Professional Documents
Culture Documents
4) Profitability Analysis
4) Profitability Analysis
ECONOMIC ANALYSIS
8.0
INTRODUCTION
Economic analysis is a continuation of market analysis which had been done in design
project one. Economic analysis is a process done to determine whether the plant will
give profit or loss to the company by analyzing the strengths and weaknesses of the
economy.
8.1
Capital costs are the total cost needed to build a plant. Capital cost are fixed and it is
not depends on the level of output. The cost other than the purchased cost of
equipment must take into consideration in order to calculate the capital cost. Table 8.1
show the factors that affecting the cost associated with evaluation of capital cost of
chemical plants.
Estimation of capital cost can be classified into three types according to their accuracy
and purpose:
8.1
Table 8.1: Factors affecting the cost associated with evaluation of capital cost of chemical plants
Factor
Associated
With
The
Symbol
Comments
Installation Of Equipment
1.
(a)
Equipment
f.o.b.
cost
(c)
Material
required
for
Includes all piping, insulation and fireproofing, foundation and structural support,
Installation
Includes all labor associated with installing the equipment and material mentioned in
and material
2.
(a)
Includes all transportation cost for shipping equipment and materials to the plant
site, all insurance on the items shipped, and any purchase taxes that may be
applicable
(b)
Construction overhead
Includes all fringe benefit such as vacation, sick leave retirement benefit, etc.; and
salaries and overhead for supervisory personnel
(c)
contractor
engineering
expenses
3.
Includes salaries and overhead for the engineering, drafting, and project
management personnel on the project
8.2
(a)
Contingency
A factor to cover unforeseen circumstances. These may include loss of time due to
storms and strikes, small changes in the design, and unpredicted price increases.
(b)
Contractor fee
4.
Auxiliary facilities
(a)
Site development
This fee varies depending on the type of plant and a verity of other factors
Includes the purchase of land, grading and excavation of the site; installation and
hook-up of electrical, water and sewer systems; and construction of all internal
roads, walkways, and parking lots
(b)
Auxiliary buildings
(c)
Includes raw material and final product storage; raw material and final product
loading and unloading facilities; all equipment necessary to supply required process
utilities (e.g., cooling water, steam generation, fuel distribution systems, etc.); central
environmental control facilities (e.g., waste water treatment, incinerators, flares,
etc.); and fire protection systems
(Source:Turton,2003)
8.3
There are a few techniques in estimating the cost of a new chemical plant. There are:
1.
total cost is calculated by multiplying the total purchased cost for all major items of
equipment by a constant, which is called the Lang Factor. Values for Lang Factors,
FLang are given in Table 8.2 below.
Table 8.2: Lang Factors for the Lang factor technique
Type of chemical plant
Lang Factor= FLang
Fluid processing plant
4.74
Solid-fluid processing plant
3.63
Solid processing plant
3.10
( Source: Turton, 2003)
(8.1)
Where
N
,
This technique is insensitive to changes in process. It cannot accurately account for the
common problems of special materials of construction and high operating pressure.
8.4
2.
The equipment module costing technique is a common technique to estimate the cost
of a new chemical plant. This approach, introduced by Guthrie, (1969) in the late 1960s
and early 1970s, forms the basis of many of the equipment module techniques in use
today. This costing technique relates all costs back to the purchased cost of equipment
evaluated for some base conditions.
Deviations from these base conditions are handled by using multiplying factors that
depend on the following:
Equation 8.2 below used to calculate the bare module cost for all equipment. The bare
module cost is the sum of the direct and indirect cost shown in Table 8.3.
(8.2)
Where
= purchased
cost
for
base
condition
8.5
Formulae
log
log
log
Equation
+
[log
( + 1)
+ 0.00315
2[850 0.6( + 1)]
=
0.0063
=
log
[log
8.3
8.4
8.5
8.6
Figure 8.1: Step to estimate bare module cost for equipment (Source: Turton,2003)
8.6
8.1.2
Cost of Equipment
The cost of major equipment such as reactor, distillation column separator and heat
exchanger are calculated to estimates the cost of piping and insulation. From Figure
9.1, the equipment use in this plant can be concluded as in Table 8.4 below:
Table 8.4: Total equipment used in plant
Items
Quantity
1
Storage tank
7
2
Heater
3
3
cooler
4
4
Mixer
4
5
Reactor
2
6
Separator
2
7
Heat exchanger
1
8
Distillation column
2
9
Compressor
1
Total
26
(Source : Tourton,2003)
8.1.2.1
Cost of Reactor
The purchased cost of separator at ambient operating pressure using any kind of
material for construction,
is calculated using
reactor made from carbon steel is calculated by substituting value in Table 8.5 into
Equation 8.7 below;
(8.7)
/ versus V, the
/A
840
840
35280
35280
The bare pressure factor, FP for reactor with thickness less than 0.0063 m is found to be
1. The bare module factor, FBM for reactor is found to be 4.
)=
= 35280 4
= $141120
This is the bare module cost for 2001 (CEPCI=397). The cost for 2010 can thus be
calculated by using Equation 9.8 as follows using the CEPCI of 525. (Chemical
Engineering Design, 2008)
(8.8)
For reactor,
2010 =
2001
2010
2001
= 141120
= $186619.60
= RM 565,514.10
= RM 565,514.10 x 3 = RM 1,696,542.24
8.1.2.2
Cost of Separator
The purchased cost of separator at ambient operating pressure using any kind of
material for construction,
K2, K3 are 3.4974, 0.4485 and 0.1074 respectively. Meanwhile, the capacity, A of the
separator is in terms of volume, m3. Thus A is calculated using Equation 8.7 as below:
) ( .
= 7.82
8.8
Therefore, Cp is calculated by using Equation 8.3 that gives the total of $9631.38.
The bare module factor, FBM for demister pad made from nickel alloy gives identification
number as 65 (Turton, 2003) and the factor is found to be 5.3. The bare module cost
then calculated as below;
= ($9631.38)(5.3) = $ 51 046.31
Bare Module Cost, CBM obtained above was from the analysis made during the period
of May to September 2001 with an average value of the CEPCI, I1 of 397 (Turton,
2003). CEPCI, I2 is obtained from the Appendix A (Figure A.2) where I2 is 520.
Therefore, cost of separator in 2011 is calculated using Equation 8.8:
= ($51 046.31)
520
= $66 861.67
397
= RM 202,611.1
8.1.2.3
The costing of a shell and tube heat exchanger, with floating head type, heat transfer
area of 24.10 m2, pressure of 81 bars and having carbon steel as material of
construction using the algorithm outlined in Figure 8.1.
The cost curve for this heat exchanger is shown in Figure 8.2 below. Referring to the
evaluation path shown in Figure 8.3,
(2001) =
=
$650
24.1
= $15,665
8.9
Cp0/A
A
Figure 8.2: Purchased cost for heat exchanger
The bare module cost, CBM for shell and tube heat exchanger is given in Equation 8.6.
The B constant value is as shown in Table 8.6.
Table 8.6: Constants for bare module factor for heat exchanger
Equipment
Type
Equipment Description
B1
B2
Heat
exchanger
1.63
1.66
The pressure factor is obtained from Equation 8.4. Inserting the three constants shown
in Table 9.7 and P = 80 barg (81 bar)
log
log
= 0.1218
81 + 0.08183[log
81]
= 1.32
The value of FM can be found from Figure 8.3 by using identification number of one. The
details for identification number of one as shown in Table 8.8.
8.10
factor,
Material
Identification
Figure 8.3: Material factor
From Figure 8.3, the material factor, FM is 1. This is the case since at base conditions,
(material of construction is carbon steel and operating near atmospheric pressure) the
value of FM and also FP are always unity.
Substituting the data into Equation 8.6;
(2001) =
This is the bare module cost for 2001 (CEPCI=397). The cost for 2010 can thus be
calculated as follows using the CEPCI of 525. (Chemical Engineering Design, 2008)
8.11
Equipment Description
C1
Heat
exchanger
C2
-0.11272
C3
Pressure
Range
(barg)
0.08183 5<P<140
Table 8.8: Identification number for material factor for heat exchanger
identification
number
Equipment Type
Equipment Description
Material of
construction
Heat exchanger
CS-shell/CS-tube
8.12
2010 =
2001
= 104354
2010
2001
525
397
= $138000
= RM 418,181.80
8.1.2.4
V r 2 h
1 . 3728 2 15 . 056
89 .14 m 3
Cp0
V
obtained is 800.
800
C p0 650 89 .14
C0p = $57941
The pressure factors for process vessels,Fp is calculated by using equation 8.4 as
expressed below.
Fp
(1.2 1)1.3728
0.00315
2850 0 .6(1.2 1)
0.0063
= 0.78
8.13
The bare module cost, CBM for distillation column is given in Equation 8.6. The B
constant value is as shown in Table 8.9 below.
Table 8.9: Constants for bare module factor for distillation column
Equipment Type
B1
B2
Distillation column
2.25
1.0
FBM = B1 + B2 FP FM
= 2.25 + (1.82) (0.78) (1.0)
= 3.67
New CBM
= 212643.5
521.9
397
= $ 279543.20
= RM 847,101.50
The purchased cost of vessel internal at ambient operating pressure using any kind of
material for construction
is;
8.14
= 1218.45
Formula for Sieve Tray:
From Table A.5, Material and Quantity Factors for Sieve Trays
CBM C 0p NFBM Fq
Where,
N = the number of tray
Fq = the quantity factor for trays
For tray >20,
F q = 1.00
Thus, bare module cost is calculated as below;
C BM C p0 NFBM Fq
1218 .45 25 3 .67 1 .00
= $ 111792.79
= RM 335378.36
This is the bare module cost for 2001 (CEPCI=397). The cost for 2010 can thus be
calculated as follows using the CEPCI of 521.9. (Chemical Engineering Design, 2008)
New CBM = 335378.36
521.9
397
= RM 440891.60
8.15
Assuming the distillation column 1 is the same properties with the distillation column
2.Therefore, Total Costing for Distillation Column 3 and 4 is = RM 1279521.20x 2
= RM 2559042.40
The bare module cost for all equipments are concluded in Table 8.10 below. Almost all
of the equipments are made from carbon steel since the components involve in this
plant are not reactive towards carbon steel.
Table 8.10: Summary on bare module cost for equipment used in 1-propanol production
plant
Material of
Construction
Bare module
cost at non-base
conditions,
(RM)
Bare module
cost at base
conditions,
(RM)
Carbon steel
3,719,731.02
2,812,824.45
Carbon steel
418,140
316,192.62
Fired-Heater (E-100)
Carbon steel
720,794.58
545,057.91
Fired-Heater(E-101)
Carbon steel
994,515.08
752,042.91
Fired-Heater(E102)
Carbon steel
964,742.601
729,529.10
Cooler (E-103)
Carbon steel
602,959.70
455,952.40
Cooler (E-104)
Carbon steel
610,575.30
461,711.16
Cooler (E-106)
Carbon steel
590,093.41
446,222.98
Cooler (E107)
Carbon steel
602,959.70
455,952.40
Reactor (PFR-100)
Carbon steel
565,514.10
427,593.60
Reactor (CRV-100)
Carbon steel
1,696,542.25
1,282,780.80
Equipment
Compressor
Compressor (K-100)
Heat Exchanger
Heat Exchanger(E-105)
Fired-Heater
Cooler
Reactor
Storage Tank
8.16
Carbon steel
172,628.07
130,539.70
Carbon steel
201,651.47
152,486.93
Carbon steel
201,651.47
152,486.93
Carbon steel
187,677.17
141,919.69
Carbon steel
172,628.07
130,539.70
Storage Tank(Tk-106)
Carbon steel
187,677.17
141,919.69
Storage Tank(Tk-107)
Carbon steel
82,682.06
62,523.38
Vessel (V-101)
Carbon steel
202,590.86
154,670.32
Vessel (V-102)
Carbon steel
213082.08
161,130.64
Mixer (Mix-100)
Carbon steel
3,455.49
2,613.01
Mixer (Mix-101)
Carbon steel
6,274.97
4,745.07
Mixer (Mix-103)
Carbon steel
1,521.99
1,150.92
Mixer (Mix-104)
Carbon steel
1,004.18
759.35
DC (T-100)
Carbon steel
10,253,895.70
7,753,898.47
DC(T-101)
Carbon steel
9,409,710.45
7,115,533.83
Cast steel
62,523.44
82,379.03
32,847,222.38
24,875,157
Separator
Mixer
Distillation Column
Waste treatment
Totals
8.1.3
According to Turton et al, (2003), the term grass roots refers to a completely new facility
in which we start the construction on essentially undeveloped land, a grass field. The
term total module cost refers to the cost of making small to moderate expansions or
alterations to an existing facility. It is necessary to account for other costs in addition to
the direct and indirect costs (item 1 and 2 respectively) which are equivalent to bare
module cost costs to estimate these costs. These additional costs are contingency and
fee costs as well as auxiliary facilities costs as shown in Table 8.1 (item 3 and 4
respectively).
8.17
The total module cost can be evaluated from the following formula
= 1.18
(8.9)
+ 0.5
(8.10)
Where n is represents the total number of pieces of equipments. Inserting the values
into the equations above equations gives the following
= 1.18
= 1.18 (32,847,222,38)
=
38,759,722.41
+ 0.5
= 38,759,722.41 + 0.5 (24,875,157.00)
=
8.2
51,197,300.91
The cost associated with the day-to-day operation of a chemical plant must be
estimated before economic feasibility of a proposed process can be assessed. There
are many elements that influence the manufacturing cost. A list of important costs
involved, including a brief explanation of each cost, is given in Table 8.11. The cost
information provided in the table is divided into three categories.
8.18
DESCRIPTION OF FACTOR
1.
Direct costs
A.
Raw materials
(CRM)
B.
Waste treatment
(CWT)
C.
Utilities (CUT)
b.
Electric power
c.
d.
Cooling water
e.
Process water
f.
g.
Instrument air
h.
i.
Refrigeration
F.
Maintenance and
repairs
G.
Operating supplies
Cost of
personnel.
maintenance
chart
paper,
lubricants,
miscellaneous
laboratory charges
I.
Patents and
royalties
8.19
Fixed cost
A.
Depreciation
B.
Local taxes and
insurance
C.
Plant overhead
cost (sometimes referred
to as factory expenses)
process.
recreation
facilities,
payroll
overhead
and
General expenses
A.
Administration
costs
B.
Distribution and
selling costs
C.
Research and
development
costs.
product. Includes salaries and funds to researchrelated equipment and supplies, etc.
(Source : Turton)
These costs represent operating expenses that vary with production rate. When product
demand drops, production rate is reduced below the design capacity. At this lower rate,
we would expect a reduction in the factors making up the direct manufacturing costs.
These reductions may be directly proportional to the production rate, for example, raw
8.20
II)
III)
General expenses
These costs represent an overhead burden that is necessary to carry out business
functions. They include management, sales, financing, and research functions. General
expenses seldom vary with production level. However, items such as research and
development and distribution and selling cost may decrease if extended periods of low
production levels occur.
The cost of manufacturing, COM can be estimated when the following costs are known.
I)
II)
III)
IV)
V)
8.2.1
The technique used to estimate operating labor requirements is based on data obtained
from five chemical companies and correlated by Alkayat and Gerrard. According to this
method, the operating labor requirement for chemical processing plants is given by
= 6.29 + 31.7
+ 0.23
(8.11)
8.21
where
involving the handling of particulate solids, for example, transportation and distribution,
particulate size control, and particulate removal.
processing steps handling and includes compression, heating and cooling, mixing and
reaction. In general, value of
is given by
(8.12)
unit per shift. A single operator works on the average 49 weeks (3 weeks off for
vacation and sick leave) a year, five 8-hour shifts a week. This amounts leads to
49
5
.
245
.
1095
.
245
= 4.5
= 6.29 + 31.7
+ 0.23
= [6.29 + 0 + 0.23 7]
.
.
= 2.81
8.22
Number of Equipment
1)
Compressors
2)
Exchangers
3)
Heaters
4)
Reactors
5)
Vessels
TOTAL
From calculation above, the number of operators required per shift is 2.81. So,
Operating labor = 4.5 2.81 = 12.65 (rounding up to the nearest integer yields 13
operators)
To estimate the cost of operating labor, the hourly wage of an operator is required.
Chemical plant operators are relatively highly paid. The hourly rate for miscellaneous
plant and operators is RM20 (Department of Human Resource). Therefore
8
20 344
= 13
=
55,040
55,040
715,520
2001)
2010 = 715,520
=
8.2.2
525
397
946,216.62
The production of 1-Propanol is to reach 100,000 metric tonne per year. The costs of
raw material needed for this production rate are shown in Table 8.13 below. From Table
8.13, the total raw material cost is RM 19,596,816.43.
8.23
Amount (kg/hr)
Cost (RM/kg)
RM/hr(x1000)
Ethylene
6805
1.50
10,207.50
Hydrogen
3338
1.00
3338
30565
1.50
10,188.33
48157.2
455
21,911,526
Carbon monoxide
Catalyst
Total
19,596,816.43
(Source : www.titangroup.com,www.mox.cokayom.my)
8.2.3
Cost of Utilities
This term includes steam (high pressure, medium pressure, low pressure), cooling and
process water, electricity, boiler feed water and effluent treatment.
Amount
RM/year
Steam
1.00/kg
26.32 kg/h
217,197.92
Cooling water
0.05/kg
341.85kg/hr
141,115.68
0.087/kWh
53kWh
38,068.42
Utilities
Electricity
Total
394,382.02
The cost of waste treatment is calculated and concluded in Table 8.15 below.
Table 8.15: Waste treatment Cost
Item
Waste
Price (RM/unit)
Amount
RM/year
2.42/m3
0.14 m3/h
2,742.02
Total
2,742.02
(Source: Fogler)
8.24
8.2.5
The cost of manufacturing with and without depreciation can be obtained using the
formulae given by Turton, (2003)
= 0.280
+ 2.73
+ 1.23(
(8.13)
and
= 0.180
+ 2.73
+ 1.23(
(8.14)
where COM and COMd are cost of manufacturing with and without depreciation
respectively. Other symbols are the same as encountered before. Using the value of
fixed capital investment (FCI which is equivalent to CGR) estimated in section 8.2.2, the
production cost for 1-propanol can be calculated as follows
= 0.280
+ 2.73
+ 1.23(
= 0.280(51,197,300.91) + 2.73(946,216.62)
+ 1.23(394,382.02 + 2,742.02 + 19,596,816.43)
= 41,510,962.41
42
10
And
= 0.180
+ 2.73
+ 1.23(
37
The direct (variable) and fixed manufacturing costs can be evaluated as follows
)=
+ 1.33
+ 0.069
+ 0.03
8.25
26,030,351.21
And
) = 0.708
+ 0.168
= 0.708(946,216.62) + 0.168(51,197,300.91)
=
8.3
9,271,067.92
TOTAL REVENUE
The price for 1 kg n-propanol is RM4.40 (Matrade). So, the total revenue for production
of 95,836,944kg of n-propanol and carbon monoxide and propanal are RM
567,405,823.50 as shown in Table 8.16.
8.4
Income (RM/year)
422,911,948.80
410,162.69
144,083,712
567,405,823.50
PROFITABILITY ANALYSIS
According to Turton (2003), in the economic analysis of a project, it is assumed that any
new land purchases required are done at the start of the project, that is, at time zero.
After the decision has been made to build a new chemical plant, the construction phase
of the projects starts. Depending on the size and scope of the project, this construction
may take anywhere from six months to three years to complete.
8.26
In this plant, it is assumed that it takes a typical value of two years for time from project
initiation to the start-up of the plant. Over the two-year construction phase, there is a
major capital outlay. This represents the fixed capital investment for purchasing and
installing the equipment and auxiliary facilities required to run the plant. The distribution
of this fixed capital investment is usually larger towards the beginning of construction.
At the end of second year, construction has finished and the plant is started up. At this
point, the additional expenditure for working capital is required to float the first few
months of operations. This is a one-time expense at the start-up of the plant and will be
recovered at the end of the project.
After start-up, the process begins to generate finished products for sale, and yearly
cash flows become positive. The cash flows for early years of operation are larger than
those for later years due to the effect of depreciation. The time for depreciation used in
this plant is six years. The method of depreciation used is based on Modified
Accelerated Cost Recovery System (MACRS). Under this method, all equipment is
assigned a class life, which is the period over which the depreciable portion of the
investment may be discounted. Most equipment in a chemical plant has a class life of
9.5 years. The MACRS method uses a double declining balance method and switches
to a straight line method when straight line method yields a greater depreciation
allowance for the year. The Table 8.17 is the depreciation allowance using MACRS
method.
8.27
Table 8.17: Depreciation schedule for MACRS method for equipment with a 9.5 year
class life
Year
20.00
32.00
19.20
11.52
11.52
5.76
8.4.1
The non-discounted techniques do not take into account the time value of money and
are not recommended for evaluating new large projects. Figure 9.6 below shows the
graph of cumulative cash flow for non-discounted after tax cash flow based on
information in Table 9.19. The taxation rate, t used is 45% since the rate is often in the
range of 40% to 50% according to Turton, (2003).
8.4.2
8.28
8.4.3
For discounted criteria, we discount each of the yearly cash flows back to time zero.
The following tables show the discounted cash flow from 10% to 16% p.a. All the value
is in unit of $106
150
Cash (RM106)
100
50
Land
FCL
-50
-100
Land
+
WC
10
12
14
16
18
20
FCIL
Time (years)
Figure 8.4: Cumulative cash flow diagram for nondiscounted after-tax cash flow
8.29
Investment
FCIL- d
(R-COMd-dk)x(1-t) +dk
Cash flow
17
51
-17
-17
34
51
-34
-51
27.2
51
-9
-78.2
10.2
40.8
56
39
1.3
1.3
-76.9
16.32
24.48
56
39
12.58
12.58
-64.32
9.792
14.688
56
39
10.948
10.948
-53.372
5.8752
8.8128
56
39
9.9688
9.9688
-43.4032
5.8752
2.9376
56
39
12.9064
12.9064
-30.4968
2.9376
56
39
11.4376
11.4376
-19.0592
56
39
8.5
8.5
-10.5592
10
56
39
8.5
8.5
-2.0592
11
56
39
8.5
8.5
6.4408
12
56
39
8.5
8.5
14.9408
13
56
39
8.5
8.5
23.4408
8.30
14
15
16
17
18
19
56
39
8.5
8.5
31.9408
56
39
8.5
8.5
40.4408
56
39
8.5
8.5
48.9408
56
39
8.5
8.5
57.4408
66
39
8.5
8.5
65.9408
27.2
66
39
13.5
40.7
106.6408
8.31
Non-discounted
cash flow
Discounted cash
flow
Cumulative Discounted
cash flow
-17
-17
-17
-34
-31.7757
-48.7757
-27.2
-23.7575
-72.5332
1.3
1.061187
-71.472
12.58
9.597222
-61.8748
10.948
7.805773
-54.0691
9.9688
6.642632
-47.4264
12.9064
8.037457
-39.389
11.4376
6.656787
-32.7322
8.5
4.623437
-28.1087
10
8.5
4.320969
-23.7878
11
8.5
4.038289
-19.7495
12
8.5
3.774102
-15.9754
13
8.5
3.527198
-12.4482
14
8.5
3.296447
-9.15174
15
8.5
3.080791
-6.07094
16
8.5
2.879244
-3.1917
17
8.5
2.690882
-0.50082
18
8.5
2.514843
2.014026
19
40.7
11.25389
13.26791
Non-discounted
cash flow
Discounted cash
flow
Cumulative Discounted
cash flow
-17
-17
-17
-34
-31.4815
-48.4815
-27.2
-23.3196
-71.8011
1.3
1.031982
-70.7691
12.58
9.246676
-61.5224
10.948
7.451025
-54.0714
8.32
9.9688
6.282035
-47.7894
12.9064
7.53076
-40.2586
11.4376
6.179379
-34.0792
8.5
4.252116
-29.8271
10
8.5
3.937145
-25.89
11
8.5
3.645504
-22.2445
12
8.5
3.375467
-18.869
13
8.5
3.125432
-15.7436
14
8.5
2.893919
-12.8497
15
8.5
2.679554
-10.1701
16
8.5
2.481069
-7.68903
17
8.5
2.297286
-5.39175
18
8.5
2.127117
-3.26463
19
40.7
9.430681
6.16605
Non-discounted
cash flow
Discounted cash
flow
Cumulative Discounted
cash flow
-17
-17
-17
-34
-31.1927
-48.1927
-27.2
-22.8937
-71.0864
1.3
1.003839
-70.0825
12.58
8.911989
-61.1705
10.948
7.115449
-54.0551
9.9688
5.94407
-48.111
12.9064
7.060243
-41.0508
11.4376
5.740146
-35.3106
8.5
3.913636
-31.397
10
8.5
3.590492
-27.8065
11
8.5
3.294029
-24.5125
12
8.5
3.022045
-21.4904
13
8.5
2.772518
-18.7179
14
8.5
2.543595
-16.1743
8.33
15
8.5
2.333573
-13.8407
16
8.5
2.140893
-11.6998
17
8.5
1.964122
-9.73572
18
8.5
1.801947
-7.93377
19
40.7
7.91573
-0.01804
Table 8.22: Discounted cash flow for discount rate = 10% p.a
End of
year (k)
Non-discounted
cash flow
Discounted cash
flow
Cumulative Discounted
cash flow
-17
-17
-17
-17
-34
-30.9091
-47.9091
-34
-27.2
-22.4793
-70.3884
-27.2
1.3
0.976709
-69.4117
1.3
12.58
8.592309
-60.8194
12.58
10.948
6.797847
-54.0216
10.948
9.9688
5.627128
-48.3944
9.9688
12.9064
6.623024
-41.7714
12.9064
11.4376
5.335725
-36.4357
11.4376
8.5
3.60483
-32.8309
8.5
8.5
3.277118
-29.5537
8.5
8.5
2.979198
-26.5745
8.5
8.5
2.708362
-23.8662
8.5
8.5
2.462147
-21.404
8.5
8.5
2.238316
-19.1657
8.5
8.5
2.034832
-17.1309
8.5
8.5
1.849848
-15.281
8.5
8.5
1.68168
-13.5994
8.5
8.5
1.5288
-12.0706
8.5
40.7
6.654775
-5.41578
40.7
8.34
100
50
0
0
10
15
20
-50
-100
Time (years)
Figure 8.5: Cumulative cash flow diagram using different discount rates
i)
Payback Period
Payback period is defined as time required after start-up, to recover the fixed capital
investment, FCIL required for the project, with all cash flows discounted back to time
zero. The payback period shown in Figure 9.8 can be found as follows.
= 17 10 +
=
10.2 10
1.1546
24.65 10
=5+
24.65 10
(30.50 + 24.65)
(30.50 + 19.06)
= 5.51
This means that plant takes about 5.5 years after start-up to get back the fixed capital
investment. In other words, it takes about 7.5 years for the plant to "repay" the sum of
the original investment after the commencement of constructions.
8.35
ii)
The discounted cumulative cash position, more commonly known as the net present
value (NPV) or net present worth (NPW) of the project is defined as cumulative
discounted cash position at the end of the project. The net present value decision rule is
to accept positive net present value project and reject project with the negative NPV.
The net present worth for the project is RM6.17x106 as shown in Table 9.21. Therefore,
the project is accepted since the net present value is positive.
iii)
Again, the net present value of a project is greatly influenced by the level of fixed capital
investment and a better criterion for comparision of projects with different levels may be
the present value ratio (PVR)
=
A present value ratio of unity for a project represents a break even situation. Values
greater than unity indicate profitable processes while those less than unity represent
unprofitable projects. Therefore, for this project, the PVR can be evaluated as follows
1.03 + 9.25 + 7.45 + 6.28 + 7.53 + 6.18 + 4.25 + 3.93 + 3.65 + 3.38 + 3.13 + 2.89 + 2.68
10
+2.48 + 2.30 + 2.12 + 9.43
=
(17 + 31.48 + 23.32) 10
=
77.97 10
71.80 10
= 1.08>1
iv)
The discounted cash flow rate of return (DCFROR) is defined to be the interest rate at
which all the cash flows must be discounted in order for net present value or net
present worth of the project to be equal to zero. Therefore, the DCFROR represents the
highest, after-tax interest or discount rate at which the project can just break even. It is
worth noting that for evaluation of the discounted cash flow rate of return, no interest
8.36
rate is required since this is what is calculated. If the value of DCFROR is greater than
internal discount rate, then the project is considered to be profitable.
The net present values for several discount rates which have previously been
calculated (Table 8.18 to Table 8.22) are summarized in the following Table 8.23.
Table 8.23: NPV as a function of discount rates ( values in $million)
Interest or Discount Rate
7%
8%
21.82
9%
14.36
10%
7.84
12%
-2.93
The value of DCFROR can be calculated by interpolating from the table above.
(0 7.84x10 )
10%)
=
(12% 10%)
(2.93x10 7.84x10 )
= 11.46%
Clearly, the DCFROR is greater than internal discount rate (11.46% p.a). Therefore, the
project is considered to be profitable.
8.5
CONCLUSION
Table 8.26 summarizes the costs and profitability criteria for this plant. The fixed capital
investment for this plant is around RM51 million and the cost of manufacturing with and
without depreciation are RM41million and RM36 million respectively. The breakeven
point is achieved when the plant produces 6000 metric tonnes per year of 1-propanol
8.37
which is well below the planned production of 100000 metric tonnes per year. By
considering a discount rate of 10% per annum, the payback period is 5.5 years after
start-up or 7.5 years after the beginning of the constructions. The net present worth or
net present value is found to be RM50.86 million) and the present value ratio is 1.08.
The discounted cash flow rate of return for the plant is computed to be 11.46% which
gives the net present value of zero. Based on these criteria, it can be concluded that the
proposed 1-propanol plant is profitable.
Table 8.24: Summary of economic analysis
Items
Data/Value
RM51*
RM41*
RM36*
Depreciation method
MACRS
Variable cost, VC
RM26*
Fixed cost, FC
RM9.27*
17 years
Payback period
Net present value at 8% discount rate (NPV)
Present value ratio (PVR)
8.99%
Salvage value
RM1*
.Note*: in million
8.38
8.6
REFERENCES
1)
Turton et al, 2003, Analysis, Synthesis, and Design of Chemical Processes,
Prentice Hall International Series.
2)
Peters. Max S. and Timmerhaus, Klaus D. (1991). Plant Design and Economics
for Chemical Engineers. 4th Edition. Singapore: McGraw-Hill Book Company.
3)
Ulrich, G. D. (1984). A Guide to Chemical Engineering Process Design and
Economics. Toronto : John Wiley & Sons.
4)
Perry, R.H. and Green, D.W. (1997). Perrys Chemical Engineering Handbook.
7th ed. USA: McGraw-Hill, Inc
5)
Sinnott, R.K. (1983). Chemical Engineering Volume 6. 1st ed. Great Britain:
Pergamon Press.
6)
Mark, H.F., Othmer, D.F., Overberger, C.G. and Searborg, G.T. (1963). KirkOthmer: Encyclopedia of Chemical Technology Volume 1. 3rd ed. USA: Interscience
Publisher. 414-424.
8.39