You are on page 1of 2

INFRASTRUCTURE.

CHECK LIST
To : M/S
STRUCTURAL
CONSULTANT

From

PROJECT :-

PT Slab Floor :
Date:
/
/ 2015
Please check and allow P.T Beam , Slab , Chajja , etc..

Sr.No.
1

Item
CHECK
Are the sheating pipes water tight to prevent entrance of
cement grout during concreting .

Are the prestressing Strands free of grease and corrosion.

Is the Installation of tendon in accordance with the shop


drawings?
Is vertical & horizontal Tendon profile within the tolerance
limit?
Are the Anchorage are fixed to the end of the formwork by
support bar.
Are the Tendon Support bars & bar- chairs placed at
Sufficient Intervals and secured with binding wire to avoid
movement
Are the duct joints sealed with tapes?
Are the grout hose pipes protected from embedded in
concrete ?
Are sufficient no of grout hose pipes inserted?

4
5
6
7
8
9

Signatur
e

Project Engineer:
)

Yes

No