Dailyreportfrom Site: Date 18.01.2013
Dailyreportfrom Site: Date 18.01.2013
S.No:28
1.
Date 18.01.2013
Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)
Nil.
2.
3.
Nil.
4.
Nil.
5.
MR.M.E.MANIKANDAN(2141)
5.1
Staff (VEESONS)
5.2
6.
Utkal Engineers:
Boiler: Supervisor:01 IB
00; Riger-02;grinder-0 Helper-05(Total=11)
7.
8.
Site status:
VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM
1) Bunker casing stiffener flat fit up work Completed. Stiffener
flat not available at site, it is cut & suit from platform Toe
plates.
2) Dea. Outlet to feed pump suction piping erection work u/p.
ESP;
1. HT Duct Erection work Completed.( Transformer and HT
duct matching flange holes are variation.)
2. D.E.R.M Drive erection work U/P.
Prepared by (Name):
M.E.MANIKANDAN
M.E.MANIKANDAN
Signature:
Signature:
Staff No : 2141