CONCRETE WORKS
PROJECT
EDECS PROJECT
Administrative building for
CONTRACTOR
HILLS CONSTRUCTION
1
• Introduction
• Scope
2
• Objective
The objectives of this method statement is to define construction ,method,
measures, inspection , controls, safety and general practices associated with
the construction of ( horizontal elements ) )&( Vertical Elements )
• Specifications Clauses
3
• RESPONSIBILITIES& Interfacing
• Project Manager have the responsibilities for overall
the project activities including safety measures.
• Coordination with Technical Office Manager to
ensure timely availability and approval of materials,
design mixes in collaboration with Quality Manager,
and shop drawings.
• Assigning areas of responsibility of Senior Site
Engineers.
• Monitoring adherence to project schedule.
• Expediting areas of concern to best achieve project
schedule.
• Site Engineer Shall be supervising closely that
activities designated to them ensuring that all
instruction are followed are strictly adhered to, (this
may involve providing alternative access routes for
moving Traffic with Traffic Signs if necessary are in
place prior to commencing the work, safety
procedures of the project are strictly followed.
4
• The SE shall be responsible for the following
6
Survey shall be responsible for the following
• Sign off and obtain signatures from the Consultant on the forms and
verifying documents as required.
• Carry out statistical analysis of the inspection and test result to improve quality
control operation on site, to verify testing compliance and to advise the SE of
the results.
• Filling and compiling controlled copies of all test reports under the supervision
and instructions of the QC Engineer.
8
• The Lab Tech shall be responsible for
• Safety Inspector: To ensure all safety precautions has been taken into
consideration before commencing the concrete works.
9
10
Main Requirements
11
• Material
• Formwork.
Plywood
Timber
Scaffolding
• Steel Rebar.
• Ready Mix concrete.
• Construction Procedures:
• Preparation
14
• Ensure the position and alignment of starter bars of
columns .
• Clean the starter bar from cement paste or grout.
• Access scaffoldings, ladder etc. will be erected to
allow reinforcement to be fixed.
• Assure that all materials used are from approved
sources.
• Manufacturer's manuals and pre-qualifications for
concrete plants shall be submitted to the consultant
engineer for final approval.
• Assure that there is a clear and safe access for
Pump and trucks during pouring process.
• Assure the availability of sufficient light in case of
concrete casting during night.
• Assure that all safety measures are according to
the approved safety plan.
• Review / Verify the area covered By pouring
concrete by ensuring that the length of pump arm
matches sufficiently.
15
• Execution
• Surveying
• Formwork
• The design and construction of formwork shall take account of safety
and of the surface finish required. The formwork will be sufficiently
rigid and tight to prevent loss of grout or mortar from the fresh concrete
and stand concrete Vibration (Excreted Hydrostatic Pressure) without
Movements. Form work and its supports to maintain the correct position
and to maintain correct shape and profile.
• The formwork for ( horizontal elements) & ( Vertical elements) will
be made of either traditional formwork (plywood and timber and
supported by tie rod and steel support )
• Molds and formwork shall be prepared according to the shop drawing.
• Concrete placement will not commence before Engineer Approval of
Formwork and Rebar Installation.
• Formwork shall be rigid / sturdy and fixed in such a way to retain the
structure members dimensions.
16
• QC ENG will check the formwork installation and safety officer to
ensure safety of the work.
• Formwork installed to true lines and levels.
• For columns, walls shutter will not be closed before QC and consultant
releases. All materials use for temporary form works should be clean
strong and clear from any deflection.
• Forms shall be set to produce hardened concrete of the shape lines. levels
and dimensions indicated on the approved drawings.
• The forms including forms supports shall safely with stand the worst
combination of all loads [Own weight, reinforcement weight, wind load
and dynamic loads caused by casting, vibrating and compacting
concrete].
• Forms shall not be re-used if damaged unless they are well maintained
,cleaned and repaired
17
• Install formwork to its dimensions correctly and ensure that lines and
levels are within the tolerances.
• Steel Reinforcement
• Upon the arrival of steel rebar to site fabrication shop, the rebar
fabrication crew will cut and bend rebar in accordance with project
specification and shop drawings.
• The Site Engineer shall check that the reinforcement is as per
the specification.
• The Site Engineer shall ensure that the cut and bent
reinforcement is as per the approved shop drawings. All concrete
reinforcement shall be detailed, fabricated, labelled, supported, and
18
spaced in the forms and secured in place in accordance with the
project procedures requirements of the project specifications.
• All reinforcement shall be free of rust.
• The Site Engineer shall check the levels, fixings and bracing
for the chairs to ensure that the slab level and safe working loads
for top layers is not exceeded.
19
• Rebar will be assembled either inside or outside the concrete
member, outside assembly steel will be placed by a crane to
avoid any disturbance to the water proofing materials / or
polyethylene plastic sheet. Additionally, when leveling concrete
is provided, rebar mats can be assembled in the place.
• Reinforcement support shall be properly assembled at site: non
Metallic or plastic concrete spacer shall be used to maintain the
cover as required by the specifications. The rebar source will be
submitted to the consultant for approval
• The rebar deliveries will be inspected upon receiving on site by
the quality control engineer and the consultant Engineer.
• Steel reinforcement shall be :Steel reinforcement complying
with the requirements of Egyptian Standard specifications
( ESS) .
• Cold worked bars complying with the requirements of project
Specifications & standers.
• Hot rolled mild steel bars and hot rolled high yield steel
complying with the requirements of project Specifications &
standers.
• All reinforcement shall be supported and fastened together to
prevent displacement during casting.
• Fabricated steel will be placed in position manually, fixed with
sufficient number of crews according to the approved shop
drawings.
• The reinforcement will be placed on concrete spacers to give the
stated concrete cover as per approved shop drawings, project
Specifications & standers.
20
• Splices, bending of steel and other details related to shaping of
reinforcement steel will be done according to approved shop
drawings, project Specifications & standers
• Before placement of concrete , all reinforcement will be free of
mud ,oil, grease, loose rust, mill scale or any other material that
may affect or reduce the adhesion with concrete.
• Welding bars is not allowed unless otherwise approved by the
engineer
21
• Surveyor marks the concrete top level on the shutter as per approved
drawings.
• Direct discharge
• Crane and skip
• Concrete pump
22
• Concrete shall be delivered to site & casted in time less than the
mentioned time limits according to project specifications & ESS.
• Concrete, during and immediately after depositing , shall be thoroughly
compacted. The compacting shall be done by mechanical vibrator.
• The vibration shall be of sufficient duration and intensity to compact the
concrete thoroughly but shall not be continued so as to cause
segregation.
• Each layer shall be compacted so as to avoid the formation of
construction joint with the previous layer which has not taken initial
settlement.
• All necessary laboratory tools for fresh concrete quality testing shall
be available on site prior to pouring of concrete ( cube molds / slump cone,
thermometer etc.)
And third party laboratory technician is available at site or Concrete site
station ( checking temperature, slump air content and fresh concrete
density and samples taken as per specifications ). Then transit mixer
released to specified Concrete location.
Testing
• Concrete tests shall be applied according to project
specifications including
• Slump Test: Slump Range from 160 to 200 mm
Conforming to (ESS)
• Compression Test : Using 3 sets OR according to
ENGINEER of concrete compression test cubes that shall
be prepared , cured and tested in accordance with (ESS)
• Concrete test reports will be submitted to the consultant
Engineer for approval
• Procedure
• The site engineer prepare inspection request (IR) for the area ready for
inspection and submit it to the quality control department.
• The quality control engineer inspect the completeness and accuracy of-
works then sign the (IR) and submit it to the consultant through the
document controller .
• The consultant representative will inspect the work in the presence of the
QC engineer and sign off the (IR).
• In case of rejection, the consultant will write the comments in the (IR)
and hand it to the document controller and a copy is forward to the
construction department to proceed with the comments and the resubmit
after completion.
• In Case of approval (acceptance), the consultant will hand the IR to the
document controller for filing.
Health and Safety
• Safety of the personnel and properties is to be given prime
importance and all the works to be carried out without
causing any accidents or property damages.
• All safety precautions should be taken according to the
approved safety plan.
26