DAILYREPORTFROM SITE

S.No:28

1.

Date 18.01.2013

Site: M/s Baldev alloys pvt. LTD.


Vwta020,VWHA052,053,054

Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)

Nil.

2.

Details of communications sent to HO


on

Daily report, Guest house painting detail, Insu

3.

Details of consignments / materials


received from HO / others

Nil.

4.

Details of payments received from HO /


others

Nil.

5.

Attendance with details


:

MR.M.E.MANIKANDAN(2141)

5.1

Staff (VEESONS)

Mr. DINESH KUMAR.S (1832)

5.2

6.

Contract Workers (Contractor wise)

Important brief feedback about Fabrication


/ Erection / Commissioning (delay with
reference to schedule, major problems
etc.,)

Utkal Engineers:
Boiler: Supervisor:01 IB
00; Riger-02;grinder-0 Helper-05(Total=11)

1.contractor man power shortage

2. Radiography film required from con


3.customer side insert plates

4. Milwright fitter req for rotary equipm

5. Insulation work man power required


matters work completion purpose.

7.

Materials, documents, payments urgently


required from HO with details

1. Utkal engg Contractor payment.

8.

Any urgent / important site complaints

UTKAL Engineering Should be


increasing his manpower.
Refractory contractor required
for 3XWHRB boiler ABC Ducts.

Site status:

VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM
1) Bunker casing stiffener flat fit up work Completed. Stiffener
flat not available at site, it is cut & suit from platform Toe
plates.
2) Dea. Outlet to feed pump suction piping erection work u/p.

ESP;
1. HT Duct Erection work Completed.( Transformer and HT
duct matching flange holes are variation.)
2. D.E.R.M Drive erection work U/P.

Prepared by (Name):

M.E.MANIKANDAN

Checked & Approved by (Name) :

M.E.MANIKANDAN

Signature:

Signature:

Staff No : 2141

Staff No. :2141