Calculating Float

Activity

Precedenc Duration
e

Start

Start

Start

D, A

F, E

End

C, B

www.qvive.biz

BEST VIEWED IN SLIDE SHOW MODE

1. What is the duration of the critical pa


A) 32
B) 33
C) 31
D) 35
2. What is the float of activity B?
A) 0
B) 16
C) 10
D) 15
3. What is the float of Activity F?
A) 0
B) 5
C) 13
D) 7

Calculating Float

Start

ES

EF

X
LS F LF

www.qvive.biz

BEST VIEWED IN SLIDE SHOW MODE

End

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)

Q
1
2
3

Calculating Float

Start

ES

EF

X
LS F LF

www.qvive.biz

End

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)

Q
1
2
3

Calculating Float

Start

ES

EF

X
LS F LF

www.qvive.biz

End

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)

Q
1
2
3

Calculating Float
0+6=6
0 6 6

Start

13

13

18

12

13

End

18

18

25

25

33

The latest Late Finish of the preceding activities determines Early Start
ES

EF

X
F

www.qvive.biz

LF

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)

Q
1
2
3

Calculating Float
0

Start

13

13

18

12

13

End

18

18

25

25

33

The latest Early Finish of the preceding activities determines Critical Path
ES

EF

X
LS F LF

www.qvive.biz

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)

2
3

Calculating Float
0

Start

13

13

18

12

13

End

18

18

25

25

33

Activities on the Critical Path have Zero Float


ES

EF

X
LS F LF

www.qvive.biz

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)

2
3

Calculating Float
0

Start

13

13

18

13

12

13

End

18

18

G
13

25

H
18

18

25

33

C
25

25

33

Activities on the Critical Path have LS=ES and LF=EF


ES

EF

X
LS F LF

www.qvive.biz

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)

2
3

Calculating Float
0

Start

13

13

18

End

13

28 15 33

12

13

D
1

E
5

18

33 5 = 28
28 13 = 15
18

G
13

13

25

H
18

18

25

33

C
25

25

33

The earliest Late Start of the following activities determines Late Finish
ES

EF

X
LS F LF

www.qvive.biz

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)

Calculating Float
0

Start

13

13

18

End

13

28 15 33

12

13

D
1

E
5

18

18

G
13

13

25

H
18

18

25

33

C
25

25

33

What else can we learn from this example?


ES

EF

X
LS F LF

www.qvive.biz

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)

Calculating Float
0

Start

13

13

18

End

13

28 15 33

12

13

D
1

E
5

18

18

G
13

13

25

H
18

18

25

33

C
25

25

33

Project has increased RISK because of a Near-Critical Path


ES

EF

X
LS F LF

www.qvive.biz

1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)