Dailyreportfrom Site: Date 28.02.2013
Dailyreportfrom Site: Date 28.02.2013
S.No:48
1.
Date 28.02.2013
Details of
communications
received on (E-mail,
Fax, Courier, Post, by
hand etc.,)
Nil.
2.
Daily report.
3.
Nil.
4.
Nil.
5.
MR.M.E.MANIKANDAN(2141)
5.1
Staff (VEESONS)
5.2
6.
Utkal Engineers:
Boiler: Supervisor:01 IB
04; Riger-03;grinder-0 Helper-06(Total=18)
7.
8.
Site status:
VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM
1) Roof truss boxes erection work completed.
2) Transporting supports channel cut to make purlin for roof
truss.
3) Air heater to Sproger header duct welding work u/p.
4) Non IBR drain piping fit up work u/p.
ESP;
1) ESP sealing roof erection & fit up work completed.
2) Roof beam man hole door erection work completed.
3) Pressure blower & air heater piping support work
complete.
Prepared by (Name):
M.E.MANIKANDAN
M.E.MANIKANDAN
Signature:
Signature:
Staff No : 2141