EEEEEEEEE

EPC OF LAWE-LAWE FACILITIES RDMP RU-V


BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 1 / 9

ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC)


OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN

WORK METHOD STATEMENT FOR LOADING UNLOADING


GENERATOR

00A 12-Dec-21 Issued for Review Rindra Dudi M Chao Xingang


Rev. Date Description Prepared Reviewed Approved By
EEEEEEEEE
EPC OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 2 / 9

By By
EEEEEEEEE
EPC OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 3 / 9

REVISION LOG

Rev No. Date Page Description


00A 12-Dec-21 All Issued for Review
EEEEEEEEE
EPC OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 4 / 9

TABLE OF CONTENT

1. INTRODUCTION / PENDAHULUAN....................................................................4
2. EQUIPMENTS USED / ALAT YANG DIGUNAKAN................................................5
3. PERSONNEL / PERSONIL...................................................................................5
4. LAYDOWN AREA / AREA LAYDOWN..................................................................5
5. WORK STEPS/ LANGKAH PEKERJAAN...............................................................6
EEEEEEEEE
EPC OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 5 / 9

GENERATOR LOADING AND TRANSPORTATION PLAN /


RENCANA MUAT DAN TRANSPORTASI GENERATOR

1. INTRODUCTION / PENDAHULUAN
Considering our project progress will finish
soon, we plan to loading and demobilization
our generators one by one which there are
3 equipments totally (2 unit are generator
350 KVA and 1 unit is generator 800 KVA).
This work is still in Tank A area. Therefore,
we present this method so that the process
of loading-unloading and moving can run
smoothly. The generator unit can be seen in
the figure below.

Memperhatikan progres pekerjaan kami


yang akan segera berakhir, kami berencana
untuk memuat dan medemobilisasi
generator SC Rig secara berangsur-angsur
dimana terdapat tiga generator yakni dua
unit generator 350 KVA dan 1 unit
generator 800 KVA. Kegiatan ini masih
berada pada area kerja yaitu di area Tank
A. Oleh Karena itu berikut ini kami sajikan
metode atau tahapan proses bongkar-muat
generator sebagai pedoman agar dapat
berjalan dengan aman dan lancar. Unit
generator yang akan dibongkar dapat dilihat
pada gambar dibawah ini.
EEEEEEEEE
EPC OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 6 / 9

Figure 1 Generator 350 KVA

2. EQUIPMENTS AND TOOLS USED / ALAT YANG DIGUNAKAN


The Equipment and tools used to assist the Alat yang digunakan untuk membantu
process of loading of generator 350 KVA proses muat generator 350 KVA yaitu:
are: 1. Crane DC 01
1. Crane DC 01 2. Ring wrench
2. Ring wrench 3. Palu
3. Hammer
Peralatan lifting gear meliputi:
Lifting gear toll consist of: 1. Sekel
1. Shackle 2. Webbing 5 ton (L=5m)
2. Webbing 5 ton (L=5m)

3. PERSONNEL
The personnel involved in this work include - 1 Driver Guide Vehicle
(for 2 tanks): Personil yang terlibat dalam pekerjaan ini
- 1 Construction Manager meliputi :
- 2 Supervisor - 1 Construction Manager
- 1 Rigger - 1 Supervisor
- 1 Crane Operator - 1 Rigger
- 1 Truck trailer driver - 1 operator crane
- 2 Helper - 1 Driver Truk Trailer
- 1 safety Officer - 2 Helper
EEEEEEEEE
EPC OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 7 / 9

- 1 HSE - 1 Driver kendaraan pemandu

4. LAYDOWN AREA/ AREA LAYDOWN

Before loading, the access road condition Sebelum loading, kondisi jalan akses akan
will be checked including turning corner. diperiksa termasuk tikungan belok. Area
Laydown area picked from nearest area laydown dipilih berdasarkan area terdekat
from working zone which located in Tank A. dari zona kerja yang mana berada di Tank
So, all the unit of trailer will be parking in A. Kemudian, seluruh unit trailer akan
Tank A area while waiting for unloading ditempatkan di area Tank A sambil
process. Some personnel needed to menunggu proses bongka muat. Beberapa
escorting through the Tank zone area, personil dibutuhkan untuk mengawal
- 1 pilot to watch the traffic melalui zona area tangki,
- 1 flag man to manage any queue - 1 pilot untuk memperhatikan lalu
traffic lintas
- Speed zone is 20 km/h, travel speed - 1 flag man untuk mengatur antrian
on this road will be 15-18 km/h lalu lintas
- Vehicle to guide route from Gate 3 - Zona kecepatan adalah 20km/jam,
to laydown area kecepatan mengemudi pada jalan ini
adalah 15-18 km/jam
- Kendaraan untuk memandu rute dari
Gate 3 menuju area laydown

Figure 2 Laydown Area

5. WORK STEPS / LANGKAH PEKERJAAN

1) Lifting Generator By Crane/ Mengangkat Generator Dengan Crane

The generator will be lifted by crane, rigger with connected by shackle. Make sure
and helper install webbing from crane to webbing instalation with generator hook is
generator hooks which consists of 4 hooks correct way and shackle pin lock strongly.
as weight sharing and balance when it’s
lifted. The webbing is installed to the hook
EEEEEEEEE
EPC OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 8 / 9

After that, crane operator start to lift the webbing ke hook generator melalui koneksi
generator slowly in order movement efect sekel. Pastikan webbing terpasang dengan
from generator when it’s lifted can reduced benar dan sekel terkunci kuat.
and stable.
Unit Generator diangkat menggunakan Kemudian operator mulai mengangkat
Crane, rigger dibantu helper memasangkan generator secara perlahan agar efek
webbing dari crane ke hook generator pada pergerakan pada generator ketika diangkat
4 sisi berbeda sebagai pembagi beban dan tidak terlalu besar.
agar seimbang saat diangkat. Pemasangan

Figure 3 Generator Hook


2) Loading Generator To Fuso Truck/ Muat Generator Ke Truk Fuso

Make sure before that Fuso truck is on good dengan radius masih dalam jangkauan
and hard platform which is still in crane crane sehingga crane hanya cukup
radius so crane just do swing manuver. melakukan manuver swing.
When crane is lifting the generator, crane Ketika crane sudah mengangkat generator,
operator assisted the rigger loading the selanjutnya operator crane dibantu arahan
generator to the truck’s tailgate by doing rigger memuat generator ke dalam bak truk
swing manuver to Fuso truck position with fuso dengan cara melakukan manuver
the tailgate is opened firstly. After that, the swing ke arah posisi truk fuso dengan
generator is lowered into the tailgate slowly kondisi bak tersebut telah dibuka terlebih
assisted the rigger. Rigger and helper dahulu. Setelah itu, generator diturunkan ke
uninstall webbing instalation at generator dalam bak truk fuso dengan perlahan
and the crane then the driver close the dibantu arahan rigger. Selanjutnyan rigger
tailgate. dibantu helper membuka sambungan
webbing pada generator dan crane
kemudian sopir menutup pintu bak truk
fuso.
Pastikan sebelumnya bahwa kendaraan truk
fuso berada di atas platform yang keras
EEEEEEEEE
EPC OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 9 / 9

Figure 4 Fuso Truck


EEEEEEEEE
EPC OF LAWE-LAWE FACILITIES RDMP RU-V
BALIKPAPAN
Doc. No : 26076-110-GPP-GCX-00094 WORK METHOD STATEMENT FOR LOADING Rev No. : 00A

Job No : 26076 UNLOADING HEAVY EQUIPMENT Page No : 10 / 9