Professional Documents
Culture Documents
CB510
Lecture 3 – Project Scheduling
Network Calculations
• The purpose of conducting network calculations
is to know more about the scheduling of
activities:
▫ When will each activity start?
▫ When will each activity finish?
▫ When will the project finish?
▫ Can I delay an activity without delaying the
project?
1
11/3/16
Scheduling Process
Forward pass Total
0 Duration
Early times
Start End
Scheduling Process
Start End
Late times
0 Total
Backward pass
Duration
During this pass late times are calculated. This includes:
• Late Start (LS): The latest time an activity can start without delaying the project
• Late Finish (LF): The latest time an activity can finish without delaying the project
2
11/3/16
ES Description EF
LS Duration LF
3 0
5 A 15
8 10 18
The Early Start of an activity = Maximum Early Finish of all preceding activities
0 C 3
H cannot start until both C and B
3 have finished, since B will finish
6 H 8
2 after C (on day 6) then the earliest
0 B 6 possible start for activity H is day 6
6
3
11/3/16
0 B 6
6
Note
• All times are denoted as end of day
End of day 3
End of day 6
0 C 3
End of day 0
3
6 H 8
2
0 B 6
6
4
11/3/16
B E G
5 5 9
A C F H L
START 2 4 11 5 3
END
D I K
8 8 6
J
5
The Late Finish of an activity = Minimum Late Start of all succeeding activities
7 C 9
The latest time that B can finish without
8 2 10 delaying the project depends on its
1 B 4
3 4 succeeding activities. The latest possible
4 E 7 start for C is 8 and for E is 4, hence B
4 3 7 should not finish later than day 4 if the
project is not to be delayed.
5
11/3/16
7 C 9
8 2 10
1 B 4
1 3 4
4 E 7
4 3 7
Activity Float
• Represents the amount of flexibility available in
executing an activity.
• Types of float:
▫ Total Float (TF)
▫ Free Float (FF)
6
11/3/16
OR
4 E 7 TF = 0
▫ TF = LF act. – EF act. 4 3 7
• It is calculated as:
– EF of this activity
7
11/3/16
17 G 22
10 B 13 20 5 25
15 3 18
14 H 20
For activity B: 18 6 24
FF = Min (14,17) – 13 = 1
Importance of float
• If Total Float = 0 à Critical Activity
• If Total Float > 0 à Non-critical Activity
• In all cases TF ≥ FF
8
11/3/16
0 0 0 0 0 0 6 0 6 6
0 A 2 2 C 6 6 F 17 17 H 22 22 L 25
0 2 2 2 4 6 6 11 17 23 5 28 28 3 31
End
7 0 0 0 0 0
2 D 10 17 I 25 25 K 31
9 8 17 17 8 25 25 6 31
10 10
10 J 15
20 5 25
9
11/3/16
10