• Client : Al Wasl
Scope: This method of statement covers the preparation, placement, and curing
of Plain Cement Concrete in accordance with the approved construction
drawings and specifications.
4. Responsibilities:
Construction Manager:
• Overall supervision and coordination of PCC Casting and ensure that
the work activities are in accordance with specs.
Site Engineer:
• Execution of PCC Casting activities in accordance with approved
specifications.
5. Safety Measures:
• All personnel must wear appropriate personal protective equipment (PPE).
• Adequate signage and barricades must be in place to warn against
potential hazards.
• Ensure that workers are trained in concrete handling and safety
procedures.
• Regular safety briefings and toolbox talks should be conducted.
• Ensure the area is accessible.
6. Procedure:
a. Site Preparation:
• Ensure that the Backfilling and Road base are compacted well and in
accordance with specs and the approved drawing.
• Clear the construction area of any debris or obstacles.
• Set up formwork to the required dimensions and alignment.
b. Mixing of Concrete:
• Batch the concrete mix (C20/20 (64% OPC + 36 % CGBS).
• Ensure that the concrete mixer or batching plant is properly calibrated.
• Use clean and suitable aggregates, sand, cement, and water.
d. Finishing:
• Strike off the concrete surface with a straightedge to the required level
As per the approved drawing
• Finish the surface using trowels for a smooth and even appearance.
e. Curing:
• Begin curing immediately after finishing the surface.
• Use curing compounds or cover the concrete with curing blankets or other
suitable methods.
• Maintain the curing conditions for the specified duration.
9. References:
Refer to the approved Specifications, material submittals and relevant
standards throughout the process.