You are on page 1of 13

RMC Project Management, Inc.

Extra Exercises on Network Diagrams

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

Exercise 1
[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering
the questions, do a forward/backward pass.

Activity Predecessor Estimate
in weeks
Start
0
C
B
P
A
U
T
R
N
End

Start
Start
Start
C, B, P
P
A
A
U
T, R, N

6
4
3
7
4
2
3
6
0

1. How many paths are in the network, and what are they?

2. What is the critical path and its duration?

3. What is the float on activity U?

4. What is the impact to the project if activity B takes three weeks longer than planned?

Do a forward and backward pass using the original estimates.

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

Answer to Exercise 1
[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering
the questions, do a forward/backward pass.

Activity

Predecessor

Start

Estimate
in weeks
0

C
B
P
A
U
T
R
N
End

Start
Start
Start
C, B, P
P
A
A
U
T, R, N

6
4
3
7
4
2
3
6
0

Start

1. How many paths are in the network, and what are they?

There are seven paths. See the details on the next page.

2. What is the critical path and its duration?


Start, C, A, R, End

16 WEEKS

3. What is the float on activity U?


3 weeks

4. What is the impact to the project if activity B takes three weeks longer than planned?

Critical path shifts to Start, B, A, R, End.


It will delay the project end by one week.

Do a forward and backward pass using the original estimates.

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

End

Answer to Exercise 1
Note: Answers are based on using the zero method. See www.rmcproject.com/free/tips.htm for an explanation of the two
methods.

0
0

Start
0
2

0
3

6
6

6
6

13
13

13
14

4
6

13
13

3
6

3
6

15
16

End
16
16

N
7
10

7
10

13
16

Legend
D
ID
ES
EF
S
LS
LF

Start, C, A, T, End
Start, C, A, R, End
Start, B, A, T, End
Start, B, A, R, End
Start, P, A, T, End
Start, P, A, R, End
Start, P, U, N, End

15
16
13
14
12
13
13

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

Exercise 2
[AOA] Using the table below, draw the network diagram and answer the questions. When you have completed answering
the questions, do a forward/backward pass.

Activity
StartA
StartB
AC
AD
BC
BF
CE
CF
DEnd
EEnd
FEnd

Estimate in
weeks
2
3
5
4
6
2
3
Dummy
1
3
4

1. How many paths are in the network, and what are they?

2. What is the critical path and its duration?

3. What is the float on activity AC?

4. What is the impact to the project if activity F-End takes two weeks longer than planned?

Do a forward and backward pass using the original estimates.

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

Answer to Exercise 2
[AOA] Using the table below, draw the network diagram and answer the questions. When you have completed answering
the questions, do a forward/backward pass.

Activity
StartA
StartB
AC
AD
BC
BF
CE
CF
DEnd
EEnd
FEnd

Estimate in
weeks
2
3
5
4
6
2
3
Dummy
1
3
4

Start

Start

1. How many paths are in the network, and what are they?

There are six paths. See the details on the next page.

2. What is the critical path and its duration?


StartB, BC, CE, EEnd and it will take 15 weeks.

3. What is the float on activity A-C?


Two weeks

4. What is the impact to the project if activity FEnd takes two weeks longer than planned?

There are two critical paths. An additional one is StartB, BC, CF, FEnd.

Do a forward and backward pass using the original estimates.

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

Answer to Exercise 2

A
2

2
0

10

14

3
3
3

6
3

12
0 12

9
9

12
12

3
9

14

8
C

Start
0

2
6

5
11

9
11

7
15
15
15
13
15

Legend

ES
LS

D
S

EF
LF

StartA, AD, DEnd


StartA, AC, CE, EEnd
StartA, AC, CF, FEnd
StartB, BC, CE, EEnd
StartB, BC, CF, FEnd
StartB, BF, FEnd

7
13
11
15
13
9

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

End

Exercise 3
[AOA] Using the table below, draw the network diagram and answer the questions. When you have completed answering
the questions, do a forward/backward pass.

Activity

Successor

Start
A
B
C
D
E
F
G
H
I
J
K
End

A, B, C
D
E
F, G
H
I
I
J
K
K
End
End
-

Estimate in
weeks
0
2
4
5
3
4
Dummy
2
I
2
4
6
0

1. How many paths are in the network, and what are they?

2. What is the critical path and its duration?

3. What is the float on Activity F? Activity H?

4. What is the impact to the project if activity B takes three weeks longer than planned?

Do a forward and backward pass using the original estimates.

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

Answer to Exercise 3
[AOA] Using the table below, draw the network diagram and answer the questions. When you have completed answering
the questions, do a forward/backward pass.

Activity Successor Estimate in


weeks
Start
A, B, C
0
A
D
2
B
E
4
C
F, G
5
D
H
3
E
I
4
F
I
Dummy
G
J
2
H
K
I
I
K
2
J
End
4
K
End
6
End
0

Start

1. How many paths are in the network, and what are they?

There are four paths. See the details on the next page.

2. What is the critical path and its duration?


Start, B, E, I, K, End and it will take 16 weeks.

3. What is the float on Activity F? Activity H?


Because activity F is a dummy task there is no float. Activity H has float of 4 weeks.

4. What is the impact to the project if activity B takes three weeks longer than planned?

It will delay the project by 3 weeks because B is on the critical path.

Do a forward and backward pass using the original estimates.

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

End

Answer to Exercise 3

D,3
A,2
0
14

Start
0
3

2
6

2
6

H,1

5
9

5
9

I,2

6
10
10
10

B,4

0
0

E,4
4
4

4
4

C,5

J,4

K,6
16
16

8
8

8
8

10
10

End
11
16

5
5
8

G,2
5
10

7
12

7
12

Legend

ID,D
ES
LS

Start, A, D, H, K, End
Start, B, E, I, K, End
Start, C, F, I, K, End
Start, C, G, J, End

EF
LF

12
16
13
11

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

Exercise 4
[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering
the questions, do a forward/backward pass.

Activity Predecessor Estimate


in weeks
A
5
B
A
7
C
A
3
D
B
1
E
B, C
3
F
D, E
2
1. How many paths are in the network, and what are they?

2. What is the critical path and its duration?

3. What is the float on activity E?

4. What is the impact to the project if activity C takes three weeks longer than planned?

Do a forward and backward pass using the original estimates.

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

10

Answer to Exercise 4
[AON] Using the table below, draw the network diagram and answer the questions. When you have completed answering
the questions, do a forward/backward pass.

Activity Predecessor Estimate


in weeks
A
5
B
A
7
C
A
3
D
B
1
E
B, C
3
F
D, E
2


1. How many paths are in the network, and what are they?

There are three paths. See the details on the next page.

2. What is the critical path and its duration?


A, B, E, F and it will take 17 weeks

3. What is the float on activity E?


Zero, it is on the critical path.

4. What is the impact to the project if activity C takes three weeks longer than planned?

There will be no impact to the critical path or its duration.

Do a forward and backward pass using the original estimates.

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

11

Answer to Exercise 4

12

12

B
5

13

D
12

14

15

15

A
0

15

12

C
9

15

E
12

12

0 15

Legend

EF

ID
LS S LF

A, B, D, F
A, B, E, F
A, C, E, F

15
17
13

Copyright 2007 RMC Project Management, Inc. All rights reserved.


500 East Travelers Trail, Suite 100 Minneapolis, Minnesota 55337
info@rmcproject.com www.rmcproject.com (952) 846-4484
The copyright owner hereby grants permission to make copies of this handout for personal, noncommercial use only.

12

17

ES

17

You might also like