Calculating Float
Activity
Precedenc Duration
e
Start
Start
Start
D, A
F, E
End
C, B
www.qvive.biz
BEST VIEWED IN SLIDE SHOW MODE
1. What is the duration of the critical pa
A) 32
B) 33
C) 31
D) 35
2. What is the float of activity B?
A) 0
B) 16
C) 10
D) 15
3. What is the float of Activity F?
A) 0
B) 5
C) 13
D) 7
Calculating Float
Start
ES
EF
X
LS F LF
www.qvive.biz
BEST VIEWED IN SLIDE SHOW MODE
End
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
Q
1
2
3
Calculating Float
Start
ES
EF
X
LS F LF
www.qvive.biz
End
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
Q
1
2
3
Calculating Float
Start
ES
EF
X
LS F LF
www.qvive.biz
End
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
Q
1
2
3
Calculating Float
0+6=6
0 6 6
Start
13
13
18
12
13
End
18
18
25
25
33
The latest Late Finish of the preceding activities determines Early Start
ES
EF
X
F
www.qvive.biz
LF
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
Q
1
2
3
Calculating Float
0
Start
13
13
18
12
13
End
18
18
25
25
33
The latest Early Finish of the preceding activities determines Critical Path
ES
EF
X
LS F LF
www.qvive.biz
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
2
3
Calculating Float
0
Start
13
13
18
12
13
End
18
18
25
25
33
Activities on the Critical Path have Zero Float
ES
EF
X
LS F LF
www.qvive.biz
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
2
3
Calculating Float
0
Start
13
13
18
13
12
13
End
18
18
G
13
25
H
18
18
25
33
C
25
25
33
Activities on the Critical Path have LS=ES and LF=EF
ES
EF
X
LS F LF
www.qvive.biz
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
2
3
Calculating Float
0
Start
13
13
18
End
13
28 15 33
12
13
D
1
E
5
18
33 5 = 28
28 13 = 15
18
G
13
13
25
H
18
18
25
33
C
25
25
33
The earliest Late Start of the following activities determines Late Finish
ES
EF
X
LS F LF
www.qvive.biz
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
Calculating Float
0
Start
13
13
18
End
13
28 15 33
12
13
D
1
E
5
18
18
G
13
13
25
H
18
18
25
33
C
25
25
33
What else can we learn from this example?
ES
EF
X
LS F LF
www.qvive.biz
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)
Calculating Float
0
Start
13
13
18
End
13
28 15 33
12
13
D
1
E
5
18
18
G
13
13
25
H
18
18
25
33
C
25
25
33
Project has increased RISK because of a Near-Critical Path
ES
EF
X
LS F LF
www.qvive.biz
1. Precedence Diagram
2. Durations
3. Forward Pass (ES EF)
4. Critical Path
5. Float of Critical Path Activities
6. Backward Pass (LF LS)