinc coating shall be repaired with a 50 micron thick brushapplied coat of zinc-rich epoxy primer containing 90% minimum of zinc by weight in the dry film.
2. **Polyvinyl butyral etch primer or phosphoric acid-based mordant solution shall be applied
as pretreatment, if the surfaces are not sweep blast cleaned or Paint Manufacturer specifies the
need for pretreatment. If pretreatment primer is used, it shall be applied as thinly as possible.
3. ***Written assurance shall be obtained from the Paint Manufacturer that the primer used is
suitable for direct application to freshly galvanized steel surfaces, even if sweep blast cleaned.
4. The requirement for zinc coated components to be painted shall be stated in the Contract.
5. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 59 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 10
HELIDECK & WALKWAY NON-SKID SURFACES
Helidecks and walkway surfaces.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water soluble degreaser, followed by low
pressure fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitably sized abrasive to
give a surface profile amplitude of 75-100 microns.
MECHANICAL REPAIR
Vacuum or spot blast clean to ISO 8501-1 plus Supplement using a suitably sized abrasive to give
a surface profile amplitude of 75-100 microns. Power tool cleaning to St 3 standard is only
acceptable by agreement for areas that are inaccessible or impractical for blast cleaning.
MAINTENANCE
Dependent on the condition of the existing paint coating.
As for Schedule 5 Maintenance Surface Preparation requirements.
GENERIC CLASSIFICATION OF COATING
PRIMER COAT *
Two-component high-build solvent-free epoxy coating incorporating aggregate particles **
FINAL COAT ***
Two-component high-build solvent-free epoxy coating
APPLICATION OF COATING
PRIMER COAT
Apply solvent-free epoxy plus aggregate by airless spray or trowel****
FINAL COAT
Apply solvent-free epoxy by airless spray
TOTAL DRY FILM THICKNESS*****

MICRONS
@

1500

300

1800

NOTES :
1. *Zinc phosphate-pigmented epoxy holding primer, applied to a DFT of 25-50 microns, may
be used on blast cleaned surfaces if authorized by the QP Engineer. A formal request for its use
shall be submitted together with data sheets, confirming its compatibility with the epoxy paint.
2. **Aggregate particles shall be 0.4-1.5mm (average 1.0mm) diameter aggregate for helidecks
and 0.2-1.2mm (average 0.8mm) diameter aggregate particles for walkways.
3. ***All helideck markings shall be made with brush-applied aliphatic polyurethane topcoat paint.
4. ****Aggregate shall be pre-mixed into the paint used for helidecks prior to application.
5. *****Coating thickness will depend upon density and size of aggregate used. Combination of
aggregate and paint binder for any surface should be based on Manufacturers recommendation
6. Deck and walkway coatings shall be confirmed as free from pinholes by H.V. holiday detection
7. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.

Doc. File No.: SPC.L002.R1

Page 60 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 11
BURIED AND FULLY IMMERSED PIPELINES
Pipelines that are either buried or fully immersed in seawater (but not subsea pipelines).
SURFACE PRETREATMENT
Remove all oil, grease and other contamination by primary factory degreasing, followed by
controlled furnace preheating in a production line.
SURFACE PREPARATION
NEW CONSTRUCTION
Blast clean to Sa 2.5 standard* as per ISO 8501-1 plus Supplement under controlled factory
production conditions using a suitably sized abrasive to give a surface profile of 75-100 microns.
REPAIR OF DAMAGED COATING AND WELDED JOINTS
Vacuum or spot blast clean to Sa 3 standard as per ISO 8501-1 plus Supplement using a suitably
sized abrasive to give a surface profile amplitude of 75-100 microns. Power tool cleaning to St 3
standard is not acceptable for this coating system.
MAINTENANCE
Dependent upon the condition of the existing coating.
As for Schedule 5 Maintenance Preparation requirements.
GENERIC CLASSIFICATION OF COATING
PRIMER/FINAL COAT***
Fusion-bonded epoxy powder**
JOINT/REPAIR/MAINTENANCE COATING
Two-component cold-curing high-build solvent-free amine adduct-cured epoxy
APPLICATION OF COATING
MICRONS
PRIMER/FINAL COAT***
Apply fusion-bonded epoxy by electrostatic spray and thermally cure (at factory)
@
550
FIELD JOINTS
Apply fusion-bonded epoxy by electrostatic spray and thermally cure on site**** OR
Apply compatible cold-curing high-build solvent-free epoxy by airless spray*****
@
550
REPAIR/MAINTENANCE COAT
Apply compatible cold-curing high-build solvent-free epoxy by trowel/airless spray @
550
TOTAL DRY FILM THICKNESS

550

NOTES :
1. * Sa 2.5 standard is the highest preparatory standard guaranteed for factory blast cleaning.
2. ** Epoxy powder / factory-applied F.B.E. coating shall meet requirements of QP-SPC-L-005.
3. *** 50 micron thick aliphatic polyurethane topcoat is required for above-ground pipe sections
4. **** Field-applied, thermally-cured F.B.E. coating shall meet requirements of QP-SPC-L-006.
5. ***** Use of shrink wrapped polyethylene or polypropylene sleeves, applied to QP-SPC-L007, may also be considered for field joints, subject to field trials on the product and Contractor.
6. Full coating shall be subjected to a high voltage holiday detection test prior to factory dispatch
and after line fabrication to ensure that it is free from pinholes.
7. F.B.E. Coating QC and test reports shall be approved prior to acceptance of the coated pipe.
8. Concrete weight coating may be applied to submerged pipe sections to counteract buoyancy.
Doc. File No.: SPC.L002.R1

Page 61 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 12
STAINLESS STEEL AND NON-FERROUS METAL SURFACES
Stainless steel, aluminium, copper and nickel alloy pipework, vessels and components with a
design temperature of up to 120C.
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Blast clean to white metal finish (equivalent to Sa 3 standard as per ISO 8501-1) using suitably
sized non-metallic abrasive to give a surface profile amplitude of 50-75 microns.*
MECHANICAL REPAIR
Vacuum or spot blast clean to white metal finish (equivalent to Sa 3 standard as per ISO 8501-1)
using suitably sized non-metallic abrasive to give a surface profile of 50-75 microns.* Power tool
cleaning to white metal is only acceptable by agreement for impractical areas to blast clean.**
MAINTENANCE
As for Schedule 2Un Maintenance Preparation requirements with the exceptions that blast
cleaning or (by agreement) power tool cleaning shall be to white metal finish (equivalent to Sa 3
standard as per ISO 8501-1) using a suitable non-metallic abrasive or similar metal tool. */**
GENERIC CLASSIFICATION OF COATING
PRIMER COAT
Two-component zinc-free polyamide-cured epoxy primer
MID COAT
High build two-component polyamide-cured micaceous iron oxide (MIO)-pigmented epoxy***
FINAL COAT ****
Two-component aliphatic polyurethane high gloss enamel
APPLICATION OF COATING
PRIMER COAT
Apply zinc-free epoxy primer by brush or airless spray
MID COAT
Apply MIO-pigmented epoxy by brush or airless spray
FINAL COAT
Apply aliphatic polyurethane enamel by brush or airless spray
TOTAL DRY FILM THICKNESS

MICRONS
@

50

125

50

225

NOTES :
1. * For copper alloys, a fine abrasive shall be used to avoid surface distortion and expansion.
2. ** Power cleaning tools shall be constructed from the same metal as that being cleaned.
3. *** Minimum 80% MIO in the dry film.
4. **** No topcoat is not required for insulated components other than for protruding areas.
5. Requirement to paint stainless steel or nickel alloy items shall be stated in the Contract.
6. Unless otherwise authorized by the QP Engineer, the Paint Manufacturers recommendations
for paint application shall apply.
Doc. File No.: SPC.L002.R1

Page 62 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

COATING SCHEDULE 13
SELF-ADHESIVE TAPE WRAPPING FOR BURIED AND IMMERSED PIPELINES/STEELWORK
Pipelines with a design temperature up to 70C and structural steelwork that are buried (including
at road crossings), immersed in water or subject to seaspray (but not subsea pipelines).
SURFACE PRETREATMENT
Remove all oil, grease and other contamination using a water soluble degreaser, followed by
thorough fresh water washing.
SURFACE PREPARATION
NEW CONSTRUCTION
Preparation and painting prior to tape primer or adhesive application as follows.
For the Splash Zone, as per Schedule 5 but with only one coat of paint applied.
For buried and fully immersed conditions, apply Schedule 11 Maintenance Coating to 300 um DFT.
MECHANICAL REPAIR
For Splash Zone, as per Schedule 5. For buried or fully immersed conditions, as per Schedule 11.
MAINTENANCE
For Splash Zone, as per Schedule 5. For buried or fully immersed conditions, as per Schedule 11.
GENERIC CLASSIFICATION OF COATING
WRAPPING PRIMER COAT
Rubber or bituminous primer/adhesive.
FINAL COAT */**
Heavy-duty PVC-backed wrapping tape.
EXPOSED FLANGED JOINTS & MACHINED SURFACES (WHERE REQUIRED)
Grease-filled plastic caps for fasteners. Inhibited thermoplastic encapsulation for joints / surfaces.
APPLICATION OF COATING
PRIMER COAT
Apply rubber or bituminous primer/adhesive by brush or spray.
FINAL COAT
Apply heavy-duty PVC-backed wrapping tape by hand or machine to give smooth uniform profile.
EXPOSED FLANGED JOINTS & MACHINED SURFACES
Fit grease-filled caps. Apply thermoplastic encapsulation membrane using specialised equipment.
NOTES :
1. * Above-ground sections of tape wrapped pipelines and steelwork that will be exposed to
sunlight shall be overwrapped using an approved U.V.-resistant outer wrapping.
2. ** Buried or immersed sections of tape wrapped pipelines may be protected against stone and
mechanical damage during burial or laying with a loose protective wrapping sleeve.
3. Tape shall be applied to give a smooth uniform profile with 55% minimum tape layer overlap.
4. Prior to and after application of the wrapping tape, the paint coating shall be subjected to a
low or high voltage holiday detection test, to ensure the absence of pinholes.
5. Concrete weight coating may also be applied to subsea pipework to counteract buoyancy.
6. Unless otherwise authorized by the QP Engineer, the Tape Manufacturers recommendations
for application and testing of the wrapping tape shall apply.

Doc. File No.: SPC.L002.R1

Page 63 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

18.0

REVISION 1

COLOUR CODING & IDENTIFICATION SCHEDULES

18.1

The finishing colours of the paint coatings that are to be applied to the various items of
equipment and facilities shall be in accordance with those specified in the Colour
Coding Schemes given in Tables 6 to 9. The use or acceptance of different colours to
those specified for various items of equipment is subject to the QP Engineers approval.

18.2

The colours used for intermediate coats of paint shall be based upon the Paint
Manufacturers recommendations. Where a multi-coat paint system is specified, it is
desirable for different intermediate coats to be of slightly contrasting colours to
distinguish between and identify the individual coats during paint application and
inspection (see Sub-clause 11.3.3). However, the colour contrasts should not be so
great as to make it difficult to completely obliterate the previous coat.

18.3

Where environmental considerations make it necessary to select an alternative colour


to that recommended, this should be agreed in writing with the QP Engineer prior to
commencement of the work.

Doc. File No.: SPC.L002.R1

Page 64 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

19.0

APPENDICES

19.1

APPENDIX A. TABLES

REVISION 1

19.1.1 The following Tables should be read in conjunction with sections of


Schedules to which they relate.

text

and

19.1.2 The International Standards referenced in the Tables should also be consulted,
where further clarification of the Table contents is required.
19.1.3 Particular attention should be paid to the Notes accompanying many of the Tables.

Doc. File No.: SPC.L002.R1

Page 65 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE 1. CORRESPONDING DEGREES OF PAINT RUSTING STANDARDS


BASIC DESCRIPTION

ISO 4628-3 EURO SCALE ASTM D610

No visible rusting of coating


Localised rusting of 0.05% of coated surface area
Marked localised rusting of 1% of surface area
Widespread localised rusting of 10% surface area
Extensive rusting of up to 50% of surface area

Ri 0
Ri 1
Ri 3
Ri 4**
Ri 5

Re 0
Re 1
Re 3
Re 5
Re 7

No. 10
No. 8*
No. 6
No. 4
No. 1

NOTES: 1. European Scale of Rusting is the same as SIS 18 51 11


2. ASTM D610 Standards have been adopted by SSPC as Visual Standard No. 2
3. *No.8 Standard actually specifies less than 0.1% of coated surface area rusted
4. **Ri 4 Standard actually specifies 8% of coated surface area rusted

TABLE 2. CORRESPONDING SURFACE PREPARATION STANDARDS


BASIC DESCRIPTION

ISO 8501-1

Solvent cleaning
Thorough hand and power tool cleaning
Very thorough power tool cleaning
Light or brush-off blast cleaning
Thorough or commercial blast cleaning
Very thorough or near white metal blast cleaning
Visually clean or white metal blast cleaning
Pickling to white metal

St 2
St 3
Sa 1
Sa 2
Sa 2.5
Sa 3

SSPC
SP 1
SP 2
SP 3/11
SP 7
SP 6
SP 10
SP 5
SP 8

NACE

No. 4
No. 3
No. 2
No. 1

NOTES: 1. ISO 8501 Part 1 is the same as BS 7079 Part A1 and SIS 05 59 00
2. SSPC and NACE Standards are given in Steel Structures Painting Manual, Volume 2

Doc. File No.: SPC.L002.R1

Page 66 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE 3. TYPICAL PAINTING AND WRAPPING QUALITY INSPECTION AND TEST


PLAN CHECKLIST
(SUB) CONTRACTOR
WORK LOCATION
PROJECT TITLE
CONTRACT NO.
ITM.

COATING SCHEDULE
DOCUMENT REF. NO.
EQUIPMENT
DATE

DESCRIPTION OF ITEM

INSPECTION REQD

ACTIONS BY
S/CON

COMMENT

CON QP/TPI

A THROUGHOUT WORKING DAY


1
2
3
4

Safety/condition of equipment/machinery
Correct PPE is worn by all personnel
Atmospheric relative humidity/dewpoint
Metal surface temperature

Visual inspection
Visual inspection
Psychrometer & Tables
Contact thermometer

H
H
I
I

H
H
W
W

H
H
R/H
R/H

I
H
H
I
I
I
I
I
I
I
I
I

H
H
H
R
R
R
H
R
R
R
R
W

H
H
H
R
R
R
H
R
R
R
R
W/H

I
I
I
I
I
I
I
I
I
I
I

R
R
W
W/H
W/H
W
R
W/H
R
R
R

R
R
W
W/H
W/H
W
R
W/H
R
R
R

B BEFORE PREPARATORY CLEANING


Work mthds./QC system/safety measures
2 Permit to work in order and authorised
3 Control/inspection instruments calibrated
4 Presence of surface-breaking defects
5 Defects found are satisfactorily removed
6 Presence of gross surface contamination
7 Rust grade/degree of coating breakdown
8 Type of water/brand of degreasing agent
9 Presence of residual oil or grease
10 Presence of residual chlorides*
11 Type, brand & grade of abrasive used
12 Acceptance of power/hand tool cleaning
1

Record inspection
Record inspection
Visual/record inspection
Visual inspection
Visual inspection
Visual inspection
Visual inspection
Visual inspection
Water spray test
Silver nitrate test
Visual inspection
Visual inspection

C DURING PREPARATORY CLEANING


1
2
3
4
5
6
7
8
9
10
11

Batch number & date of abrasive used


Presence of oil/water in compressed air
Air pressure used for blast cleaning
Blast cleaning surface cleaning standard
Profile height of blast cleaned surfaces
Residual dust and matter on surfaces
Type/condition of power/hand tools used
Standard of power/hand tool cleanliness
Presence of residual millscale*
Presence of iron salts*
Presence of residual chlorides*

Doc. File No.: SPC.L002.R1

Visual inspection
Blotting paper at exhaust
Hypodermic needle gge.
Visual inspection v. Std.
Replica tape/comparator
Tape/pocket microscope
Visual inspection
Visual inspection
Copper sulphate test
Pot. ferricyanide test
Silver nitrate test

Page 67 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE 3. TYPICAL PAINTING AND WRAPPING QUALITY INSPECTION AND TEST


PLAN CHECKLIST (CONTINUED)
D DURING PAINT AND WRAPPING TAPE APPLICATION
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30

Types, brands, dates, condition of paints Visual inspection


Paint storage conditions
Visual inspection
Paint mixing procedure & control
Visual inspection
Rust present on blast cleaned surfaces
Visual inspection
Time between blast cleaning & priming
Record inspection
Paint application technique & quality
Visual inspection
Stripe priming of edges, corners, crevices Visual inspection
Full primer coat thickness
Wet/dry film tkns. check
Primer profile & appearance
Visual inspection
Time between primer & first midcoat
Record inspection
First midcoat & stripe thickness
Wet/dry film tkns. check
First midcoat & stripe profile/appearance Visual inspection
Time between first & second midcoat
Record inspection
Second midcoat & stripe thickness
Wet/dry film thickness
Second midcoat /stripe profile/appearance Visual inspection
Time between second midcoat & topcoat Record inspection
Complete paint coating thickness
Wet/dry film tkns. check
Complete paint coating profile/appearance Visual inspection
Time between final midcoat/tape adhesive Record inspection
Adhesive/primer thickness
Wet film tkns. check
Adhesive/primer profile & appearance
Visual inspection
Time between adhesive & tape wrapping Record inspection
Complete paint and wrapping thickness
Wet/dry film tkns. check
Wrapping profile & appearance
Visual inspection
Final curing time for coating system
Record inspection
Presence of holidays in coating/wrapping Low or high voltage test
Adhesion of coating &/or wrapping*
Dolly pull-off test
Identification of areas for repair
Use of indelible marker
Coating/wrapping appearance after repair Visual inspection
Complete QIT form & associated docs.
Record inspection

KEY: *
I
R
W
H

I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I

R
R
W
R
R
W
R
H
H
R
W
W
R
W
W
R
H
H
R
H
H
R
H
H
R
H
W
W
H
H

R
R
W
R
R
W
R
H
H
R
W
W
R
W
W
R
H
H
R
H
H
R
H
H
R
H
W
W
H
H

Subsidiary inspection test to be carried out at discretion of Corporation's Engineer


Inspection item to be carried out where operation involved forms part of Contract workscope
Inspection reports and records to be fully reviewed and approved
Inspection activity to be witnessed and approved
Mandatory Hold Point in schedule beyond which work shall not proceed without formal approval

SUB-CONTRACTOR

CONTRACTOR

Q.P. / T.P.I.

Signature
Name
Position
Date

Doc. File No.: SPC.L002.R1

Page 68 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE 4. TYPICAL PAINTING AND WRAPPING DAILY INSPECTION REPORT


(SUB) CONTRACTOR
WORK LOCATION
PROJECT TITLE
CONTRACT NO.

COATING SCHEDULE
DOCUMENT REF. NO.
ITEMS COATED
DATE

WEATHER CONDITIONS
Time
Rel. Humidity (%)
Dewpoint (C)
Metal Temp. (C)
SURFACE CONDITION AND DEGREASING
Original Status
Coated
Metal Condition
Defect-free
Metal Rust Grade
A
Coating Breakdown
Ri 0
Contamination
Heavy
Degreasing Agent
.

(Circle as necessary)
Wrapped
Bare
Laminated
Ground
B
C
Ri 3
Ri 4
Light
Degreased
Swabbed
Sprayed

Rejected
D
Ri 5
Water Washed
Water Tested

SURFACE PREPARATION
(Circle as necessary)
Method
Dry Blasting
Sweep Blasting
Wet Blasting
Power Tool
Hand Tool
Abrasive Used
Type. Brand. Batch No... Size Range..
Prep. Standard
Sa 3
Sa 2.5
Sa 2
St 3
Other.
Profile Ht. (um)
35-50
50-75
75-100
Range... Using.
Residual Matter
Class
Rating.
Other Tests
Millscale ..Yes/No
Chlorides... Yes/No
Iron Salts...Yes/No
PAINT AND WRAPPING TAPE APPLICATION
(Circle as necessary)
Method
Airless Spray
Air Spray
Brush
Trowel
Other.
When Priming
Time Since Cleaning..
Visible Surface Rusting...Yes/No
Product Details
Product
Base Batch
Additive
Overcoating WFT Range DFT Range
No.
Batch No.
Period
(um)
(um)
Stripe Coat
Primer
First Midcoat
Second Midcoat
Topcoat
Tape Adhesive
Wrapping Tape
FINAL TESTING AND REPAIR
(Circle as necessary)
Thickness/Appearance
DFT - Accept/Reject
Appearance - Accept/Reject
Holiday Detection Test LV/HV Tester Test Voltage..
Pass/Fail
Coating Adhesion Test Adhesion Tester Pull Off Stress
Accept/Reject
Repaired Areas
% of Total Area.. Primary Locations. Rejected Because.
GENERAL COMMENTS:
SUB-CONTRACTOR

CONTRACTOR

Q.P. / T.P.I.

Signature
Name
Position
Date
Doc. File No.: SPC.L002.R1

Page 69 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE 5. TYPICAL PAINTING AND WRAPPING CLOSE OUT INSPECTION REPORT


(SUB) CONTRACTOR
WORK LOCATION
PROJECT TITLE
CONTRACT NO.

COATING SCHEDULE
DOCUMENT REF.NO.
EQUIPMENT
CLOSE OUT DATE

ITEM COATED
SURFACE PREPARATION
Abrasive
Brand / Size
Other Cleaning
Cleaning Standard
Profile Height
Date

PAINTING
First Coat Product
DFT
Date
Second Coat Product
DFT
Date
Third Coat Product
DFT
Date
Fourth Coat Product
DFT
Date

WRAPPING
Adhesive Product
DFT
Date
Wrapping Tape
Date

TESTING AND REPAIRS


Holiday Test Voltage
Adhesion Test
Repaired Areas (%)

GENERAL COMMENTS
SUB-CONTRACTOR

CONTRACTOR

Q.P. / T.P.I.

Signature
Name
Position
Date
Doc. File No.: SPC.L002.R1

Page 70 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE 6. COLOUR CODING SCHEME FOR EQUIPMENT

ITEM

COLOUR

Structural steelwork, gates, fences & pipe supports


Marine platforms from lower deck to 15 feet below M.S.L.
Painted platform floors & decks (steel & exposed concrete)*
Helidecks**
Helideck guards & markings
Platform accommodation, living spaces, stores & workrooms
Stairways & walkways forming escape routes
Other stairways & walkways
Galvanised vertical ladders & handrails
Overhead obstructions & travelling cranes
Storage tanks, pressure vessels, towers & exchangers,
including skirts & saddles***
Pipework, process valves & fittings
Pumps, compressors, generators & drivers
Electrical & mechanical equipment & instrumentation,
including control panels & supports
Insulation when not clad with aluminium or st. steel sheet
Safety valves (SRV, PRV & TRV) & overpres. protn. devices
Dangerous exposed machinery & electrical installations
Fire fighting installations & equipment
First aid equipment
Hazards & fire & safety systems & signs
Industrial gas cylinders

BS 4800 REF.
NO

Light grey or white*


10-A-03 or 00-E-55
Black
00-E-53
Light grey
10-A-03
Dark grey
18-B-25
Light grey
10-A-03
Light grey
10-A-03
Yellow
10-E-53
Light grey
10-A-03
Yellow
10-E-53
Yellow with black stripes 08-E-51 & 00-E-53
Light grey or white*
10-A-03 or 00-E-55
Service related (Table 7)
Light grey or white*
10-A-03 or 00-E-55
Light grey or manf. finish
Light grey
Peacock blue
Signal red
Signal red
Grass green
Type related (Table 8)
Product related (Table 9)

10-A-03
10-A-03
20-D-45
04-E-53
04-E-53
14-C-39

NOTES: 1. * The same colour shall used for all the components within a particular plant or facility.
2. ** Components to be finished with a non-skid topcoat.
3. *** Colour coding in the form of banding per BS 1710 may be used on the exterior surface of
some tanks and vessels for content identification purposes. Where used, the identification
colours will be the same as those used for pipeline identification (see Table 7).The Corporation's
Engineer should be consulted to establish whether such content colour identification is
required for particular tanks and vessels.

Doc. File No.: SPC.L002.R1

Page 71 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE 7. COLOUR CODING SCHEME FOR PIPEWORK, VALVES AND FITTINGS

IMPORTANCE OF PIPE DIAMETER ON COLOUR CODING REQUIREMENTS


1. PIPEWORK SYSTEMS BELOW 2" NPS DIAMETER (plus firewater pipework of all sizes).
The topcoat paint over the whole external surface shall be in the colour specified in this Table.
2. PIPEWORK SYSTEMS 2" NPS DIAMETER AND LARGER IN SIZE.
The topcoat paint on the external surface shall generally be light grey to BS 4800 code reference number
10-A-03 or white to code reference number 00-E-55 but line identification shall generally be in the form
of bands in the colours specified in this Table applied in accordance with B.S. 1710 requirements.

SERVICE
Gas
NGL condensate & diesel
Crude oil
Process gas
Lube oil
Seal oil
Lean glycol
Rich glycol
Chemical injection
Vents, drains & flare piping
Inert gas
Compressed air
Steam
Seawater
Firewater & fire fighting systems
Brackish water
Potable water
Hot water
Chilled water
Central heating
Refrigeration systems

Doc. File No.: SPC.L002.R1

COLOUR

BS 4800 REF.NO.

Pale green
Teak
Golden brown
Ochre
Pink
Lilac
Emerald green
Yellow
Violet
Black
Dark brown
Peacock blue
Crimson
Grass green
Signal red
Azure blue & green stripes
Light blue
Grass green
Azure blue & light grey stripes
Grass green
Light grey

14-C-35
04-B-25
08-C-37
08-C-35
02-C-33
04-B-17
14-E-53
08-E-51
22-C-37
00-E-53
06-C-39
20-D-45
04-D-45
14-C-39
04-E-53
18-D-43 & 12-D-45
18-E-53
14-C-39
18-D-43 & 10-A-03
14-C-39
10-A-03

Page 72 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE 8. COLOUR CODING SCHEME FOR HAZARDS AND FIRE / SAFETY SIGNS
HAZARD OR SIGN
Safety
Attention
Danger
Mandatory
Alert
Traffic lines
NOTE:

COLOUR

BS 4800 REF. NO.

Grass green
Golden yellow
Signal red
Light blue
Yellow
White

14-C-39
08-E-51
04-E-53
18-E-53
10-E-53
00-E-55

All hazards and fire and safety signs shall have a gloss finish.

TABLE 9. COLOUR CODING SCHEME FOR INDUSTRIAL GAS CYLINDERS


NAME / FORMULA OF GAS

Acetylene (C2H2)
Air (no formula)
Ammonia (NH3)
Argon (Ar)
Carbon dioxide (CO2)
Carbon monoxide (CO)
Chlorine (Cl2)
Coal gas (C2H2CH4)
Ethyl chloride (C2H3Cl)
Ethylene (C2H4)
Helium (He2)
Hydrogen (H2)
Nitrogen (N2)
Oxygen (O2)
Phosgene (COCl2)
Propane (Commercial) (C3H8)
Sulphur dioxide (SO2)

BASE COLOUR
COLOUR BS 4800 REF.
Maroon
Light grey
Black

RAL 3009*
10-A-03
00-E-53

Peacock blue
Black, alumin.
or white
Signal red
Golden yellow
Signal red
Grey
Dark violet
Mid brown
Signal red
Light grey
Black
Black

20-D-45
00-E-53
00-E-55
04-E-53
08-E-51
04-E-53
10-A-30
22-C-37
08-C-37
04-E-53
10-A-03
00-E-53
00-E-53

Signal red
Pale green

04-E-53
14-C-35

BAND COLOUR
COLOUR BS 4800 REF.
None
None
Signal red
Golden yellow
None
White
None
Golden yellow
None
Orange
Signal red
Signal red
None
None
Black
None
Peacock blue
Golden yellow
Mid brown
Golden yellow

N/A
N/A
04-E-53
08-E-51
N/A
00-E-55
N/A
08-E-51
N/A
RAL 2002*
04-E-53
04-E-53
N/A
N/A
00-E-53
N/A
20-D-45
08-E-51
08-C-37
08-E-51

NOTES: 1. * Colour coding to B.S. 381C.


2. All gas cylinders shall have a gloss finish.

Doc. File No.: SPC.L002.R1

Page 73 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

TABLE 10. RESPIRATORY PERSONNEL PROTECTIVE EQUIPMENT


EQUIPMENT

OPERATION OR HAZARD
BLAST
CLEANING

Air-fed blasting helmet*/**


Air-fed hood*
Breathing apparatus
Air-fed mask(pos pres)*
Air line (constant flow)*
Lt./wt. dust respirator
Twin filter respirator
Lt./wt. disposable mask

PAINT
SPRAYING

TOXIC
DUST

NONTOXIC
DUST

CONFINED
SPACES

X
X
X
X

X
X
X

X
X
X
X

NOTES: 1. * Air to be supplied from a remote compressor.


2. ** Blasting helmets shall be certified as meeting the requirements of BS EN 271 and CE marked

TABLE 11. EYE AND FACE PERSONAL PROTECTIVE EQUIPMENT


EQUIPMENT

OPERATION OR HAZARD
BLAST
CLEANING

WATER
JETTING

X
X

Air-fed blasting helmet*/**


Fibre glass hood
Full view safety goggles
Swing-back face shield
Clip-on face shield

GRINDING
X
X
X
X

X
X

METAL
SPRAYING

NONTOXIC
DUST

X
X
X
X

NOTES: 1. * Air to be supplied from a remote compressor.


2. ** Blasting helmets shall be certified as meeting the requirements of BS EN 271 and CE marked
3. Sweat bands shall be worn inside vessels after blast cleaning, to minimize sweat contamination
of the blast cleaned surfaces prior to and during paint application.

TABLE 12. FOOT AND BODY PERSONAL PROTECTIVE EQUIPMENT


EQUIPMENT

OPERATION OR HAZARD
BLAST
CLEANING

WATER
JETTING

GRINDING

X
X

Coveralls
Leather apron
Cloth gloves
Rubber gauntlets
Chrm. leather gauntlets
Rubber thigh boots
Rubber ankle boots
Leather boots

HANDLING PAINT
TINS/BAGS SPRAYING
X

X
X

X
X

X
X
X

NOTES: 1. Rubber ankle boots shall be worn on slippery surfaces, irrespective of the work carried out.
2. Elasticated soft disposable overshoes shall be worn for vessel entry after the internal vessel
surfaces have been blast cleaned.

Doc. File No.: SPC.L002.R1

Page 74 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

19.2

APPENDIX B.

REVISION 1

FIGURES

FIGURE 1. ZONES OF OFFSHORE STRUCTURES FOR CORROSION PROTECTION

Doc. File No.: SPC.L002.R1

Page 75 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

19.3

REVISION 1

APPENDIX C. MINIMUM FORCED VENTILATION REQUIREMENTS FOR


ENCLOSED SPACES DURING PAINT APPLICATION AND CURING
This requirement shall be applicable to all enclosed spaces, including tanks and vessels,
during paint application and throughout the coating curing period. To avoid fires and
explosions, the flammable vapour concentration must be maintained below the lower
explosive limit (L.E.L.). As a guide, the required level of ventilation can be calculated
using the following formula.
N = Q X 125
V
where

N = Number of air renewals per hour


Q = Quantity (average) of paint applied in litres per hour
V = Volume of enclosed space in cubic metres

EXAMPLE
A 1000 cubic metre capacity tank is being lined with a paint that is being applied at an
average rate of 1.5 litres per minute.
N = 1.5 (litres) x 60 (minutes) x 125
1000 (cubic metres)
= 11.25
The minimum level of air ventilation should therefore be 11.25 air changes per hour.
NOTES:
1. The ventilation requirements and efficiency are affected by such variables as the
types of fans and/or eductors used and the presence of dead spaces. It is therefore
often advisable to request that an explosivity meter test is carried out.
2. Even when ventilation meeting the above requirements is provided, it is still possible
for a fire or explosion to occur if the air flow to the actual paint spraying areas is
insufficient. It is therefore advisable to eliminate all possible sources of ignition in
addition to providing the required level of forced ventilation.

Doc. File No.: SPC.L002.R1

Page 76 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

REVISION 1

REVISION HISTORY LOG


Revision Number: 1

Date: October 2001

Item Revised:

Reason for Change/Amendment: New Standard Format

1.03.0
FOREWORD,
OBJECTIVE,
SCOPE &
APPLICATION

Changes/Amendments Made:
OBJECTIVE and APPLICATION
Sections added and
FOREWORD and SCOPE sections modified to meet new
Corporate Standard format

Item Revised

Reason for Change/Amendment: Clarifications


Changes/ Amendments Made:

4.0
TERMINOLOGY

Item Revised

A new Sub- section on Abbreviations added, a number of


Definitions modified and others added
Reason for Change/Amendment: Updates & Additions
Changes/ Amendments Made:

5.0 RELATED
DOCUMENTS

New documents added and superceded and withdrawn


documents deleted

Item Revised

Reason for Change/Amendment: Clarifications

6.0 & 7.0


CONTRACTOR
& H., S. & E.
REQUIREMENT

Changes/ Amendments Made:


Original Sections 6.08.0 & 10.0 completely reorganised into
new Sections 6.0 & 7.0 with expansions for improved clarity

Item Revised

Reason for Change/Amendment: Additions & Clarifications


Changes/ Amendments Made:

8.0 & 9.0 NEW/


MAINTENANCE
PAINTING

New Sections on Painting of New Equipment/Structures and


Maintenance Painting of Existing Equipment/Structure added

Item Revised

Reason for Change/Amendment: Additions & Clarifications


Changes/ Amendments Made:

10.0 SURFACE
PREPARATION

Original Sections 12.0 & 13.0 combined and expanded

Doc. File No.: SPC.L002.R1

Page 77 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

Item Revised

REVISION 1

Reason for Change/Amendment: Additions


Changes/ Amendments Made:

11.0 PAINT
APPLICATION

New Section on Paint Application added

Item Revised

Reason for Change/Amendment: Clarifications & Additions


Changes/ Amendments Made:

12.0 TAPE
APPLICATION

Original Section 14.0 modified and expanded

Item Revised

Reason for Change/Amendment: Clarifications & Additions


Changes/ Amendments Made:

13.0
INSPECTION

Original Section 11.0 modified and expanded

Item Revised

Reason for Change/Amendment: Corporate Quality System


Changes/ Amendments Made:

14.0 QUALITY
REQUIREMENT

New Section on Quality Assurance Requirements added

Item Revised

Reason for Change/Amendment: New Standard Format

Changes/ Amendments Made:


15.0
DOCUMENTTN New Section added to meet new Corporate Standard format
Item Revised

Reason for Change/Amendment: Clarifications


Changes/ Amendments Made:

16.0 SCHEDULE
CLASSIFICATN

Classification Table for Protective Systems modified

Item Revised

Reason for Change/Amendment: Updates & Clarifications


Changes/ Amendments Made:

17.0
SCHEDULES

New explanatory Cover Sheet added, number of Coating


Schedules increased and most Schedules changed to reflect
latest coating & wrapping developments, current industry
practices and new area classifications

Doc. File No.: SPC.L002.R1

Page 78 of 79

Custodian Dept.: FQAD

QP TECHNICAL SPECIFICATION FOR PAINTING & WRAPPING OF METAL


SURFACES (NEW CONSTRUCTION AND MAINTENANCE)
DOCUMENT NO. QP-SPC-L-002

Item Revised

REVISION 1

Reason for Change/Amendment: Clarifications


Changes/ Amendments Made:

18.0 COLOUR
CODING

Cover Sheet modified and Tables moved to Appendix A

Item Revised

Reason for Change/Amendment: Additions & Clarifications


Changes/ Amendments Made:

APPENDIX A.
TABLES

Item Revised

New explanatory Cover Sheet and new Tables on Paint


Rusting and Surface Preparation Standards, Quality
Inspection and Test Plan, Daily and Close Out Inspection
Reports added and original Tables on Colour Coding and
Personal Protective Equipment modified
Reason for Change/Amendment: Additions
Changes/ Amendments Made:

APPENDIX B.
FIGURES

Item Revised

New Figure added to illustrate Protective Zones for Offshore


Structures
Reason for Change/Amendment: New Standard Format
Changes/ Amendments Made:

OLD APPENDIX
A

Renumbered as Appendix C

Item Revised

Reason for Change/Amendment: Product Approval Confusion


Changes/ Amendments Made:

OLD APPENDIX
B. COATING
PRODUCTS

Original Table on Participating Paint Manufacturer Coating


Systems omitted

Doc. File No.: SPC.L002.R1

Page 79 of 79

Custodian Dept.: FQAD

You might also like