Professional Documents
Culture Documents
School of Engineering
Department of Chemical Engineering
Summary
The objective of this assignment is to estimate the fixed capital cost by using the equations and
tables of appendix A in Turton and by using the CAPCOST program.
1.1Introduction
The planning, engineering and construction of a chemical process plant finds its justification in economic
life. One of the essential phases in the evaluation of the economic soundness of a plant is Cost
Estimation. The scope of cost estimating activities is to calculate the fixed capital costs, which is “the
sum of all direct and indirect costs, plus additional amounts for contingency and auxiliary costs, incurred
in planning and building a plant ready for start up”.
Chemical plants are built to make a profit, and an estimate of the investment required, and the cost of
production is needed before the profitability of a project can be measured.
1.2Theory
The following steps were followed to estimate the bare module cost for equipment’s:
1-Estimate base cost Cp0 using equation (1) for the desired piece of equipment by referring to
the figures in Appendix A(figures A.1-A.17) or the data in Table A.1. from Turton book.
…(1)
2- For exchangers ,pumps, and vessels, find the pressure factor Fp by referring to table A.2 and
using equation (2) or equation (3). And for the material of construction factor FM, use Table A.3
and figure A.18. from Turton book.
…(2)
…(3)
3-Use equation (4) to estimate the bare module factor, FBM, or find FBM by using table A.6 and
figure A.19 from Turton book.
F BM =B 1+ B 2∗Fm∗Fp …(4)
4-Calculate the bare module cost of equipment CBM from equation (5)
C BM =C P∗F BM …(5)
Using the CAPCOST program to generate the same data of Table E.7.14 (b), Capcost
values of the equipment summarized in table (2).
Cp CBM Cp CBM
E-101 32,800 108,000 32,977 108,494
E-102 36,600 177,000 36,874 171,336
E-103 3700 12,200 3730 12,271
T-101 54,721 290,640 54,742 290,701
32 trays 71,808 126,200 32(2241) 131,232
V101 13,400 47,300 13,500 51,165
1.4conclusion
In conclusions it was noticed that using Capcost or manually calculating the costs both give
the same answers with small difference.
1.5References
1. Prof .Menwer Attarakih’s handouts
APPENDIX:
Using the equations and tables of Appendix A in Turton book.
For the heat exchanger (E-101):
Constants K1, K2 and K3 for floating head shell and tube heat exchangers from table A.1:
Table 4 Constants K1, K2 and K3 for floating head shell and tube heat exchangers from table A.1
Value
K1 4.8306
K2 -0.8509
K3 0.3187
A m2 170
Value
B1 1.63
B2 1.66
Fm 1
Fp 1
F BM =B 1+ B 2∗Fm∗Fp
F BM =1.63+1.66∗1∗1=3.29
C BM =C P∗F BM =32977∗3.29=108494.33
C BM =C P∗F BM =¿ ¿32977*3.29=108494.33
Value
K1 4.8306
K2 -0.8509
K3 0.3187
A m2 205
2
log (Cp)=4.8306−0.8509∗log ( 205 ) +0.3187∗[ log ( 205 ) ]
Cp=36874.5
Value
C1 0.03881
C2 -0.11272
C3 0.0818
Table 8 Values from table A.4, A.3 and graph A.18
Value
B1 1.63
B2 1.66
Fm 1.8
Fp 1.00862
F BM =B 1+ B 2∗Fm∗Fp
F BM =1.63+1.66∗1.8∗1.00862=4.64376
C BM =C P∗F BM =36874.5∗4.64376=171236.2013
C BM =C P∗F BM =36874.5*3.29=121317
Value
K1 3.3444
K2 0.2745
K3 -0.0472
A 10
m
2
Table10 Values from table A.4, A.3 and graph A.18 in Appendix A
Value
B1 1.74
B2 1.55
Fm 1
Fp 1
F BM =B 1+ B 2∗Fm∗Fp
F BM =1.74+ 1.55∗1∗1=3.29
C BM =C P∗F BM =3730∗3.29=12271 .7
C BM =C P∗F BM =3730*3.29=12271.7
For (T-101):
Table 11 Constants K1, K2 and K3 for towers from table A.1
Value
K1 3.4974
K2 0.4485
K3 0.1074
D 2.1
L 23
P 5
π D2
V= (L)= 79.66m3
4
Cp=54742.
Table.12 Values from table A.4, A.3 and graph A.18 in Appendix A
Value
B1 2.25
B2 1.82
Fm 1
Fp 1.6815
Fp=1
F BM =B 1+ B 2∗Fm∗Fp
F BM =2.25+1.82∗1∗1.6815=5.31
C BM =C P∗F BM =54742.7∗5.31=290701.8
C BM =C P∗F BM =54742.7*4.04=222802.8
For 32 trays:
Using the equation in appendix A:
Table.13 Constants K1, K2 and K3 for trays from table A.1
Value
K1 2.9948
K2 0.4465
K3 0.3961
D 2.1
Trays 32
π D2
Area ¿ =3.46m2
4
Cp=2241 for 32tray
Using table A.6 & fig.A.9 to find Fm for sieve tray MOC SS
Fm≈ 1.83
Table.14 Values from table A.4, A.3 and graph A.18 in Appendix A
Value
Fm 1.83
Fp 1
F BM =1.83
C BM =C P∗N∗F BM =2241∗32∗1.83=131232.
C BM =C P∗N∗F BM =2241*32*1=71712
For (V-101):
Value
K1 3.5565
K2 0.3776
K3 0.0905
D 1.8
L 6
π D2
V= ∗( L)= 15.26m3
4
Cp=13500
Table 16 Values from table A.4, A.3 and graph A.18 in Appendix A
Value
B1 1.49
B2 1.52
Fm 1
Fp 1.6815
Fp for tower:
F BM =B 1+ B 2∗Fm∗Fp
F BM =1.49+1.52∗1∗1.5126=3.789
C BM =C P∗F BM =13500∗3.789=51165
C BM =C P∗F BM =13500*3.01=40635