TOOL BOX TALK - QUALITY

Work Piles Installation


work

QHSE
DEPARTMENT
TBT NO

PAGE

1 of 1

INTRODUCTION

Important things to be kept in mind while Pile pitching

WHY?

To ensure that material is placed as per the approved drawings, method statement and
specification.

DOs

DONT

Survey Setting out points:

Survey Setting out points:

Ensure that Temporary bench mark point


prior to start of work.

Temporary bench mark (request for


inspection) client approval required.

Ensure that client approved Temporary


bench mark reference copy keep on survey
instrument box.

Use client reference points.

Ensure that all survey instruments should


calibrate.

Use all survey instruments calibration


required.

Use Approved drawing

Ensure that all piles coordinate & levels as


per the approved drawing.
Casing pile driving:

Ensure that casing pile coordinate & levels.

Ensure that casing pile driving records.

Ensure that alignment & plumpness


according with drawings.
Drilling work :

Ensure that bedrock level according with


drawings and design levels.

Ensure that whole dia according with design.

Permanente pile pitching :

Ensure that pile toe level according with


drawings and design levels.

Ensure that pile coordinate & cut of levels


according with drawings and design levels.

Ensure that alignment & plumpness


according with drawings.

Casing pile driving:

Use survey points.

Use approved pile driving check list.

Use template according with drawings.

Drilling work :

Use drilling log.

Permanente pile pitching:

Use pile pitching according with survey


points & drawing.