Professional Documents
Culture Documents
07/29/2008 03:10 PM
Rich Campbell/R9/USEPA/US
To:
Aaron Setran/R9/USEPA/US@EPA,
Cc:
Archive:
1 attachment
Image.1217369396819.jpg
B5
Rich
-----Aaron Setran/R9/USEPA/US wrote: ----To: Rich Campbell/R9/USEPA/US@EPA
From: Aaron Setran/R9/USEPA/US
Date: 07/24/2008 02:04PM
cc: David Albright/R9/USEPA/US@EPA
Subject: Fw: Pineview Questions
Hey Rich:
B5
Aaron Carr Setran
U.S. EPA, Water Division
75 Hawthorne St.
San Francisco, CA 94105
(415) 972-3457
----- Forwarded by Aaron Setran/R9/USEPA/US on 07/24/2008 02:01 PM ----"Brenda Stein"
<brenda@exdengineering.c
om>
07/23/2008 11:14 AM
ToAaron Setran/R9/USEPA/US@EPA
cc"Justin Clouser"
<jclouser@clouserlaw.com>
SubjectPineview Questions
Aaron,
I am meeting with Leon May and we have a couple questions for you.
1- Can we put the monitoring wells on a quarterly sampling schedule even before the
new permit is in place? If so, is there a process we should go through?
2- Can I help expedite the new permit? PTP is at the last steps of turning the project
over to the homeowners association and they would like the new permit to be in place
prior to the transition.
3- Is there any special paperwork required by EPA for the ownership transition to the
HOA? Can you send the paperwork, if there is any? Leon is going to ask Justin Clouser
to prepare any paperwork for the transition, so you will be able to work with him also.
4- Are there any other issues you can think of for the transition or the new permit?
I hope all is well with you. I look forward to hearing from you.
Thank you,