Ref.: MS/C/002
Date: 13-8-2013
Issue Date
13-8-2013
Status
Prepared by
Engineer /
Construction
Manager
Reviewed by
Reviewed by
QA Engineer
Safety Manager
Submission
Tiu Ching Chiu,
Thomas
Date:
13-8-2013
Date:
Reviewed by
Senior Construction
Manager
Date:
Date:
Approved by
Project Manager
Date:
Ref.: MS/C/002
Date: 13-8-2013
Content
Page
1.
2.
3.
4.
Construction Programme 5
5.
6.
7.
8.
Contingency Plan
Appendices
Appendix A - Layout Plan of Additional Trial Pits
Appendix B Shoring Details
Appendix C - Risk Assessment
Ref.: MS/C/002
1.
Date: 13-8-2013
The following soil mechanical tests shall be carried out for the sample retrieved from the trial pit;
i)
In-situ density test
ii)
Relative compaction Test
The movement monitoring on tracks and adjacent Operational Railway Facilities shall be
conducted concurrently to review any impact caused by the trial pit excavation to these facilities.
2.
viii)
ix)
x)
xi)
xii)
Ref.: MS/C/002
Date: 13-8-2013
Ref.: MS/C/002
3.
4.
Date: 13-8-2013
Construction Programme
Tentative Start: Early September; Tentative Finish: End September
5.
6.
Safety access shall be provided. The edge of trial pit shall be fenced off.
Temporary shoring system shall be properly designed. ICE shall check and certify the
temporary works design. After completion of shoring system, ICE shall check and certify the
construction of temporary works construction before carrying out any soil in-site test.
Weekly regularly inspection and checking will be carried out by Competent Person. After
checking, CP will report in CSSR-Form 4 and display it on site.
Temporary stockpile shall be fully covered by tarpaulin sheet and surrounded by continuous
sand bags.
Figure 2 Temporary Stockpile shall be fully covered tarpaulin and surrounded by sand bags.
Ref.: MS/C/002
Date: 13-8-2013
8.
Contingency Plan
The movement monitoring on tracks and adjacent Operational Railway Facilities shall be conducted
concurrently to review any impact caused by the trial pit excavation to these facilities.
If the movement due to the trial excavation exceeding the Alert values be observed, the
Contractors shall revise his method excavation and enhance the monitoring scheme including realtime monitoring tract. The Contact will resubmit the method statement to the Engineer and Railway
Operator for Approval.
~ END ~
Ref.: MS/C/002
Appendix A
Layout Plan of Additional Trial Pits
Date: 13-8-2013
Ref.: MS/C/002
Date: 13-8-2013
Ref.: MS/C/002
Date: 13-8-2013
Ref.: MS/C/002
Ref.: MS/C/002
Ref.: MS/C/002
Ref.: MS/C/002
Appendix B
Shoring Details
Ref.: MS/C/002
Ref.: MS/C/002
Ref.: MS/C/002
Appendix C
Risk Assessment