Professional Documents
Culture Documents
Torm Mathilde Electrical Report: Power Management System
Torm Mathilde Electrical Report: Power Management System
Channel
1
2
3
4
5
6
7
8
Location
Bridge
Ship control center
Pump room Entrance/Bottom
Emergency generator
ECR/Main engine side
Cargo manifolds Port side/Stb side
Cargo pump prime mover side
Steering gear room
Ecdis installation
The signal cables for the ecdis are in good order, and the network cables are either cat
5e UTP or FTP, so thats also in good order.
There is a Wireless router on the ecdis network, but you cannot access the internet via
this router since the router is connected to the MDS computer. I still do recommend it
to be switch to a switch without a wireless connection in order to protect the network
completely.
All the ecdis are connected to the emergency supply, and the monitoring ecdis has a
UPS backup.
Fuses have been placed on the supply for the GPS nmea buffer, to protect against
overloads. There are no nmea buffers for the Gyro or the speedlog.
The cables for the Ecdis have been labeled, for easy identification.
Survey
The cable has been penetrated through the hull, by a penetration block that is too big,
also the block next to it is missing half.
These blocks need to be replaced, and the cable needs to be moved to another block,
that will fit the cable.
Maybe if my suspicions are right this cable can be removed all together.
The cable penetration is located in the BCC, to doors to the right of the monitoring
ecdis.
Two cables have not been passed through cable penetration correctly, the cables need
to be moved to fitting blocks, and the damaged blocks need to be replaced.
I believe the cable to the left in the picture, is the same cable as mentioned in the
pictures above. This cable is not connected and I believe it can be removed all
together.
The penetration is located in the 2nd cupboard to the right when entering the bridge,
facing the BCC.
A cable has not been passed correctly through a cable penetration, this issue needs to
be rectified.
The penetration is full, so a new penetration needs to be made, and the cable needs to
be pulled back in order to pass it through the new penetration.
The penetration is located to the far left of the BCC.
This is another example of a cable not passed correctly through a penetration, the
block needs to be replaced and fitted to the cable.
The penetration is placed in the cupboard to the far left facing the BCC.
The penetration in these photos have not been closed, this issue needs to be
addressed. The penetration is located in the cable trunk on C deck.
Electrician has rectified this issue.
The terminal for this capacitor is in a bad condition, I recommend changing the
capacitor.
The junction box for this installation is located in the cable trunk on C Deck.
Electrician has rectified this issue.
The terminal for this capacitor is in a bad condition, I recommend changing the
capacitor.
The junction box for this installation is located in the cable trunk on C Deck.
Electrician has rectified this issue.
The terminal for this capacitor is in a bad condition, I recommend changing the
capacitor.
The junction box for this installation is located in the cable trunk on upp. Deck.
The terminal for this capacitor is in a bad condition, I recommend changing the
capacitor.
The junction box for this installation is located in the cable trunk on upp. Deck.
The terminal for this capacitor is in a bad condition, I recommend changing the
capacitor.
The junction box for this installation is located in the cable trunk on up. Deck.
To wires have been connected using tape in the no. 1 main air compressor circuit
board, this is not acceptable. The issue has to be rectified either by using a press
connector, or a proper terminal.
The penetration in Boiler 2 power panel needs to be re closed, in order to protect the
cables from moving in the penetration and being damaged.
The terminal for this capacitor is in a bad condition, I recommend changing the
capacitor. Also the wire has been burned over and needs to be repaired.
The junction box for this installation is located in the forward.
The terminal blocks in this junction box has been damaged and replaced by poor
substitute. New terminal block needs to be fitted to rectify the issue.
The junction box for this installation is located in the forward.
10
Installation For the washing machine on C deck need to be fitted with a correct outlet,
and then precautions taken so the cable doesnt get damaged.
T
he power cable for the switch en the computer room needs to be fixed to the wall.
11
Penetrations in the cable trunks in the accomedation needs to be correctly sealed from
the bottom.
12
Roxtech penetration needs new blocks, and be correctly closed. Location is in the
cable trunk on upp. deck.
Spares needed
Roxtech Blocks:
20x20 1 pcs
30x30 4 pcs
35x35 3 pcs
13
Date
Technician signature