A Report on
EMBA/13/45
A) Synopsis...1
B) Chapters
1. Introduction......2
1.1 Wind Energy Basics...2
1.2 Wind Energy Cost..6
2. Current status of Wind energy market.9
2.1 Global Wind Energy Sector...9
2.1.1 Africa14
2.1.2 Asia...14
2.1.3 Australia & Oceania..15
2.1.4 Europe...15
2.1.5 Latin America...16
2.1.6 North America..16
2.1.7 Offshore wind farms..17
2.1.8 SWOT Analysis19
2.2 Indian Wind Energy Sector..19
2.2.1 Wind Power development in India...21
2.2.2 The Wind energy Policy structure in India...23
2.2.3 The Current Scenario....24
2.2.4 Foreign Investment Policy....24
2.2.5 Regulatory Issues..25
2.2.6 SWOT Analysis....26
3. Elements of a Wind Project (Value Chain)28
3.1 Design, planning & supervision...28
3.2 Pure component manufacturer.30
3.3 Installation and Operation & Maintenance..31
3.4 Fully integrated service providers34
4. Larsen & Toubro Limited..35
4.1 Prologue...35
4.2 Wind Energy Industry (Porters five force analysis)...36
4.3 SWOT analysis L&T ...37
4.4 SWOT analysis L&T in Wind Energy Industry...39
5. Opportunities in the Wind energy market..43
5.1 International energy market.43
5.1.1 Wind Power Development Strategies Europe43
5.1.2 Wind Power Development Strategies United States..45
5.1.3 Wind Power Development Strategies China..46
5.1.4 Wind Power Development Strategies Offshore.................46
5.2 Domestic energy market..48
D) References...61
EMBA
Synopsis:
International wind markets have seen another impressive year in 2008, with over
27 GW of new capacity brought online and a total installed capacity close to 121GW.
Over the past three years the global wind turbine market has seen explosive growth in
terms of competitors, capacity investments, and project orders as the industry races to
keep up with booming global demand. Scaling exponentially in nearly all dimensions
including the size of turbines, projects, and buyers .The growth in 2008 was primarily
driven by developments in China and the US, but other markets are also starting to
emerge on the wind energy map the industry is generating enormous opportunities for
all players, as well as challenges to improve competitiveness and position wind energy as
a long-term, reliable source of power generation.
Key trends in the international wind market include:
Competition among wind turbine OEMs is rapidly intensifying as growth extends
to new regions, encouraging start-ups of new manufacturers while pushing leading
suppliers to expand their sales and production globally.
Turbine prices, and the costs of installation, have trended upward over the last
four years after nearly a decade of cost reductions per megawatt of nameplate
capacity. The global markets boom in demand has clearly shifted the industry from a
buyers to a sellers market in the past three years, with corresponding price
increases.
Multiple players moving on 2 MW and above segment: Vestas and Enercon
pioneers in 2 MW and larger turbinesare aiming to protect their share of this
market. However, multiple proven machines from Gamesa, Siemens,
Suzlon/REpower, Alstom/Ecotecnia and others are providing buyers more options.
Component suppliers face new challenges to keep pace with turbine demand,
calling for major production capacity investments in the multi-megawatt segment, as
well as a focus on local supply in booming new markets while keeping costs
competitive.
1 of 62
EMBA
1. Introduction
In order to understand the business of wind power we must initially understand the basic
fundamentals and terms which are common in the arena of wind energy and its related
businesses.
a rotor, or blades, which convert the wind's energy into rotational shaft energy;
a nacelle (enclosure) containing a drive train, usually including a gearbox* and a
generator;
a tower, to support the rotor and drive train; and
Electronic equipment such as controls, electrical cables, ground support
equipment, and interconnection equipment
2 of 62
EMBA
Rotor (meters)
Rating (KW)
Annual MWh
1981
10
25
45
1985
17
100
220
1990
27
225
550
1996
40
550
1,480
1999
50
750
2,200
2000
71
1,650
5,600
The electricity generated by a utility-scale wind turbine is normally collected and fed into
utility power lines, where it is mixed with electricity from other power plants and
delivered to utility customers.
What is wind turbines made of?
The towers are mostly tubular and made of steel. The blades are made of fiberglassreinforced polyester or wood-epoxy.
How big is a wind turbine?
Utility-scale wind turbines for land-based wind farms come in various sizes, with rotor
diameters ranging from about 50 meters to about 90 meters, and with towers of roughly
3 of 62
EMBA
the same size. A 90-meter machine, definitely at the large end of the scale at this writing,
with a 90-meter tower would have a total height from the tower base to the tip of the rotor
of approximately 135 meters (442 feet).
Offshore turbine designs are under further development and will have larger rotorsat
the moment, the largest has a 110-meter rotor diameterbecause it is easier to transport
large rotor blades by ship than by land.
Small wind turbines intended for residential or small business use are much smaller. Most
have rotor diameters of 8 meters or less and would be mounted on towers of 40 meters in
height or less.
How much electricity can one wind turbine generate?
The ability to generate electricity is measured in watts. Watts are very small units, so the
terms kilowatt (kW, 1,000 watts), megawatt (MW, 1 million watts), and gigawatt
(pronounced "jig-a-watt," GW, 1 billion watts) are most commonly used to describe the
capacity of generating units like wind turbines or other power plants.
Electricity production and consumption are most commonly measured in kilowatt-hours
(kWh). A kilowatt-hour means one kilowatt (1,000 watts) of electricity produced or
consumed for one hour. One 50-watt light bulb left on for 20 hours consumes one
kilowatt-hour of electricity (50 watts x 20 hours = 1,000 watt-hours = 1 kilowatt-hour).
The output of a wind turbine depends on the turbine's size and the wind's speed through
the rotor. Wind turbines being manufactured now have power ratings ranging from 250
watts to 5 megawatts (MW).
Example: A 10-kW wind turbine can generate about 10,000 kWh annually at a site with
wind speeds averaging 12 miles per hour, or about enough to power a typical household.
A 5-MW turbine can produce more than 15 million kWh in a year--enough to power
more than 1, 400 households. The average U.S. household consumes about 10,000 kWh
of electricity each year.
Example: A 250-kW turbine installed at the elementary school in Spirit Lake, Iowa,
provides an average of 350,000 kWh of electricity per year, more than is necessary for
the 53,000-square-foot school. Excess electricity fed into the local utility system earned
the school $25,000 in its first five years of operation. The school uses electricity from the
utility at times when the wind does not blow. This project has been so successful that the
Spirit Lake school district has since installed a second turbine with a capacity of 750 kW.
Wind speed is a crucial element in projecting turbine performance, and a site's wind
speed is measured through wind resource assessment prior to a wind system's
construction. Generally, an annual average wind speed greater than four meters per
second (m/s) (9 mph) is required for small wind electric turbines (less wind is required
for water-pumping operations). Utility-scale wind power plants require minimum average
wind speeds of 6 m/s (13 mph).
4 of 62
EMBA
The power available in the wind is proportional to the cube of its speed, which means that
doubling the wind speed increases the available power by a factor of eight. Thus, a
turbine operating at a site with an average wind speed of 12 mph could in theory generate
about 33% more electricity than one at an 11-mph site, because the cube of 12 (1,768) is
33% larger than the cube of 11 (1,331). (In the real world, the turbine will not produce
quite that much more electricity, but it will still generate much more than the 9%
difference in wind speed.) The important thing to understand is that what seems like a
small difference in wind speed can mean a large difference in available energy and in
electricity produced, and therefore, a large difference in the cost of the electricity
generated. Also, there is little energy to be harvested at very low wind speeds (6-mph
winds contain less than one-eighth the energy of 12-mph winds).
How many turbines does it take to make one megawatt (MW)?
Most manufacturers of utility-scale turbines offer machines in the 700-kW to 2.5-MW
range. Ten 700-kW units would make a 7-MW wind plant, while 10 2.5-MW machines
would make a 25-MW facility. In the future, machines of larger size will be available,
although they will probably be installed offshore, where larger transportation and
construction equipment can be used. Units up to 5 MW in capacity are now under
development.
How many homes can one megawatt of wind energy supply?
An average U.S. household uses about 10,655 kilowatt-hours (kWh) of electricity each
year. One megawatt of wind energy can generate from 2.4 to more than 3 million kWh
annually. Therefore, a megawatt of wind generates about as much electricity as 225 to
300 households use. It is important to note that since the wind does not blow all of the
time, it cannot be the only power source for that many households without some form of
storage system. The "number of homes served" is just a convenient way to translate a
quantity of electricity into a familiar term that people can understand. (Typically, storage
is not needed, because wind generators are only part of the power plants on a utility
system, and other fuel sources are used when the wind is not blowing. )
What is a wind power plant?
The most economical application of wind electric turbines is in groups of large machines
(660 kW and up), called "wind power plants" or "wind farms."
Wind plants can range in size from a few megawatts to hundreds of megawatts in
capacity. Wind power plants are "modular," which means they consist of small individual
modules (the turbines) and can easily be made larger or smaller as needed. Turbines can
be added as electricity demand grows. Today, a 50-MW wind farm can be completed in
18 months to two years. Most of that time is needed for measuring the wind and
obtaining construction permitsthe wind farm itself can be built in less than six months.
What is "capacity factor"?
Capacity factor is one element in measuring the productivity of a wind turbine or any
other power production facility. It compares the plant's actual production over a given
5 of 62
EMBA
period of time with the amount of power the plant would have produced if it had run at
full capacity for the same amount of time.
A conventional utility power plant uses fuel, so it will normally run much of the time
unless it is idled by equipment problems or for maintenance. A capacity factor of 40% to
80% is typical for conventional plants.
A wind plant is "fueled" by the wind, which blows steadily at times and not at all at other
times. Although modern utility-scale wind turbines typically operate 65% to 90% of the
time, they often run at less than full capacity. Therefore, a capacity factor of 25% to 40%
is common, although they may achieve higher capacity factors during windy weeks or
months.
It is important to note that while capacity factor is almost entirely a matter of reliability
for a fueled power plant, it is not for a wind plantfor a wind plant, it is a matter of
economical turbine design. With a very large rotor and a very small generator, a wind
turbine would run at full capacity whenever the wind blew and would have a 60-80%
capacity factorbut it would produce very little electricity. The most electricity per
dollar of investment is gained by using a larger generator and accepting the fact that the
capacity factor will be lower as a result. Wind turbines are fundamentally different from
fueled power plants in this respect.
If a wind turbine's capacity factor is 33%, doesn't that mean it is only running onethird of the time?
No. A wind turbine at a typical location in the Midwestern U.S. should run about 65-90%
of the time. However, much of the time it will be generating at less than full capacity (see
previous answer), making its capacity factor lower.
What is "availability" or "availability factor"?
Availability factor (or just "availability") is a measurement of the reliability of a wind
turbine or other power plant. It refers to the percentage of time that a plant is ready to
generate (that is, not out of service for maintenance or repairs). Modern wind turbines
have an availability of more than 98%--higher than most other types of power plant.
After more than two decades of constant engineering refinement, today's wind machines
are highly reliable.
6 of 62
EMBA
The three examples above are for costs per kilowatt-hour for a 51 MW wind farm
at three different average wind speeds expressed in meters per second. Cost
figures include the current wind production tax credit.
Improvements in turbine design bring down costs. The taller the turbine tower and the
larger the area swept by the blades, the more powerful and productive the turbine. The
swept area of a turbine rotor (a circle) is a function of the square of the blade length (the
circles radius).
Therefore, a fivefold increase in rotor diameter (from 10 meters on a 25-kW turbine like
those built in the 1980s to 50 meters on a 750-kW turbine common today) yields a 55fold increase in yearly electricity output, partly because the swept area is 25 times larger
and partly because the tower height has increased substantially, and wind speeds increase
with distance from the ground. Advances in electronic monitoring and controls, blade
design, and other features have also contributed to a drop in cost. The following table
shows how a modern 1.65-MW turbine generates 120 times the electricity at one-sixth
the cost of an older 25-kW turbine:
A large wind farm is more economical than a small one. Assuming the same average
wind speed of 18 mph and identical wind turbine sizes, a 3MW wind project delivers
electricity at a cost of $0.059 per kWh and a 51-MW project delivers electricity at $0.036
per kWha drop in costs of $0.023, or nearly 40%. Any project has transaction costs
that can be spread over more kilowatt-hours with a larger project. Similarly, a larger
project has lower O&M (operations and maintenance) costs per kilowatt-hour because of
the efficiencies of managing a larger wind farm.
Optimal configuration of the turbines to take the best advantage of micro-features on
the terrain will also improve a project's productivity.
7 of 62
EMBA
The cost of financing affects the cost of wind energy. Wind energy is capital-intensive,
so the cost of financing constitutes a large variable in a wind energy project's economics.
For a variety of reason financing for wind project remains more expensive than for
mainstream form of electricity generation.
Project ownership affects cost of financing and the economics of a wind power project.
Independent ownershipthat is, financing of projects by private power producers on a
stand-alone basis, is more expensive than utility-owned financing.
How do utility-scale wind power plants compare in cost to other renewable energy
sources?
Wind is the low-cost emerging renewable energy resource.
8 of 62
EMBA
9 of 62
EMBA
General Situation:
Wind energy has continued the worldwide success story as the most dynamically growing
energy source again in the year 2008. Since 2005, global wind installations more than
doubled. They reached 121,188 MW, after 59,024 MW in 2005, 74,151 MW in 2006, and
93,927 MW in 2007. The turnover of the wind sector worldwide reached 40 billion in the
year 2008. The market for new wind turbines showed a 42 % increase and reached an
overall size of 27,261 MW, after 19,776 MW in 2007 and 15,127 MW in the year 2006.
Ten years ago, the market for new wind turbines had a size of 2,187 MW, less than one
tenth of the size in 2008. In comparison, no new nuclear reactor started operation in 2008,
according to the International Atomic Energy Agency.
10 of 62
EMBA
wind turbine capacity. 350 MW were added offshore in 2008, equaling a growth rate of
30 %.
Diversification continues:
This development goes hand in hand with a general diversification process which can be
watched with today 16 markets having installations of more than 1,000 MW, compared
with 13 countries one year ago. 32 countries have more than 100 MW installed,
compared with 24 countries three years ago. Altogether 76 countries are today using wind
energy on a commercial basis. Newcomers on the list are two Asian countries, Pakistan
and Mongolia, which both for the first time installed larger grid-connected wind turbines.
Increasing growth rates:
An important indicator for the vitality of the wind market is the growth rate in relation to
the installed capacity of the previous year. The growth rate went up steadily since the
year 2004, reaching 29.0 % in 2008, after 26.6 % in 2007, 25.6 % in the year 2006 and
23.8 % in 2005. However, this increase in the average growth rate is mainly due to the
fact that the two biggest markets showed growth rates far above the average: USA 50 %
and China 107 %. Bulgaria showed the highest growth rate with 177 %, however, starting
from a low level. Also Australia, Poland, Turkey and Ireland showed a dynamic growth
far above the average.
11 of 62
EMBA
offshore wind farms or under unstable political frameworks and in countries which are
seen as not offering sufficient legal stability.
Wind energy as a low-risk investment
In the mid to long term it is clear that wind energy investments will rather be
strengthened due to their low-risk character and societal and additional economic
benefits. Investment in a wind turbine today means that the electricity generation cost are
fixed to the major extend over the lifetime of the wind turbine. Wind energy implies no
expenses on fuel and operation and maintenance costs are usually well predictable and
rather marginal, in relation to the overall investment.
Employment: Wind energy as job generator
One fundamental advantage of wind energy is that it replaces expenditure on mostly
imported fossil or nuclear energy resources by human capacities and labor. Wind energy
utilization creates many more jobs than centralized, non-renewable energy sources. The
wind sector worldwide has become a major job generator: Within only three years, the
wind sector worldwide almost doubled the number of jobs from 235,000 in 2005 to
440,000 in the year 2008. These 440,000 employees in the wind sector worldwide, most
of them highly skilled jobs, are contributing to the generation of 260 TWh of electricity.
Future prospects worldwide
Based on the experience and growth rates of the past years, it is expected that wind
energy will continue its dynamic development also in the coming years. Although the
short term impacts of the current finance crisis makes short-term predictions rather
difficult, it can be expected that in the mid-term wind energy will rather attract more
investors due to its low risk character and the need for clean and reliable energy sources.
More and more governments understand the manifold benefits of wind energy and are
setting up favorable policies, including those that are stimulation decentralized
investment by independent power producers, small and medium sized enterprises and
community based projects, all of which will be main drivers for a more sustainable
energy system also in the future. Carefully calculating and taking into account some
insecurity factors, wind energy will be able to contribute in the year 2020 at least 12 % of
global electricity consumption. By the year 2020, at least 1,500,000 MW can be expected
to be installed globally. A recently published study by the Energy Watch Group reveals
as one out of four described scenarios that by the year 2025 it is even likely to have
7,500,000 MW installed worldwide producing 16,400 TWh. All renewable energies
together would exceed 50 % of the global electricity supply. As a result, wind energy,
along with solar, would conquer a 50 % market share of new power plant installations
worldwide by 2019. Global non-renewable power generation would peak in 2018 and
could be phased out completely by 2037.
12 of 62
EMBA
Continental Scenarios:
In terms of continental distribution, a continuous diversification process can be watched
as well: In general, the focus of the wind sector moves away from Europe to Asia and
North America. Europe decreased its share in total installed capacity from 65.5 % in 2006
to 61 % in the year 2007 further down to 54.6 % in 2008. Only four years ago Europe
dominated the world market with 70.7 % of the new capacity. In 2008 the continent lost
this position and, for the first time, Europe (32.8 %), North America (32.6 %) and Asia
(31.5 %) account for almost similar shares in new capacity. However, Europe is still the
strongest continent while North America and Asia are increasing rapidly their shares. The
countries in Latin America and Africa counted for respectively only 0.6 % and 0.5 % of
the total capacity and fell back in terms of new installations down to respectively only 0.4
% and 0.3 % of the additional capacity installed worldwide in the year 2008.
13 of 62
EMBA
2.1.1 Africa:
In spite of the huge potentials all over the continent, with worlds best sites in the North
and South of the continent, wind energy plays still a marginal role on the continent with
563 MW of total capacity. Several major wind farms can be found in some of the North
African countries like Morocco, Egypt or Tunisia. In the year 2009 and 2010, substantial
increases can be expected from projects which are already in the development stage.
However, so far, the emergence of domestic wind industry in African countries is only in
a very early stage and donor organizations should put a special focus on the creation of
markets which enable industries to emerge. However, it is interesting to see that
companies from the region are showing an increasing interest and have started investing
in the wind sector. In Sub-Saharan Africa, the installation of the first wind farm in South
Africa operated by an Independent Power Producer can be seen as a major breakthrough.
The South African government prepares the introduction of a feed-in tariff which would
create a real market, enable independent operators to invest and thus play a key role in
tackling the countrys power crisis.
In the mid-term, small, decentralized and stand-alone wind energy systems, in
combination with other renewable energies, will be key technologies in rural
electrification of huge parts of so far un-served areas of Africa. This process has only
started at very few places and the main limiting factor is lack of access to know-how as
well as financial resources.
2.1.2 Asia:
Asia with the two leading wind countries China and India and 24439 MW of installed
capacity is in a position of becoming the worldwide locomotive for the wind industry.
China has again doubled its installations and Chinese domestic wind turbine
manufacturers have started for the first time to export their products. It can be expected
that in the foreseeable future Chinese and Indian wind turbine manufacturers will be
among the international top suppliers. The Indian market has shown robust and stable
growth in the year 2008. It has already a well-established wind industry which already
plays a significant and increasing role on the world markets. Further countries like South
Korea (already with 45 % growth rate in 2008) start investing on a larger scale in wind
energy and it can be observed that more and more companies are developing wind
turbines and installing first prototypes. In parallel with the market growth in the country,
it can be expected that also new manufacturers will be able to establish themselves. The
World Wind Energy Conference held on Jeju island in June 2009 is expected to push the
14 of 62
EMBA
development in the region. Pakistan installed its first wind farm in the year 2008 and the
Government of the country aims at further wind farms in the near future.
2.1.4 Europe:
Europe lost its dominating role as new market but kept its leading position in terms of
total installation with 66160 MW. Germany and Spain maintained as leading markets,
both showing stable growth. The most dynamic European markets were Ireland (adding
440 MW, 55 % growth) and Poland (196 MW added, 71 % growth), the first Eastern
European country with a substantial wind deployment. All in all, the European wind
sector showed almost stagnation with a very small increase in added capacity from 8607
MW to 8928 MW. The biggest market Germany is expected, after the amendment of the
renewable energy law EEG, to show bigger market growth in 2009. An encouraging
change happened in the UK where the government announced the introduction of a feedin tariff for community based renewable energy projects. However, the cap of 5 MW
15 of 62
EMBA
represents a major hurdle so that the UK wind market will still grow at moderate rates.
However, without additional incentives for wind power in more EU member states, such
as improved feed-in legislation, the European Union may not be able to achieve its 2020
targets for renewable energy.
16 of 62
EMBA
administration will improve substantially the political frameworks for wind power in the
country, especially for those type of investors that have practically been excluded from
the production tax credit scheme, like farmers, smaller companies or community based
projects. The credit crunch, however, may lead to delays in project development in the
short term. The Canadian government has rather been hesitating. However, among the
Canadian provinces Quebec and Ontario are showing increasing commitment towards an
accelerated deployment of wind energy. During and after the World Wind Energy
Conference Community Power held in Kingston/Ontario in June 2008, the Government
of Ontario showed strong commitment to rapid expansion of renewable energy and is
expected to present soon a proposal for a Green Energy Act, including feed-in tariffs for
the different renewable energies including wind. In Quebec, contracts for new projects
were signed for a total of 2000 MW, the first to be operational by 2011.
17 of 62
EMBA
Transporting large wind turbine components (tower sections, nacelles, and blades) is
much easier over water than on land, because ships and barges can handle large loads
more easily than trucks/lorries or trains. On land, large goods vehicles must negotiate
bends on roadways, which fixes the maximum length of a wind turbine blade that can
move from point to point on the road network; no such limitation exists for transport on
open water. Construction and maintenance costs per wind turbine are higher for offshore
wind farms, motivating operators to reduce the number of wind turbines for a given total
power by installing the largest available units. An example is Belgium's Thorntonbank
Wind Farm with construction underway in 2008, featuring 5MW wind turbines from
REpower, which were among the largest wind turbines in the world at the time.
18 of 62
EMBA
19 of 62
EMBA
and capacity for manufacture, installation, operation and maintenance of wind electric
generators; and policy support. The programme aims at catalyzing commercialization of
wind power generation in the country. The Wind Resources Assessment Programme is
being implemented through the State Nodal Agencies, Field Research Unit of Indian
Institute of Tropical Meteorology (IITM-FRU) and Center for Wind Energy Technology
(C-WET).
Wind in India are influenced by the strong south-west summer monsoon, which starts in
May-June, when cool, humid air moves towards the land and the weaker north-east
winter monsoon, which starts in October, when cool, dry sir moves towards the ocean.
During the period march to August, the winds are uniformly strong over the whole Indian
Peninsula, except the eastern peninsular coast. Wind speeds during the period November
to march are relatively weak, though higher winds are available during a part of the
period on the Tamil Nadu coastline.
A notable feature of the Indian programme has been the interest among private
investors/developers in setting up of commercial wind power projects. The gross
potential is 45,000 MW (source MNES) and a total of about 8757.2 MW of commercial
projects have been established until March 31, 2008.
The Asian continent is developing into one of the main powerhouses of wind energy. The
strongest market leader in wind energy in the continent is India. With a total of 4,430
MW of wind capacity in 2005, India is in the fourth position in the international wind
power league. The Indian Wind Turbine Manufacturers Association (IWTMA) expects
between 1,500-1,800 MW to be commissioned every year for the next 3 years. Over the
past few years, both the government and wind power industry have succeeded in injecting
greater stability into the Indian market. Incentives by the Central and State Governments
have encouraged large private and public sector enterprises to invest in wind projects
stimulating the domestic manufacturing sector. Some companies now source more than
80% of the components for their turbines. This has contributed to both more cost
effective production and additional local employment. The geographical spread of Indian
wind power has so far been concentrated, especially in the southern state of Tamil-Nadu,
which accounts for more than half of all installations. This is beginning to change with
other states including Maharashtra, Gujarat, Rajasthan and Andhra Pradesh, catching up
in this drive to tap this emerging renewable energy option. With the potential for up to
65,000 MW of wind capacity across the country, the sector can continue further strides
over the next decade. Industry and research programs are geared up to meet this
challenge. With the notable exceptions of Tamil-Nadu, Andhra Pradesh and Gujarat,
other states view wind farms more as a nuisance than a benefit, due to the low reliability
and non-dispatchability. Government policy has placed them in a position where they
have to pay higher prices for wind-generated electricity. This has caused them significant
financial hardship and has not heightened their enthusiasm and support of the technology.
In addition, Indias relatively poor infrastructure previously meant that transport and
installation of megawatt scale wind power technology was impossible (WPM, June
2004:38). In 1996 grid abnormalities induced a 20% loss in potential revenue due to
direct generation loss (inability of wind plants to operate when the wind is blowing).
20 of 62
EMBA
Half of all these losses are due to weak grids in the region. Utilities are suffering the
burden of having wind farms connected to their grids. The rapid growth in wind power
development in the 1990s, rendered grid capacity in the wind farm regions in Tamil Nadu
and Gujarat inefficient in accommodating the wind power. It caused frequent outages of
the grid and reduced return from the wind farms. In 1998, RIS (A national laboratory in
Denmark) and C-WET (Center for Wind Energy Technology) collaborated on a research
project to study wind power integration in weak grids in India.
2.2.1 Wind Power Development in India
The Government of India realized the importance of private sector participation in wind
power as early as 1983/84. Accordingly, a national program was initiated to tap the then
estimated potential of 20,000 MW by adopting a market-oriented strategy. This
ultimately led to a successful commercial development of wind power technology and
substantial additions to power generation capacity in the country. The reassessed gross
wind power potential of the country stands at 45,000 MW. However, the technical
potential, assuming 20 per cent grid penetration, works out to be 13,000 MW. The
technical potential would increase as the grid capacity increases.
According to the Indian Wind Association, the installed wind power capacity was 30
MW in 1990. It increased to 3,568 MW, now the fourth largest in the world. The first
wind power development was a government-supported demonstration plant in 1986.
India witnessed notable wind power developments by the late 1990s, largely due to
incentives such as accelerated depreciation allowance of capital costs and exemptions
from excise duties and sales taxes, and regionally administered feed-in tariffs. India has
been an active supporter of wind development since the 1990s. In the 1990s, Indias
market experienced a significant boom as a result of various tax incentives, attractive
buy-back rates, and some preferential loans. For example, 100% depreciation of wind
equipment was allowed in the first year of project installation, and a 5-year tax holiday
was allowed (Rajsekhar et al., 1999). The national Guidelines for Clearance of Wind
Power Projects implemented in July 1995 (and further refined in June 1996) mandated
that all State electricity boards and their nodal agencies make plans ensuring grid
compatibility with planned wind developments, and that they seek Detailed Project
Reports (DPRs) from independent consultants (for capacities above 1 MW) on all
proposed wind development projects to verify project capital costs and proposed power
generation against certified wind turbine power curves and wind data at the site, before
granting approval for projects (Rajsekhar et al., 1999). The expectations for future market
growth in the early-mid 1990s attracted a number of firms to the Indian market. India has
also developed a national certification program for wind turbines administered by the
Ministry on New and Renewable Sources (MNRS), based in large part on international
testing and certification standards. However, even with extensive government regulations
pertaining to wind farm development, inaccurate resource data, poor installation practices
and poor power plant performance led to a dramatic slowdown of installed capacity in the
Indian market in the late 1990s and early 2000s (Rajsekhar et al., 1999). Policy drivers
also became unstable during this period.
The early perception of growth prospects for India had led to the presence of local
manufacturing of wind turbines by international companies, and more recently Indian
21 of 62
EMBA
companies. As far as the domestic industry is concerned, there are 8 major companies
manufacturing wind turbines and components. These companies are joint-ventures or
licensee of reputed international companies, a majority of them from the EU. Of these, 5
are ISO certified. The manufacturing base not only meets domestic needs but also caters
to the emerging export markets, including Europe. The annual production capacity is of
the order of 500 MW, which can be increased to 750 MW. Large capacity wind turbines
in the range of 1 to 1.25 MW are being produced in the country. Wind turbines of 250
kW - 1,650 kW are being manufactured. These systems require an average wind speed of
about 2.5 m/s to 30 m/s velocity. Wind turbine components are exported to Europe,
Australia and the USA.
India has taken some direct steps to encourage local manufacturing. For example,
customs duties have been levied in favor of importing wind turbine components over
importing complete machines. There is no customs duty on special bearings, gearboxes,
yaw components and sensors for the manufacture of wind turbines, or on parts and raw
materials used in the manufacture of rotor blades. There is a reduced customs duty on
brake hydraulics, flexible coupling, brake calipers, wind turbine controllers and rotor
blades for the manufacture of wind turbines, and the excise duty is exempted for parts
used in the manufacture of electric generators (Rajsekhar et al., 1999). The MNES
(Ministry of Non-Conventional Energy Sources) is implementing a program on small
wind energy and hybrid systems, with the main objectives of - (i) field testing,
demonstrating, and strengthening the manufacturing base of water pumping windmills,
aero-generators/hybrid systems, and (ii) undertaking research and development for
improvements in design and efficiency of these systems. Presently, the program is being
implemented mainly in the states of Andhra Pradesh, Bihar, Gujarat, Karnataka,
Maharashtra, Rajasthan and Tamil Nadu, owing to the felt need for water pumping and
small power generation. The program is, however, being extended to other potential
states also. The program has made very slow progress and not very popular with the
beneficiaries, financial institutions, NGOs, etc. By year 2003-04, 945 water pumping
windmills, aero-generators and hybrid systems of about 370 kW capacity wind-solar
hybrid systems have been installed in the country. The program on water pumping
windmills is being implemented through the SNAs (State Nodal Agencies)/departments.
The manufacturers and suppliers of water pumping windmills are also eligible to market
them to users directly. The program on small aero-generators and hybrid systems is
implemented through the SNAs or user organizations like research institutions, NGOs,
Central and State government organizations, defense organizations, para military forces
and autonomous non-commercial institutions. Despite subsidies ranging from 30 to 75
per cent, the programs are still not popular due to a variety of reasons. The entire project
had been heavily subsidized. It was a failure for two main reasons. The equipment in use
was not adapted to Indian circumstances (hence it broke down and could not be fixed by
the locals) and the communities involved had no sense of ownership in the project.
However, a useful lesson that can be learned from this example is that these wind pumps
have a big role to play in a decentralized rural community, besides avoiding the
aforementioned mistakes. High transaction cost is also a serious concern. At times, the
user prefers grid supply, which is almost free.
22 of 62
EMBA
23 of 62
EMBA
24 of 62
EMBA
of the salient features of Indias foreign investment policies in the renewable sector are as
follows:
Foreign investors can enter into a joint venture with an Indian partner for
financial and/or technical collaboration and also for setting up of renewable
energy based power generation projects.
Liberalized foreign investment approval regime to facilitate foreign
investment and transfer of technology through joint ventures.
The proposal for up to 74 per cent foreign equity participation in a joint
venture qualifies for automatic approval.
100 per cent foreign investment as equity is permissible with the approval of
the Foreign Investment Promotion Board (FIPB).
Various chambers of commerce and industry associations in India can be
approached for providing guidance to investors in finding appropriate
partners.
Foreign investors can also set up a liaison office in India.
The Government of India is also encouraging foreign investors to set up
renewable energy based power generation projects on built, own and operate
basis.
Further, the government also provides several fiscal and financial incentives
for investments in the wind energy sector. These are available to foreign
investors. They include capital subsidy, interest rate subsidy, 80 per cent
accelerated depreciation benefit and exemption/reduction in custom duty,
sales tax, excise tax etc.
The policy adopted by the government successfully attracted several European players
who have their presence in India today, either as a wholly owned subsidiary or joint
ventures, or as technology collaborations. However, most of the investments made were
in the form of private equity in manufacturing ventures. Financial intermediation of other
forms such as debt, working capital and other sophisticated financial services such as
insurance, risk management solutions, etc. is still lacking. In the recent past, several
European banks and FIs (Financial Institutions) have entered the Indian market. Given
below is a compilation of the European banks and financial institutions operating in
India. Most European banks and FIs have not yet realized the attractiveness of the Indian
market, or consider it too risky. As per stakeholders, a couple of existing European banks
in India are active in wind energy investment. Therefore, there remains a significant
potential for financial intermediation between Europe and India.
2.2.5 Regulatory Issues
Power reforms were initiated by the Central Government in 1991.Due to this the sector is
witnessing transformation characterized by unbundling of functions, ownership changes,
the emergence of competitive markets, and the establishment of Regulatory
Commissions. In such a changing scenario government policies and regulatory
approaches are going to have significant influences on the development of grid connected
wind power.
25 of 62
EMBA
Setting up of the CERC (Central Electricity Regulatory Commission) and the SERCs
(State Electricity Regulatory Commission) was a key element of this process. The Central
Government passed legislations enabling the setting up of independent and autonomous
regulatory bodies at central and state levels in July 1998. These regulatory bodies are
expected to promote competition, efficiency, and economy in the consumption of
electricity, and in investments for the development of the sector. The Electricity Act 2003
has certain provisions for renewable energy sources. One additional responsibility of the
SERCs, defined by the Act, is to promote cogeneration and generation of electricity from
renewable sources. Hence it also encourages providing suitable measures for connectivity
with the grid, sale of electricity to any person, and also specifies if it considers
appropriate, for purchase of electricity from such sources, a percentage of the total
consumption of electricity in the area of a distribution license. The role of the state
governments assumes significance in wind power generation. Though the Electricity Act
2003 did away with the need for licenses for setting up small power plants in rural areas,
none of the states have notified this provision. The Electricity Act has not become fully
operational. In each state, wind farms have to sign power purchase agreements with the
respective SEBs (State Electricity Board). ERCs (Electricity Regulatory Commission) fix
the prices at which the unit of power will be purchased. While the Regulatory
Commissions are in the process of evolution, one may encounter conflicting situations
and undue interferences from the political class. Regulatory functions are expected to be
fair and unbiased to all stakeholders.
2.2.6 SWOT Analysis
The wind energy program in India is a positive development. In this context, a SWOT
analysis has been attempted with the viewpoint of enhancing the uptake of this program
in the future years.
a) Strengths
Continuing demand- supply gap and escalation in the cost of fossil fuel-based
power generation and electricity tariffs for industry and organized sector.
Encouragement by Central and State Government policies - fiscal incentives
such as accelerated depreciation and reasonable tariffs for industry and
organized sector.
Growth in wind manufacturing sector- joint ventures as well as indigenous
industry contributing to adoption of the merging technologies, up-scaling size
of machines and cost cutting initiatives.
Massive nation-wide efforts for wind resource assessment covering 25 states,
comprising 900 stations and micro-survey of sites.
Setting up a well managed C-WET, an institution in the public sector with EU
support testing, R & D and advisory functions.
Tactical project management orientation by wind industry, which involves
land procurement, site selection, installation of the wind generation facilities
on a turn key basis by the project developers/ equipment suppliers.
26 of 62
EMBA
b) Weaknesses
Low capacity utilization of the wind generation plants - this is not attributed to
availability of wind but also factors such as
Over- capacity due to biasing of the market mechanism to tax incentives for
installing of wind farms rather than efficient operation. This led to inadequate
resource assessment in advance of construction and poor engineering.
Forced outages due to technical factors such as weak grid integration,
mechanical problems, etc.
Dearth of O & M skills and service organizations.
Small wind power generation program not successful due to techno- economic
considerations and inadequacy of the demonstrative efforts taken up so far.
Rising land costs and developmental issues.
c) Opportunities
Substantial untapped market- off- shore and on- shore.
Enhancing productivity of existing installations by re- powering existing ones.
CDM credits for clean technologies.
Tried and tested technologies for such small applications is under developed
due to mismatch, poor project design, dearth of trouble shooting skills and
barriers in commercial operations. The small wind industry implementation
Strategy (SWIIS) project, co-coordinated by Societe d Etudes Et de
Development (SEED) to increase the sectors impacts through provision of
tools such as sectoral market analyses, a catalogue of manufacturers,
comprehensive listing of available
turbines, their applications and detailed information on hybrid technologies
such as wind-diesel and wind-PV. Similar initiatives are needed in the Indian
context.
d) Threats
Technical progress and financial outlays may not keep pace with the
prospective markets in the future years.
Wind power subsidies may be rationalized or pegged down discouraging
prospective buyers.
Cost cutting may not work out favorably- land costs may shoot up & costcutting ideas by equipment suppliers may dry up.
27 of 62
EMBA
28 of 62
EMBA
Environmental impact
We need to establish baselines for flora and fauna and estimate the impact on the
environment from the wind project leading to Environmental Impact Statements (EIS).
Visual impact and as well as impact from noise and flicker are examples of issues that are
assessed in the EIS. The EIS forms part of the basis on which the local authorities will
decide, whether the wind project is to be approved or not.
Assessment of met-ocean data
We will have to assess wave and current data for input to the structural design.
Furthermore, we need to investigate correlations between waves and wind, which is an
important parameter in connection with the design for fatigue. The assessment of wave
and current data is also to be used in the numerical modeling of the morphological
processes such as erosion and scour.
Geophysical investigations
We will have to specify and perform geophysical investigations and underwater video
recordings. These investigations provide input to the archaeological investigations, the
environmental impact assessment (EIA) and to the base of the structural design.
Geotechnical investigations
In order to adapt the geotechnical investigations to the specific sites, we will have to
specify the investigations in laboratories to suit the individual sites before the
investigations are carried out. Furthermore, we need to carry out and interpret the
geotechnical investigations in order to provide a base for the structural design of the
foundations of the turbines and the laying of cables.
Navigational risk analyses
For offshore wind farms, we will have to estimate the navigational risk for passing
vessels during the construction and during the operational lifetime of the wind farm. The
risk analysis provides input to the environmental impact statement, the financial risk
analysis and to the base of the structural design.
Structural design
We need to perform conceptual or detailed design of all parts of the wind project
including towers, foundations and structures for transformer platforms. The design
amongst others includes in-place analyses, spectral and time-domain dynamic analyses,
fatigue analyses, and drivability of piles. An analysis of transportation and installation is
also required.
Electrical design
We will have to provide overall grid analyses in connection with the implementation of
the wind project, electrical design options for the turbines and the interconnection of
turbines, and design of cabling to connection point/landfall.
Decommissioning
We will have to consider the decommissioning of the wind project as an integral part of
29 of 62
EMBA
the design, as well as an important element within the life-cycle-analyses. This element
hence will need proper attention.
Contracting of wind projects
Based on our experience within construction works and energy projects, we will have to
suggest a contract strategy. Furthermore, we might be required to perform the prequalification of tenders and develop the enquiry documents. Finally, we might have to
perform the tender evaluation and the contracting.
Construction management and supervision
On behalf of the owner we might have to manage the construction and the contract for the
wind project. We might have to perform the commissioning and supervision of all site
works and tests.
Key Players:
Ramboll (www.ramboll-wind.com)
GEC - Global Energy Concepts ( www.globalenergyconcepts.com )
AWS Truewind (www.awstruewind.com )
L&T related businesses @ present:
L&T E&C E&C Projects - Sargent & Lundy Engineering Services
L&T E&C E&C Projects - Power
30 of 62
EMBA
4. Component suppliers face new challenges to keep pace with turbine demand,
calling for major production capacity investments in the multi-megawatt segment,
as well as a focus on local supply in booming new markets while keeping costs
competitive.
Key Players:
1. Rotor / Blades - LM Glasfiber ( www.lmglasfiber.com ) ; Sinoi ( www.sinoi.de )
2. Gear-box Moventas ( www.moventas.com ) ; Bosch ( www.bosch.com )
3. Controls Mita-teknik ( www.mita-teknik.com ) ; Ingeteam (
www.ingeteam.com )
4. Generators ABB ( www.abb.com/windpower )
5. Towers Siag ( www.lausitzer-industriebau.de )
L&T related businesses @ present:
L&T Electrical & Electronics Electrical & Automation Operating Company
L&T Machinery & Industrial Products
L&T Engineering & Construction Heavy Industry
31 of 62
EMBA
Installation:
Installation costs include foundations, normally made of reinforced concrete, road
construction (necessary to move the turbine and the sections of the tower to the building
site), a transformer (necessary to convert the low voltage (690 V) current from the turbine
to 10-30 kV current for the local electrical grid, telephone connection for remote control
and surveillance of the turbine, and cabling costs, i.e. the cable from the turbine to the
local 10-30 kV power line.
Installation Costs will vary
Obviously, the costs of roads and foundations will depend on soil conditions, i.e.
how cheap and easy it is to build a road capable of carrying 30 tonne trucks.
Another variable factor is the distance to the nearest ordinary road, the cost of
getting a mobile crane to the site, and the distance to a power line capable of
handling the maximum energy output from the turbine.
A telephone connection and remote control is not a necessity, but is is often
fairly cheap, and thus economic to include in a turbine installation. Transportation
costs for the turbine may enter the calculation, if the site is very remote, though
usually they will not exceed some 15 000 USD.
Economies of Scale
It is obviously cheaper to connect many turbines in the same location, rather than
just one. On the other hand, there are limits to the amount of electrical energy the
local electrical grid can handle . If the local grid is too weak to handle the output
from the turbine, there may be need for grid reinforcement, i.e. extending the high
voltage electrical grid. It varies from country to country who pays for grid
reinforcement - the power company or the owner of the turbine.
Operation & Maintenance:
Operation and Maintenance Costs for Wind Turbines
Modern wind turbines are designed to work for some 120,000 hours of operation
throughout their design lifetime of 20 years. That is far more than an automobile engine
which will generally last for some 4,000 to 6,000 hours.
Operation and Maintenance Costs
Experience shows that maintenance cost are generally very low while the turbines are
brand new, but they increase somewhat as the turbine ages. Studies done on the various
wind turbines installed around the world since 1975 show that newer generations of
turbines have relatively lower repair and maintenance costs that the older generations.
(The studies compare turbines which are the same age, but which belong to different
generations).
Older wind turbines (25-150 kW) have annual maintenance costs with an average of
around 3 per cent of the original turbine investment. Newer turbines are on average
32 of 62
EMBA
substantially larger, which would tend to lower maintenance costs per kW installed
power (you do not need to service a large, modern machine more often than a small one).
For newer machines the estimates range around 1.5 to 2 per cent per year of the original
turbine investment.
Most of maintenance cost is a fixed amount per year for the regular service of the
turbines, but some people prefer to use a fixed amount per kWh of output in their
calculations, usually around 0.01 USD/kWh. The reasoning behind this method is that
tear and wear on the turbine generally increases with increasing production.
Economies of Scale
Other than the economies of scale which vary with the size of the turbine,
mentioned above, there may be economies of scale in the operation of wind parks
rather than individual turbines. These economies are related to the semi-annual
maintenance visits, surveillance and administration, etc.
Turbine Reinvestment (Refurbishment, Major Overhauls)
Some wind turbine components are more subject to tear and wear than others.
This is particularly true for rotor blades and gearboxes. Wind turbine owners who
see that their turbine is close the end of their technical design lifetime may find it
advantageous to increase the lifetime of the turbine by doing a major overhaul of
the turbine, e.g. by replacing the rotor blades.
The price of a new set of rotor blades, a gearbox, or a generator is usually in the
order of magnitude of 15-20 per cent of the price of the turbine.
Project Lifetime, Design Lifetime
The components of Danish wind turbines are designed to last 20 years. It would,
of course, be possible to design certain components to last much longer, but it
would really be a waste, if other major components were to fail earlier.
The 20 year design lifetime is a useful economic compromise which is used to
guide engineers who develop components for the turbines. Their calculations have
to prove that their components have a very small probability of failure before 20
years have elapsed.
The actual lifetime of a wind turbine depends both on the quality of the turbine
and the local climatic conditions, e.g. the amount of turbulence at the site.
Offshore turbines may e.g. last longer, due to low turbulence at sea. This may
in turn lower costs.
Key Players:
6. Shell ( www.shell.com )
7. Gamesa ( www.gamesacorp.com )
33 of 62
EMBA
34 of 62
EMBA
35 of 62
EMBA
36 of 62
EMBA
EMBA
b) Weakness
Decreasing order book value from Oil & Gas Sector Oil & Gas business
unit is one of the primary revenue earners for the company. Due to the recent
slowdown in the economy and dip in oil prices have forced Oil & Gas majors
to reduce capex investment and issue of new projects (tenders). As a result of
which there have been no new order booking in the Oil & Gas sector for L&T
in the past 6 months (as on end Feb 09)
Talent retention & acquisition retaining existing talent and acquiring new
talent with proper know-how will be the key element for L&T in the years to
view.
c) Opportunities
Strengthening international presence L&T has an international presence,
over the last few years its overseas earnings have grown upto 18 per cent of its
total revenue. With factories and offices located around the country, further
supplemented by a wide marketing and distribution network, L&T's image
and equity extends to virtually every district of India. Over the years the
company has proactively created the necessary infrastructure for its global
initiative with office locations USA, Europe, Middle East and Japan.The
Engineering Construction & Contracts Division made significant progress
during the years in increasing its presence in the overseas markets. The
Division secured orders from international clients located at Malaysia, USA,
UK, Brazil, Saudi Arabia, UAE, Qatar, Bangladesh, Sri Lanka etc
L&T has customers spread across various industry segments, and spread
across various geographical regions in the world. The customer profile
includes leading names such as Samsung, Chevron, Bechtel, Kvaerner, Pirelli,
Siam Michelin, Goodyear, etc. Bechtel is one of the biggest clients of L&T in
the construction business. Bechtel has outsourced a large chunk of the
rehabilitation projects in Iraq and Afghanistan to L&T and its associated
companies. L&T will have to built on its presence and previous track reocrd in
the various regions so as to gain market share and increase contribution
towards the sales revenue.
d) Threats
Interest rate risk significant increase in the interest rates impacts corporate
capex and infrastructure investment adversely. Interest cost has gone up in
L&T because L&T has hedged all foreign currency loans into rupees. There
has been additional borrowing as compared to the previous year, the
additional borrowings are to the extent of almost Rs 2,000 crore and thats
why there has been an interest cost increase. The total interest cost for the
company is around 6% now which was lower last year and that is
predominantly due to the hedging. L&T has completely swapped foreign
currency loans into rupee loans.
Global Slowdown - The general economy slowdown will cast a gloom on the
future order intake as well the execution on account of a dent in the capex
38 of 62
EMBA
plans. Although the visibility exists for a 30% revenue growth over the next
one year, the future will remain uncertain for the time being.
Commodity price volatility L&Ts key raw material inputs comprise
metals, cement, bitumen etc. - A sharp surge in raw material prices impacts
margins adversely
Intense competition L&T is considered as the largest engineering &
construction conglomerate in India. However, due to liberalization and entry
of a number of new entrants the competition has intensified in the local
market. And as L&T has also forayed into international market it is also
facing stiff competition from the existing players in those particular regions.
Global Production L&T has 2 well equipped yards - @ Hazira, India and
@ Sohar, Oman wherein various large scale project execution is carried out.
This state of the art facility will serve an added advantage to reduce cost, keep
a check on product quality and deliver the product on time.
39 of 62
EMBA
L&T can also utilize the capabilities of its Electrical & Electronics business
unit so as to gain added advantage in entering the segment of component
manufacturing.
Strong management L&T has always had a strong management team , the
top management is made up of personalities stalwart in diverse fields with
vast business knowledge and experience. The top management has always
shown prudence when evaluating new business ventures.
Focus towards new initiatives L&T is determined to enter new business
initiatives and develop on its core competency and diversify into related
businesses. L&T is more focused in businesses with higher RoI (Return on
Investment)
b) Weakness
Cash Conversion L&T when competing in the Wind Energy Sector will be
unaware of the cash flow cycle involved in the business.
Growth in Assets overweighing growth in profits as a new entrant into
the field of wind energy L&T will have to weigh its margin in acquiring
projects and in doing so growth in assets may overweigh the growth in profits
c) Opportunities
Environmental awareness and government initiatives there has been
growing environmental awareness towards reducing CO2 emissions and
shifting to a greener option for power generation. Government both domestic
and world-wide have responded to increased demand of power and alternative
sources of energy are being evaluated and initiatives being taken to implement
the same.
Favorable Tax Exemptions in order to encourage organizations to set-up
and enter the renewable source of energy sector, governments are providing
favorable tax exemptions to both operators & service providers.
Untapped Offshore market though 99 % of the wind farms are on-shore
the off-shore market is gradually developing and there is a likelihood of the
early entrant having an added advantage over others
40 of 62
EMBA
Alliances with Power Sector there are possibilities to form alliances with
the power sector which is mostly government owned in India. However,
globally there are private suppliers of power who would be interested in
forming alliances if given a option of cheaper power generation.
Vast coast lines of India and low cost India has a vast coastline with
steady wind speeds & directions for a substantial period of the year which
could be an added advantage for wind power generation on-shore as well as
off-shore.
Steady source of demand
Other renewable energy opportunities seem bright
d) Threats
Technology risk as the wind energy sector is in the first stage of the product
life-cycle there are chances of technology becoming obsolete within a short
span of time and newer advanced technologies replacing the older ones.
Expiry of Federal Production TAX credits in USA may slowdown the
growth - The US Energy Bill has extended production tax credits (PTC) till
31st Dec 2009 only, creating uncertainty for wind farm developers. In the
past, US wind markets have reacted negatively to PTC not being extended.
41 of 62
EMBA
Competencies
Low
Designing,
Planning &
Supervision
Pure Component
Manufacturer
Installation and
Operation &
Maintenance
Medium
Fully Integrated
Service Provider
42 of 62
High
EMBA
EMBA
44 of 62
EMBA
45 of 62
EMBA
46 of 62
EMBA
Project size increasing: Offshore wind is entering a critical phase in which projects
are to move from 100 MW to 400 MW and larger requiring a major scaling up and
technology specialization across the industry.
Europe offshore serving as model for North America and Asia projects: Europe
is set for paced offshore expansion though 2020, with the UK, Germany, and Sweden
driving future growth. North America will begin to take off after 2011, following the
first phase of Cape Wind. Asia will be driven by pilot projects in China, South Korea,
and Taiwan that are set for construction in 2010.
IPPs moving into project development space: Many IPPs are looking to partner
with utilities to realize their offshore projects. As financing becomes more readily
available and project costs decrease in the longer term, the opportunities for IPPs to
become offshore wind plant owners and operators will increase together with their
share of the market.
Utilities leveraging onshore experience offshore: Experience acquired by power
producers developing and managing onshore wind plant can be leveraged into
offshore expansion as these players look to further diversify their energy mix.
New market offers supply chain challenges: To realize the large scale the market
promises, developers must first secure a steady flow of permitted, well financed
projects that will justify major supply chain investments by players that currently
focus more on oil and gas offshore, such as EPC contractors and installation vessel
operators.
On the industry side, the challenge is to create a sustainable offshore wind industry.
While the onshore wind industry is starting to be integrated at European level, offshore
wind is still primarily based around a limited number of European Member State markets.
No series production in offshore wind manufacturing and installation has yet been
established, and the sector is still developing and utilizing large specialized components
rather than the standard components needed for reducing cost. The different challenges of
offshore wind require the industry to move more swiftly to establish links across borders
and develop a European industry for a European market. The creation of such
partnerships, necessary in order to deliver complex offshore projects, will inspire greater
confidence in industry players to develop the techniques and technologies that will enable
the sector to expand rapidly, as onshore wind power has done.
Leading Global Offshore Wind Energy Markets
47 of 62
EMBA
48 of 62
EMBA
49 of 62
EMBA
Utilize low cost labor and skill set availability for manufacturing by setting up
plants in India & China
Continuously reduce cost per unit of power generation and also maintain a consistent
new product launch schedule
Set-up headquarters in Denmark as it is the hub for wind energy market
Form an extensive network of component suppliers
Provide end to end solutions to the clients needs
50 of 62
51 of 62
52 of 62
53 of 62
54 of 62
State
Total
Capacity
(MW) till
31.03.08
Technical
Potential
(MW)
Andhra Pradesh
8275
122.5
1750
Gujarat
9675
1252.9
1780
Karnataka
6620
1011.4
1120
875
10.5
605
Madhya Pradesh
5500
187.7
825
Maharashtra
3650
1755.9
3020
Rajasthan
5400
538.8
895
Tamil Nadu
3050
3873.4
1750
450
1.1
450
2990
3.2
45195
8757.2
Kerala
West Bengal
Others
Total
(All India)
12875
Mar-08
3873.4 MW
1011.4 MW
1755.9 MW
538.8 MW
122.5 MW
187.7 MW
10.5 MW
1252.9 MW
1.1 MW
8754.0 MW
Mar-07
3492.7 MW
821.1MW
1487.7 MW
469.8 MW
122.5 MW
57.3 MW
2 MW
636.6 MW
1.1 MW
7090.8 MW
Mar-06
2894.6 MW
584.5 MW
1001.3 MW
358.1 MW
121.1 MW
40.3 MW
2 MW
338 MW
1.1 MW
5341 MW
Mar-05
2037 MW
410.7 MW
456.2 MW
284.8 MW
120.6 MW
28.9 MW
2 MW
253 MW
1.1 MW
3594.3 MW
55 of 62
State
RPS(%)
specified
Tariffs fixed by
commissions in INR
per kWh
Cross
subsidy
surcharge
for sale to
3rd party
in INR per
kWh
Validity
of tariff
(year)
Charges
for captive
users
1.08
Tamilnadu
10%
2.90 (fixed)
20
10 %
(includes
5% for
banking if
applicable)
Karnataka
7-10%
3.40 (fixed)
10
0.79
13
NIL
20
10%
0.27
1.81
20
2% plus
transmission
charge
20
5%
Flexible
20
2%
4%
1.03
Not
Notified
Not
Notified
1
2%
NIL
Maharashtra
3-6%
Rajasthan
Andhra
Pradesh
7.50%
Madhya
Pradesh
Kerala
5%
10%
3%
West Bengal
Gujarat
3.80%
2%
Haryana
3-10%
3.50 + escalation of
0.15 on an annual basis
3.59 + escalation of
0.02 for the first 12
years + escalation of
0.01 for the balance 8
years
3.37 (fixed)
4.03 reducing at 0.17
per year till the 4th
year; subsequently
fixed at 3.36 till the
20th year
3.14 (fixed)
4.00 (fixed, to be used
as a cap)
3.37 (fixed)
4.08 (with 1.5 %
escalation per year)
* Based on capacity charge plus transmission / distribution losses as per the order
56 of 62
for
the
iv) Parts for the manufacturer/maintenance of blades for rotor of wind operated electricity
generation 5%
v) Raw materials for manufacturer of blades for rotor of wind operated electricity
generators - 5%
Conditions:
(a) If the importer at the time of importation furnishes in all cases, a certificate to the Dy.
Commissioner of Customs or Assistant Commissioner of Customs as the case may be,
from an officer not below the rank of Deputy Secretary to the Government of India in the
Ministry of Non-Conventional Energy Sources recommending the grant of this
57 of 62
exemption and in the case of the goods at (ii) to (v) the said officer certifies that the
goods are required for the specified purposes; and
(b) Furnishes an undertaking to the said Dy. Commissioner of Customs Assistant
Commissioner to the effect that (i) In the case of wind operated electricity generators upto 30 kW, or wind
operated battery chargers upto 30 kW, he shall not sell or otherwise dispose off, in
any manner, such generators or chargers for a period of two years from the date of
importation.
(ii) In case of other goods specified at (ii) to (v), he shall use them for the
specified purpose, and
(iii) In case he fails to comply with sub-conditions (i) or (ii), or both conditions,
as the case may be, he shall pay an amount equal to the difference between the
duty leviable on the imported goods but for the exemption under this notification
and that already paid at the time of importation.
58 of 62
6. Related Companies
Designing & Planning Companies:
Ramboll (www.ramboll-wind.com)
GEC - Global Energy Concepts ( www.globalenergyconcepts.com )
AWS Truewind (www.awstruewind.com )
Pure component manufacturer:
59 of 62
60 of 62
References:
1. World Wind Energy Report 2008
2. Renewables 2007 Global Status Report
3. Global Wind Energy Council www.gwec.net
4. Wind Power: Capacity Factor, Intermittency, and what happens when the wind
doesnt blow? Renewable Energy Research Laboratory, University of
Massachusetts at Amherst
5. Policy Paper on Collaboration between European & Indian Wind Sector
www.euindiawind.net
6. Delivering Offshore Wind Power in Europe by European Wind Energy
Assosiation
7. India Energy Outlook 200 7 KPMG Report
8. http://www.wwindea.org
9. http://www.awea.org
10. http://www.windpowerindia.com
11. http://www.mongabay.com/igapo/technology/EPC.html
12. http://en.wikipedia.org/wiki/Wind_power
13. http://www.larsentoubro.com/lntcorporate/common/ui_templates/homepage_news
.aspx?res=P_CORP
14. http://www.cwet.tn.nic.in/html/information_wtt.html
15. http://www.windpower.org/en/tour/econ/oandm.htm
16. http://www.worldwatch.org/node/5282#wind
17. http://cii.in/documents/Policyreport.pdf
18. The effects of integrating Wind Power on transmission systems Planning,
Reliability, and Operations prepared by GE Energy (March 2005)
19. Indian
Wind
Turbine
http://www.indiawindpower.com
Manufacturers
Association
61 of 62
20. http://www.emerging-energy.com/user/marketstudies.aspx?catid=1
21. www.newenergyfinance.com
22. http://www.moneycontrol.com/india/news/results-boardroom/lt-eyes-larger-highquality-orders-for-ec-biz/361393
23. http://www.moneycontrol.com/news_html_files/news_attachment/2008/LarsenTo
ubro-16-10-08-PL1.pdf
24. http://www.lntenc.com/lntenc/ezine/jan09/Performance_for_the_quarter_ended_dec08.pdf