Professional Documents
Culture Documents
150 MIGD
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
2.0 Scope:
This document defines the methods to be adopted for material storage, Installation, testing,
inspection and documentation of SS & CS Pipes and Fittings at IWP Project in UAQ, U.A,E
Subordinate to Site Manager and responsible for the overall control of storage of materials
(pipes & fittings}, installation & jointing. He is also responsible for the coordination with QC
and preparation of Risk Assessment Report in consultation with HSE team and reporting.
Flange Connections:
1. Thoroughly clean the face of the flanges & the gaskets.
2. Inspect the gasket (as per approved material) for any damage. Do not use
damaged gasket. Place the gasket in position and hold it in right place.
3. Insert the flange’s bolts.
4. Install washer and apply nut until it is hand tight
5. Number each bolt starting at the top in a clockwise direction.
6. Tighten all the bolts at 60% of the recommended torque using the diagonally
sequence for two rounds.
7. Tighten all the bolts at 100% of the recommended torque value using the
diagonally
8. Do not over torque the flange bolts
9. Calibrated torque wrench with required socket size and torque capacity shall be
used
• Method of Radiography
• Radiographic examination will be carried out in both Day & Night Shifts.
• Radiographic examination shall be carried out by only qualified & certified
Technicians.
• Obtain all required ES&H Induction and required trainings for all RT Crew Members
before entering to Site.
• Notice of Radiography Notifications will be sent out to all contractors at site in
advance.
• Obtain Radiography Permit, relevant Work Permit & RT Request for carrying out
Radiographic examination from ABJV.
• Identify the job & safe distance from job having acceptable radiation level.
• Establish Safe distance and Cordon off area 360° around the job by barricading
(Poly –Rope with Triangular yellow and black flags with radiation warning signs),
also display radiation warning sign boards & blinker lights at night to avoid
unauthorized personnel in the radiation zone.
• Mobilize the RT Crew to site with radiographic isotopes & equipment.
• Carry out Radiographic exposure for offered welds only.
• After radiographic exposure, carefully retract radioactive source in the projector.
• Demobilization of RT crew from site & keep the source back into the storage pit.
• Developing of films in Dark Room at Site.
QC Inspector shall review in accordance to the drawing and to the requirements of the project
specifications. These data shall be entered in the inspection sheet and to be attached in the
Test Pack documentation.
A. PREPARATIONS
• Only qualified and authorizes personnel shall operate the pressurizing instruments.
• Pipes shall be visually inspected throughout the installation process to ensure the
correct methods are being employed.
• Supervise the test section of the pipeline by qualified supervisor at all times during
the test.
• Measuring instruments to be calibrated prior to its usage.
• The pipe to be restrained against possible movement from sudden failure at a joint
or connection, and proper support / anchorage to be provided where required.
• Test pressure shall be 1.5 x Design Pressure as per project specification.
• Testing shall be carried out as follows:
▪ At the end where the test is to be applied (lowest end where possible)
a test gauge and pressure pump shall be attached.
▪ At the blank a test gauge and air valve shall be fitted. The temporary
air valve shall be fitted at the highest end of the pipeline being test to
allow trapped air within the line to be removed.
▪ The test gauge at the lowest end of the line shall be monitored for
pressure loss.
▪ The test pressure shall be maintained for a as per client
recommendation.
▪ The pressure test is considered complete after a steady specific pressure
has been held for the required minimum test duration time and the
examination are completed.
▪ If the section of pipeline fails, then the pressure shall be released and
the necessary remedial works carried out and retested.
▪ After testing, ensure that the line is depressurized and drain the line
completely.
C. PNEUMATIC TESTING
• Only qualified and authorizes personnel shall operate the pressurizing instruments.
• Visual examination of the piping to verify that the piping and other fitting are free
of any visual defects, etc.
• Verify that all piping is constructed in accordance with approved drawings.
• Verify that all the lines are installed properly as per requirement.
• All the flanges and other related bolted connections are tight
• Supervise the test section of the pipeline by qualified supervisor at all times during
the test.
• The test equipment shall be in accordance with the applicable range and shall be
adequate to provide necessary test pressure at a safe rate of increase and it should
have valid calibration certificates.
• The pipe to be restrained against possible movement from sudden failure at a joint
or connection, and proper support / anchorage to be provided where required.
• Test pressure shall be as per project requirements.
• Testing shall be carried out as follows:
• Connect the compressed air to the piping systems with a
regulator and pressure gauge.
• A minimum of two calibrated pressure gauges will be used for
the test One gauge will be on the test Compressor.
• The test pressure shall be maintained for a as per client
recommendation.
• All joints (welded, threaded & flanged) shall be inspected for
leaks with soap suds.
• The pressure test is considered complete after a steady specific
pressure has been held for the required minimum test duration
time and the examination are completed.
• If the test fails, all defects revealed by the test shall be rectified
and a new test carried out until a satisfactory result is obtained
• Care shall be exercised not to allow the system to stand for
higher lengths of time without venting to atmosphere as
temperature variations may cause excess pressure build up or
create a vacuum.
• After testing, ensure that the line is depressurized.
• The system shall then be depressurized gradually in steps by
holding for sufficient time as done for pressurizing before fully
depressurizing.
D. SAFETY PRECAUTIONS
E. PERSONNEL RESPONSIBILITIES
G. GASKETS
The gaskets to be used in the test should be Kroll and Ziller type gaskets
1. After completion of pressure test, all the system shall be reinstated as per the
approved drawings.
2. Temporary blind flanges, fasteners and other equipment installed for testing shall
be removed on completion of test.
3. The temporary gaskets installed for testing purpose shall be replaced with original
service gaskets
4. Check for the flow direction of reinstalled inline equipment’s.
5. Ensure that right gaskets are installed for all flanges.
6. Bolting shall be completed and torqued to required value.
7. Ensure that all supports are clamped.
8. Do a final line check