You are on page 1of 76

Oct - Dec 2010 Volume-33 Issue-4

In this issue

Focus

Oct - Dec 2010 Volume - 33 Issue - 4

L&Ts capabilities from the very beginning of its


inception are aligned to serve the national interest
and countrys development. This has earned the
Company the axiom Builders to the Nation
and in-tune with this adage, L&T is continuing its
quest of contributing its best to the industrial and
infrastructural development of the country.
L&T has made a significant contribution to the
development of Indias transportation sector,
be it the hi-tech highways, bridges, tunnels,
viaducts, ports, airports and railways. In
all these projects, L&T has taken the lead
by introducing pioneering construction
techniques, resulting in execution of projects
with innovation, high quality and speed.
L&T has been associated with Delhi Metro
Rail Corporation (DMRC) for more than a
decade and has executed some of the most
critical projects under Phase I and Phase II
of Delhi Metro covering both elevated and
underground metro rail corridors including
station buildings. The good work carried
out by DMRC in Delhi is now extended to
other metros and L&T is actively involved in
Bangalore, Chennai and Hyderabad cities.
In this issue of ECC Concord, we bring to you
our success story in building Phase - II projects
under Delhi Metro where L&T was involved in
five packages. Apart from this, the issue also
delineates the expansion project at Marutis
Manesar facility, Cairn Indias Barmer project
and Hindustan Zinc project at Rajpura Dariba
mine. The kaleidoscope section, as usual,
presents a colorful array of important events
that occurred during the third quarter of the
current fiscal.
Hope, you will find these articles interesting along
with many other kaleidoscope items.
Happy reading.

Delhi Metro Rail Corporation


Delhis traffic and pollution solution

34

Cairn India
Burning the midnight oil at Barmer

42

Hindustan Zinc Ltd


Rajpura Dariba - The Zinc Thing

Kaliedoscope
Inauguration ..................................

46

New Orders . ..................................

49

Events ............................................

51

Corporate Sustainability ...............

59

Awards . .........................................

66

Editor

: V. S. Ramana

Editorial team

: K. Sridharan | Alex Benjamin

V. Ramesh Kumar | Gopi Kannan. S

V. Eswar | Ashwin Chand | Mayura. K

Subha Anand

Photography

- Editor

30

Maruti
Buildings for gearing up production

: V. S. Natanavelu

Design & layout : Global Print Design, Chennai

Metro - Delhis traffic and pollution solution


The exploding population of
Delhi and the resultant traffic
snarls on road comes as no big
surprise. But what can be truly
astonishing is the fact that the
number of vehicles on the roads
of Delhi is more than that of the
three other major Indian metros
put together. The Government,
in order to mitigate this
problem, aimed at discouraging
private mode of transport and
encouraging public mode through
the introduction of quality rail
based MRTS or the Mass Rapid
Transit
System.
Developed
countries include such systems
in their city planning even when
the population touches 1 million.
This is done so that the city can

handle the burden of population


and yet allow for free flow of
traffic in a planned and phased
manner.
The city administration of Delhi has
to deal with a growing population
of 16 million, a figure that very
few cities in the world face today.
But on the positive side, Delhi
has offered itself for upgrading
to the MRTS by having wide
roads (that form 23% of the
city) with excellent connectivity.
Another attribute that favoured
faster implementation of MRTS
at Delhi is that majority of land
are Government owned and
consequently
lesser
worries
regarding acquisition of private
land.

Phase 1
Delhi Metro Rail Corporation, was
incorporated in 1995 with equal equity
partnership between Government of
India and Government of National
Capital Territory of Delhi. Phase 1 of
Delhi Metro has already earned the
credit of being a passenger friendly,
clean, safe and fast mode of transport
in the Capital region. Costing close
to Rs.105.7 billion, Phase 1 of Delhi
Metro primarily comprises of three
lines (I, II & III) that totals a length of
62.29km.
Line I runs between Shahdara
to Rithala covering a distance of
22.06km, with 18 stations and 18
trains available at a frequency of
4 minutes during peak time. Line II

Underground rail corridor for Delhi Metro

ECC CONCORD Oct - Dec 2010

Phase 1 Network

Colourful lines that intersect Delhi


Length
(Kms)

No. of
Stations

Line No.1- Shahdara-Tri Nagar-Rithala

22.06

18

Line No.2- Vishwavidyalaya-Central Secretariat

10.84

10

Line No.3- Indraprastha-Barakhamba


Dwarka Sub City

32.10

31

65.00

59

Line

Total

Road-

The Red Line was the first line of the


Metro and connects Rithala in the
west to Dilshad Garden in the east,
covering a distance of 25.09 km
The Yellow Line was the first
underground line running for
44.36 km (27.56 mi) from north to
south and connects Jahangirpuri
with HUDA City Centre
The Blue Line is the first Metro line
that connects areas outside Delhi.
It is partly overhead and partly
underground connecting Dwarka
Sub City in the west with the satellite
city of Noida in the east, covering a
distance of 47.4 km
Green Line is the first standardgauge corridor of the Delhi Metro.
This fully elevated line connects
Mundka with Inderlok, covering a
distance of 15.1 km
The Violet Line is the most recent
line of the Metro, covering 15 km
connecting Sarita Vihar to Central
Secretariat

Top down excavation method with diaphragm wall

runs between Vishwavidyalaya and


Central Secretariat Stations covering
a distance of 10.84kms and has
10 underground stations. Line III is
operating between Barakhamba
Dwarka section and covers a distance
of 32.10kms with 31 stations. In
1988, the construction of Metro Rail
Project commenced. The Shahdara
Tis Hazari section was commissioned
in 2002;Tis Hazari Inderlok section
in 2003; Inderlok Rithala in 2004.
The first underground section between
Vishwavidyalaya and Kashmere Gate
was inaugurated in 2004 and the
Kashmere Gate Central Secretariat
was completed in 2005. The benefits
of Phase I project include 1.5 million
commuter trips per day siphoned off
the roads with 1,650 less buses on
the roads; Increase in average speed

ECC CONCORD Oct - Dec 2010

of road buses from 10.5 km/h to


14 km/h; Saving of 2 million manhours per day and the fuel cost of
approximately Rs.650 crores per
year; Reduction in pollution (30%)
and accidents (30%).

Various components of an underground station

DMRC Phase II
If one were to look at the Metro
map of Delhi, it would present a
vibrant picture with colourful lines
intersecting the populous city. Each
metro line is represented by colours

such as red, yellow, blue, green,


and violet. This colour coding has
made it elementary and simple for
commuters to identify the network
and travel with ease. As of October
2010, the whole of Phase-I and
parts of Phase-II are complete, with
the network comprising five lines
with 130 metro stations and a total
length of 156 km.

L&T and DMRC


Under Phase I, L&T was involved as
a Joint Venture partner in the design
and construction of civil, mechanical
and electrical works for DMRC
MC1B package comprising of
7km tunnelling using tunnel boring
machines and construction of six
underground station buildings. This
included construction of cut and
cover tunnel structure between Ch. (-)
1.52km and (-) 2.05km, Mandi House
underground station and a ramp on
the extension of Barakhamba RoadConnaught Place-Dwarka Section
(Line No.3) and Barakhamba Road
Indraprastha section for DMRC.
Construction for DMRC predominantly
included methodology such as cut &
cover, top-down and bottom-up.
Construction process of top down
method
yy

Construction of diaphragm wall

yy

Installation of plunge columns &


tension piles

yy

Install dewatering and re-charge


wells

yy

Excavation upto roof slab level at


3m from natural ground level

yy

Construction of roof slab

yy

Excavation below roof slab and


upto concourse slab

yy

Construction of concourse slab

yy

Excavation below concourse


slab to base slab bottom level

yy

Installation of waterproofing
system including drainage layer

Excavation in progresses for D wall

yy

Construction of base slab over


no-drainage layer

yy

Construction of up-walls and


platform slab

yy

Develop plunge column into


permanent
columns
from
concourse to roof slab & base
slab to concourse slab

Construction process of cut &


cover method
yy

Installation of dewatering well


at least 6 m below the formation
level in case of aluvium soil

yy

Installation of recharging well

yy

Installation of soldier piles

yy

Manual excavation upto 1.8m


depth to search utilities and
suitable supporting system if
detected. Installation of timber
lagging is done simultaneously

yy

Excavation with machine


upto 1m below the 1st layer
strut

yy

Installation of 1st layer strut

yy

Proceed
with
2nd
level
excavation upto 1m below the
2nd layer strut

yy

Installation of 2nd layer strut

Bottom up excavation method with soldier piling

ECC CONCORD Oct - Dec 2010

Delhi Metro Map - Phase 1 & 2

yy

Repeat this procedure


formation level is reached

yy

Monitor the soil displacement


periodically

yy

Construction of the concrete


tunnel/station

yy

Sand filling at the side of the

tunnel/station and soil filling


upto ground level

yy

Stop dewatering and plug the


dewatering wells

yy

Simultaneous de-lagging in
correlation with the progress of
backfilling but not more than
1m at any point of time

yy

Restore the road and other


existing installation as it was
earlier

yy

Remove the soldier pile

till

Phase II Network*
Length
(Kms)

No. of
Stations

Shahdara Dilshad Garden

3.09

Indraprastha Noida Sector 32 City Centre

15.07

11

Yamuna Bank Anand Vihar ISBT

6.17

Vishwavidyalaya Jahangir Puri

6.36

Inderlok Kirti Nagar -Mundka

18.46

15

Central Secretariat HUDA City Centre

27.45

19

Dwarka Sector 9 to Dwarka Sector 21

2.76

Airport Express Line

22.70

Anand Vihar KB Vaishali

2.57

Central Secretariat Badarpur

20.04

15

Total

124.63

83

Line

*courtesy www.delhimetrorail.com
6

ECC CONCORD Oct - Dec 2010

In Phase II, L&T was awarded five


packages that included

1. BC 15 Udyog Bhawan
Underground Station &
Tunnel
2. BC 17 Green Park
Underground Station &
Tunnel
3. BC 18 Hauz Khas
& Malviya Nagar
Underground Station &
Tunnel
4. BC 19 A / C Saket
Underground Station &
Tunnel
5. C 5 Airport Link Tunnel

BC 15 - Udyog Bhawan
underground station and
tunnel

yy

Concreting
(M35/M20/M15)
for Station & Tunnel

yy

Single tube twin Tunnel (Cut &


Cover) North Side - 40m

The scope of work of the package


BC 15 was to design and construct
an underground station plus the
tunnel by cut & cover method
including all temporary support
works, design of temporary works,
formwork, staging, shuttering, utility
diversion, traffic diversion etc.

yy

Twin tunnel (Cut & Cover) South


Side 110m

yy

Roof Slab

yy

Concourse Slab

yy

Base Slab

yy

Plenum Walls

yy

Platform Slab

Scope of work

yy

Public Staircase
staircases

yy

UPE Walls

yy

Vent shafts

yy

Entry & Exits with integration


with the existing traffic

yy

Underground Ancillary Buildings.

yy

all other Equipment Rooms like


ECS/TV, SER, SCR etc. including
Cable Ducts from ASS for
Designated Contractor Access.

yy
yy

yy

Construction of diaphragm wall


for station 800mm thick
Excavation between Diaphragm
Wall
including/excluding
temporary
supports
and
excavation between soldier
Piling including instillation of
soldier piling, struts, etc.
Waterproofing with 2mm thick PVC
Membrane for Station & Tunnel

&

fireman

yy

All other Equipment Rooms like


ECS/TV, SER, SCR etc. including
Cable Ducts from ASS for
Designated Contractor Access Lift & Escalators

yy

Track way Basic Structure for


Designated Contractor Access
Track work

yy

Station concourse Paid/Free


Areas for Designated Contractor
Access - AFC (Udyog Bhawan
Station) including EFO & TOM.

yy

Provision of station & substation


structures, utility diversion &
relocation etc.

yy

All works necessary to provide


inter-modal transfer facilities
for pedestrians & road users
at ground level & access into
station.

yy

All temporary & permanent


utilities including foul drainage
to be connected into public
services.

Work in progress at Udyog Bhawan underground station

ECC CONCORD Oct - Dec 2010

Major Equipment
Cranes

3 nos.

Batching Plant

: 1no.60cu.m
+ 1 no. 30 cu.m

Boom Placer

1 no.

Excavator

5 nos.

Loaders

2 nos.

Total Station

1 nos.

Diaphragm Wall Rig :

1 nos.

Piling Rig

1 nos.

Bar Bending Machine :

6 nos.

Bar Cutting Machine :

6 nos.

Generator

3 nos.

Transit Mixers

11 nos.

Excavation works in progress at Hauz Khas

yy

Co-ordination & interfacing with


other
contractors/consultants
for track work. System- Wide
work etc.

yy

All temporary traffic diversion


works which will be required

Udyog Bhawan station after completion

ECC CONCORD Oct - Dec 2010

for the smooth flow of Traffic


in order to carry out the works
without
any
interruptions
including all safety precautions,
signage,
barricading,
emergency lighting etc.

yy

All aspects of quality assurance,


including testing of materials
and other components of work.

yy

Shifting of Utilities coming in


the area of work. Manpower

Security screening at Udyog Bhawan

deployment for road diversions.


Ensuring cleanliness of Road.
yy

yy

yy

Submission of completion
(As Built) drawings and
other related documents as
specified.
Site Clearance and dismantling
of obstructions etc., before
commencement of work.
Setting out & layout of the works,
bench marks and provision of
necessary labour, instruments
and appliances.

yy

Cleaning of site and handing over

yy

Maintenance of completed
Work during the period of
Maintenance

The BC 15 package takes


paramount importance among all
other packages in Phase II because
the underground station and the

running tunnel on both sides are


located right below one of the most
important and VVIP areas of the
country. Due to the presence of
important Government buildings
and residence of eminent leaders
Major quantities
Diaphragm Wall

: 7650 sq.m

Concrete

: 55,000 cu.m

Reinforcement Steel :

8,145 t

Structural Steel

2,600 t

Excavation

: 2,10,000 cu.m

Backfilling

: 48,000 cu.m

Waterproofing

: 35,000 sq.m

I m dia Pilling

: 2400 rmt

Doka Steel

500 t

and bureaucrats, diverting traffic


for construction posed a great
challenge and all activities had

to be planned in such a manner


that construction caused minimal
possible hindrance to these
VVIPs.
The underground station and the
tunnel were to be located below
the road. The width of the station
varies from 12 m to 26 m and the
depth was 16 m. The station design
consisted of Base Slab at 16 m
depth which were to be used for
track work, platform at 13 m and
equipment at concourse level at 9
m depth for passenger ticketing
and rooms for functioning of
station; and at the top is the roof
slab at 2 m depth. Once the roof
slab is completed, back filling
needs to be done after which the
roads need to be laid.
During peak period labour
strength was at 1200 with staff
strength at 34. Both the labour

ECC CONCORD Oct - Dec 2010

Passengers alighting at Udyog Bhawan station

control measures were taken


appropriately

and staff were divided into two


shifts to execute the job round the
clock.

yy

Construction Methodology

Medical tests were carried out


for all labours before induction

yy

Cranes were provided with


Safe Load Indicators (SLI) and
tools & tackles were inspected
by an external agency before
implementing at work

North tunnel measuring 38 m


was done using cut and cover
method, followed by bottom up
station, top-down station and
another tunnel at the south side
measuring 110m.

yy

Safety Health & Environment and


Project Quality
yy
yy

yy

10

Barricading
zone

the

construction

Monitoring
instruments
like
settlement
points,
Piezometer,
Inclinometer,
Load Cell and Strain Gauges
were installed to monitor the
movement of structure on a
daily basis
Air and Noise monitoring was
done on quarterly basis and

ECC CONCORD Oct - Dec 2010

yy

Dumpers were provided with


reverse horns and backlights.
Drivers were checked for alcohol
consumption through alcohol
monitoring machine
Diversion boards were placed
at frequent intervals for proper
vehicular traffic diversion

yy

Traffic marshals were provided


to manage traffic

yy

Noise Proof Power Generators


were used

yy

Columns were marked with


Fluorescent paint for easy
visibility during excavation

Safety,
Health
and
Environment Statistics (as of
Oct 2010)
Total man-hours :

5377780

No of First-Aid cases :

55

No of reportable accidents :

NIL

No of fatal accidents :

NIL

Total workmen covered under


Tetanus Immunization :

306

No of reportable sick cases :

NIL

Total workmen who have undergone


medical examination :
4414
Tree Plantation / Tree Cut : 241/ 86
Environmental Accidents :

NIL

Awards
yy

ISO 14001:2004 and OHSAS


18001:1999.

yy

Prashansa Patra in Construction


Safety Awards from National
Safety Council India

BC 17 - Green Park
Underground Station &
Tunnel
Located in South Delhi, the Green Park
station falls in the corridor between
Central Secretariat to Gurgoan. With
Gurgoan gaining significance as a
business hub, there is a heavy traffic
of commuters proceeding for work
Major quantities
Concrete

: 85,000 cu.m

Reinforcement Steel :

14,500 t

Structural Steel

4,200 t

Excavation

: 3,50,000 cu.m

Backfilling

: 1,25,000 cu.m

Trial run of metro train during construction of Green Park station

Doka Steel

Secretariat Viswavidhalya corridor


constructed under Phase - I. The
Green Park station is also strategic
in location as it is located below
the arterial road of Delhi called
Aurobindo Marg.

800 t

to this area from Delhi. There are 9


underground stations in this corridor
which is an extension of the Central

Scope of work
yy

Design of the station 318 m and


tunnels on both side of station
(including cross passages)
486m. The Design was done by
M/s Mott Mac Donald

Tunnel breakthrough after drive from Hauz Khas to Green Park

ECC CONCORD Oct - Dec 2010

11

Entry gates at Green Park station

yy

yy

Construction of underground
tunnels on both sides of station
by cut & cover method

yy

Construction of client office

yy

Interfacing with architectural,


system contractors like E&M,
signaling& telecommunication,
lift for access to equipment

Major Equipment
Cranes

Traffic
diversion
including
diversion of roads for construction
of station and tunnel

Batching Plant

: 1 no. 60 cum
+ 1 no. 30 cu.m

Boom Placer

1 no

yy

Installation of steel walkway


inside the tunnel

Excavator

8 nos

Loaders

3 nos

yy

Block work for equipment and


ancillary rooms in station

Total Station

2 nos

yy

Restoration of roads and other


structure after construction

Diaphragm Wall Rig :

2 nos

Piling Rig

2 nos

yy

Diversion and restoration of civil


utilities, electrical utilities and
telecom utilities fouling in the
alignment

Bar Bending Machine :

10 nos

Bar Cutting Machine :

8 nos

Generator

5 nos

Transit Mixers

11 nos

yy

12

Construction of underground
station by cut & cover method
including entry-exit structures,
utility
galleries,
equipment
rooms, etc.

ECC CONCORD Oct - Dec 2010

6 nos

rooms,
installation
equipment etc.

of

The construction of Underground


Station and Tunnel at Green Park
was also a mission critical task
due to presence of enormous
utilities and heavy traffic on the
arterial Aurobindo Marg. The
Underground Station and Tunnel
was to be constructed just below
the surface of the road. The width
of the station was 20 m and depth
of station below Ground Level at
16 m. The station consisted of
Base Slab at 16 m Depth which is
to be used for track work, platform
at 13 m depth for passengers
boarding the train and equipment
rooms for working of Station,
Concourse Level at 9 m depth for
Passenger Ticketing and Rooms
for functioning of Station; and at
top is the roof slab at 4 m depth.
Above roof Slab backfilling was

done and then restoration of road


was done.
Traffic survey conducted before
commencement of construction
indicated that traffic density
Passenger Car Units (PCU)
at this stretch was already
more than 1 (i.e. the existing
road width was insufficient for
carrying traffic). The maximum
road width available was 42
m and minimum was 35 m
width. Out of this, construction
activities would occupy 25 m
leaving only 10 to 17 m for
vehicular traffic. Top down
Construction
methodology
was adopted for Station and
Bottom up methodology for the
tunnels.
At peak period this package
had a labour strength of 2000
labours and staff strength at 60

Green Park station with metro trains on both the platforms

who were divided into day and


night shifts.
Awards & achievements
yy

ISO 14001:2004 and OHSAS


18001:1999

yy

RoSPA
Gold
Award
for
contribution
towards
Occupational Health and Safety

yy

Completed 9.5 million safe


man hours

A train arrives on the platform at Green Park station

ECC CONCORD Oct - Dec 2010

13

14

ECC CONCORD Oct - Dec 2010

ECC CONCORD Oct - Dec 2010

15

BC 18 -Hauz Khas & Malviya


Nagar Underground Station
& Tunnel
Scope of work
Design & build two underground
metro stations including 3.2 km
of twin tunnel was awarded to
the Metro Tunnelling Group Joint
Venture of which L&T is a partner.
Hauz Khas station was constructed
using cut and cover method and
top-down approach method while
Malviya Nagar was done by using
bottom up approach. The scope
also included
construction of
associated entry / exit structures,
utilities galleries, AC plant rooms,
pump houses, water tanks, diesel
generator set room, etc. All the
surface
restoration
including
restoration of utilities was also
part of this lump-sum contract.
The contract also included getting
all
the
necessary
approvals

and clearances from


Government authorities.

RCC

86500 cu.m

Rebar used

13200 t

Earthwork

: 326000 cu.m

Diaphragm Wall :16343 sq.m (932 m)


Waterproofing :

ECC CONCORD Oct - Dec 2010

26570 sq.m

Plunge Columns : 34 nos. (1.2 m dia)


Soldier Piles

680 nos.

Rock Excavation :

12000 cu.m

Soil Anchors

721 nos.

Corridor overview
Tunnel Length : 3144.046 m
Station Length : 618.4 m (Hauz
Khas = 318 m ; Malviya Nagar
=300.4m)
No. of rings : 5300 nos

Width of rings : 1.2 m


Avg. segments cast/day : 15 nos

Quantities for Hauz Khas &


Malviya Nagar Stations ( MTG ) :

Top down construction - roof slab casting in progress at Hauz Khas

16

various

Start of Tunnelling : 4th Jan, 08


End of Tunnelling : 20th April, 09
No. of drives : Three x Twin
Avg. daily progress in tunnels : 10
rings/day
Avg. weekly progress in tunnels :
70 rings/week
Highest monthly progress achieved
: 362 rings (B7 East Tunnel) during
May 08
No of Cross Passages (NATM
Method) : 5 Nos.
Major achievements at Hauz Khas
Station
yy

52 trees that were to be cut during


flyover diversion were saved

yy

Utility of trunk sewer of 1200


mm dia diverted using TBM
trenchless technique for a
length of 280m.

yy

All the affected works were


restored to the satisfaction of
Laxman public school - the
major contributors of land for
the station

yy

This was the only station in the


whole corridor having 1200
mm thickness Diaphragm wall
due to its heavy design on
account of 5-6 m overburden
on top of roof slab of station
box.

yy

Hauz Khas station had been


the model station for various
new activities such as block
works, erection of smoke down
station, cavity wall construction,
finishing items, etc.

Rebar of steps at entrance - Hauz Khas station

yy

Optical fibre cable of 2400


pairs crossing the station was
meticulously supported below
the deck and accommodated
in backfilling

Major Equipment
TBM : 2Nos.
Crane : 450mt, 150mt, 75mt
Locomotive : 2 nos.
Segment wagon : 2 nos.
Grout car : 1 no. (3.5 cu.m)
Muck wagon : 5 nos. (10 cu.m)
Grout batching plant :1 no. (30 cu.m / hr)
Power supply : 1000 KVA DG 3 nos.
Chilled water : Chiller plant installed
at surface
Compressed air : Compressors
installed at surface to operate man
lock and other equipment
Ventilation :
Fans installed at
surface with ducting extending
continuously with tunnel progress
yy

600 dia sewer line diverted at


6m depth using part trenchless
and part open-cut method

yy

An alternative arrangement
was planned for smooth and
unhindered flow of traffic

Base slab RC work in progress at Hauz Khas station

ECC CONCORD Oct - Dec 2010

17

Hauz Khas station after completion

Major Challenges

Bottom up construction at Malviya Nagar station box

18

ECC CONCORD Oct - Dec 2010

yy

Land Acquisition was a major


challenge in the beginning as
the Malviya Nagar station was
situated on DDA land having
legal cases pending since 1982

yy

The central part of 180 m long


stretch out of 300 m length
was of rocky strata (from -10
m depth) so it was not possible
to execute Diaphragm Wall.
It was sought to re-design
the station using bored piles
with embedment of 1 m in the
rock and soil anchors to retain
the soil while proceeding for
excavation

yy

Executing
diaphragm
wall
needed operation of hydraulic
rigs with a swing radius of 9
m. This operation was partly
blocking the gate of Laxman

public school. Inconvenience


was avoided by establishing
a time frame to work on the
diaphragm wall only after the
school hours
yy

Hauz Khas Station encountered


major utilities on the southern
part of the ring road such as
major water lines (700 dia, 200
dia, and 1800 mm dia SWD
and 1200 mm dia )and sewer
line at 10 m depth

yy

During construction of panel no.


123,a 600 dia sewer line which
was not shown in the drawing was
encountered. This was overcome
by first closing the panel by soft
concrete and diverting the sewer
line to an alternate path

yy

Tunnel was constructed with


proper alignment and within
tolerance

yy

The tunneling was completed

D-Wall cage being lowered

safely
despite the fact that
alignment passes below the old
Begumpur villages with many
underground basements and
high rise buildings

yy

All
the
contractors
were
sensitized on crucial due dates
to plan on their tight interface
and civil works

yy

Lifting and lowering of heavy

Entrance of Malviya Nagar station

ECC CONCORD Oct - Dec 2010

19

Excavation works in progress side soil retaining using soldier piles and soil anchors at Malviya Nagar

TBM components and their


movement was an interface
challenge

Saket underground station after completion

20

ECC CONCORD Oct - Dec 2010

Safety
yy

Sites of the Corridor and


Trophy was awarded
by
lieutenant
Governor
of
Delhi

MTG was adjudged the best


safe site among all DMRC
yy

Safety
helmets,
shoes,
goggles,
helmets
with
tinted shields and gloves
were provided as per the
requirement of the task

yy

Safety
officials
inspection

yy

Daily
PEP
talks,
alcohol
consumption monitoring and
training programmes

yy

Clean and hazard free house


keeping

yy

Completed 16.5 million


man hours

weekly

safe

BC 19 A & BC 19 C - Saket
Underground Station &
Tunnel

Major Quantities

BC 19 A - Saket Underground
Station
Scope for this package includes
design
and
construction
of
underground station at Saket by
cut & cover method on Central
Secretariat Qutub Minar Corridor.
This too is an important corridor
of Delhi metro that connects North
Delhi to South Delhi and going
upto Gurgaon cutting across a very
densely populated and frequently
commuted area in the Capital.
The Saket station measures about
285 m alongwith 3 entry and
exits that measure an average of
80m. The contract also includes a
double storied ancillary building.
During peak period this package

Excavation (Upto 17 m depth)

170000 cu.m

Backfilling

42000 cu.m

Soldier Piles (Depth upto 24 m)

632 nos

Diaphragm Wall (800 mm)

6400 sq.m

Plunge Columns (1 m Dia & 20 m Depth)

43 nos

Roof Slab (Depth 500mm to 1200mm)

11500 sq.m

Concourse Slab (Depth 400mm to 750mm)

6000 sq.m

Base Slab (Depth 500mm to 1000mm)

11500 sq.m

Platform Slab (Depth 500mm to 1000mm)

3396 sq.m

External Walls (500mm to 800mm)

6000 sq.m

Internal RCC Walls (200mm to 800mm)

3000 sq.m

Solid Block Wall (200mm)


:

12000 sq.m /
2400 cu.m

Waterproofing

13000 sq.m

Concrete (M35) in all RCC Works

43000 cu.m

Reinforcement Steel (Fe500) in all RCC Works

6600 MT

Structural Steel (in Soldier Piles, Struts & Walers)

2500 MT

Concreting of roof slab at Hauz Khas station

ECC CONCORD Oct - Dec 2010

21

NATM tunnel shafts at Saket

involved close to 900 labour and


34 staff.
Underground station Construction
Methodology
yy
yy

TopDown Method (adopted for


30%of Station Construction)
Diaphragm Wall Roof Slab
Concourse Slab Base Slab
Internal Works

Herenkenith make S-198 TBM duly refurbished

22

ECC CONCORD Oct - Dec 2010

yy

Bottom-Up Method (adopted for


40% Station Construction)

yy

Base Slab Side Walls


Concourse Slab Side Walls
Roof Slab Internal Works

This type of combining two


construction methodology for the
same structure is an innovative
attempt and couplers were used

extensively in Diaphragm Wall for


ease in construction and to save time
and cost. Koden Ultrasonic Tests were
performed to check the verticality of
diaphragm walls while construction
and thereby avoid cost of rework.
Challenges faced
yy

The fabrication and installation


of 32 m long, heavy struts
(weighing upto 18.5 t) and
welding with walers upto a
depth of 15 m below ground
level in 3 layers

yy

Erection in true vertical position


of huge diaphragm wall panel
reinforcement cage weighing
over 22 t and measuring 6 m in
length and 22 m deep

yy

Installation of heavy 2.2 m


diameter hume pipes, each
weighing 9 tons at a radius of
over 20 m in a confined nala

yy

Safety of existing nearby structures


was constantly monitored and
ensured by installing various
instruments such as Tiltmeters,
Strain gauges & load cells

BC 19 C - Saket
Underground Link Tunnel
Design and Construction of
Underground Link Tunnel &

Ramp between Saket & Qutub


Minar (both excluding) by Cut
& Cover Method on Central
Secretariat Qutub Minar
Corridor of Delhi MRTS Project.

Major Quantities
Soil & Rock Excavation (Upto 17 m Depth)

220000 cu.m

Backfilling

110000 cu.m

Soldier Piles (Depth upto 24 m)

720 nos

Roof Slab (Depth 800mm)

11500 sq.m

Base Slab (Depth 800mm)

12300 sq.m

External Walls (Thk 800mm)

15700 sq.m

Internal Walls (Thk 500mm)

5000 sq.m

Waterproofing

15300 sq.m

NATM Lining (600 mm)

9000 sq.m

Concrete (M35) in all RCC Works

49000 cu.m

Reinforcement Steel (Fe500) in all RCC Works

5700 MT

Structural Steel (in Soldier Piles, Struts & Walers)

3400 MT

This project employed 600


laborers and 33 staff during
peak periods.
Construction Methodology
yy

Bottom-Up Method (for Tunnel


& Ramp Construction)

yy

New Austrian Tunnelling Method


(NATM) for tunnel construction

yy

Soil Anchors were used in place


of regular structural struts and
walers in NATM tunnel shaft
in order to have spacious
working platform. This saved
time and ensured safety to a
large extent

yy

Compaction
grouting
was
introduced to make soil conditions
stable in Nala portion, below
which NATM tunnel had to pass

A section of completed tunnel at Saket

ECC CONCORD Oct - Dec 2010

23

TUNNEL BORING MACHINE (TBM)


Parts of EPB (Earth Pressure Balance) type TBM
The Tunnel Boring Machine is a huge, incredible piece of equipment that can forge its way through hard
rock , sand or soil, hollow out tunnels without any disturbance to the surroundings .In DMRC Phase II 12
nos. of TBM were used in the construction of tunnelling for various sections. This is a world record as it is the
highest number of TBMs used in a single location thus far.

Major Components of TBM

1) Cutter Disc

1. Cutter Disc - To excavate rock or soft ground by


the rotation of an assembly of teeth or cutting
wheels under pressure against rock face.
2. Shield Skin - keeps the soil from getting into the
machine and to provide a safe working space for
the workers.

3) Pushing Jack

6) Erector

Erected Segments

4) Main
Drive

3. Pushing Jack - To be in full contact with the


erected segment and hydraulically extend as the
cutter disc turns and thrusts forward.

2) Shield Skin

5) Screw Conveyor

7) Back Up Facilities

4. Main Drive - To provide a force in rotating the cutter disc.


5. Screw Conveyor - To move the spoil at the cutter disc and feed onto a conveyor system.
6. Erector - To erect the segments to form a complete ring after shoving at the tail of the TBM.
7. Back Up Facilities - To travel with the TBM and to service the operation of annular grouting, welding,
extension of ventilation, power and track etc.

24

Initial Drive

Main Drive

Completion of Drive

Disassembly of TBM

ECC CONCORD Oct - Dec 2010

C 5 - AIRPORT LINK
TUNNEL
C5 package forms part of the
Airport Express Line of Delhi Metro
that connects the 23-kilometre
stretch between Connaught Place
and Indira Gandhi International
Airport (IGI). This is also known as
Orange Line and will be operated
by the Delhi Airport Metro Express
Pvt. Limited (DAMEL), a subsidiary
of Reliance Infrastructure, the
concessionaire of the Line. The
metro trains on this line will be the
fastest in the country and will travel
up to 135 km/h instead of 80 km/h
as on the other metro lines.
Once completed, this line will provide
high speed connectivity from the city
to airport with advanced features
such as baggage check-in and
issuance of boarding pass facility at
certain metro stations. This project

also envisages stations with wider lifts


in order to accommodate passengers
with luggage and multilevel parking
at stations.

Some of the important features


at the Airport Metro Express Link
stations include:yy

Direct baggage check-in facility


at New Delhi Railway Station
and Shivaji stadium

yy

Wide lifts at all stations to


accommodate passengers with
luggage

yy

Multilevel parking is planned at


New Delhi Station and regular
parking bay at Shivaji Stadium

yy

Dwarka Sector-21 station will


have an interchange between
Airport Express Line and Line3

yy

Airport Express line has been


built over eight busy roads which
carry a substantial volume of
traffic, including the Ring Road,
National Highway 8, Ridge
Road and Sardar Patel Marg.
Once completed this metro

Major Equipment
TBM with all accessories : 2 units
Cranes

: 7 nos

Gantries

: 7 nos

EOTS

: 2 nos

Vacuum lifters

: 02 nos

Batching plant/grout plants : 4 nos


DGs (diff. Capacities)

: 12 nos

Boom Placer

: 01 nos

Excavators

: 02 nos

There are six proposed stations


on this line known as City Airport
Terminals (CATs) and all the stations
will be secured through a network of
CCTV cameras.

Precast tunnel ring segments on the airport link

ECC CONCORD Oct - Dec 2010

25

Transportation of muck by rail system

line is expected to reduce traffic


volumes and pollution on these
arterial roads
The total 23 km stretch of Airport
line is divided into 7 Contract
packages namely AMEL C1 to
Major Quantities
Tunnelling by TBM : 1.587 km x 2

Lines (5.70m Dia)
Cut &Cover Tunnel : 813 m x 2 Lines
Shafts

02 nos

No. of Segment Rings :

2116 nos

Cross Passages

04 nos

Excavation works : 2,60,000 cu.m


Backfilling works : 1,90,000 cu.m
Concreting Works : 42000 cu.m

Hauz Khas entry - exit excavation

TMT-Rebar Works :

5800 m

Structural Steel Works :

3000 t

C7, and Larsen & Toubro Limited


Shanghai Urban Construction
Group - JV has been entrusted
to construct AMEL-C5 Design &

Water Proofing

26

: 12,000 sq.m

ECC CONCORD Oct - Dec 2010

Construction of Tunnel between IGI


Airport Station and Dwarka Sector
21 Station (Excluding Stations).
This AMEL-C5 Package is the link

tunnel between the IGI station and


Dwarka sector 21 stations
The contract for AMEL-C5
awarded
to
L&T-SUCG
JV
includes design and construction
of tunnel between IGI station
and Dwarka Sector 21 station
(excluding stations).

yy

tunnel with strut waler system

yy

Shifting of utility services

Construction of box tunnel by


cut & cover method

yy

Settlement monitoring activities

yy

Building survey works

yy

Providing waterproofing system

yy

Backfilling works & removal of


solder piles

Construction Methodology
yy

Tunnel

by

TBM

method,

Scope of Work
yy

Construction of TBM launching


chamber

yy

Pre-cast
segments

tunnel

ring

yy

Construction of twin
tunnel by TBM method

bored

yy

Construction of TBM receiving


chamber

yy

Construction of cross passages


connecting bored tunnels

yy

Providing soldier pile system


and excavation for underground

of

Utility services at an underground station

Work in progress at Saket underground station

ECC CONCORD Oct - Dec 2010

27

excavation / boring by EPB


machine and precast segment
erection
yy

Cut & Cover tunnel by soldier


piling , excavation with strut-waler
system and box construction by
bottom-up method

yy

Cross passages by NATM

Challenges
Alignment of tunnel in DIAL and
prevention of settlement
Delhi International Airport Limited
(DIAL) was apprehensive that the
underground tunnel may lead to
settlement and create problems
for the operation of planes on the
runway. It was also considered that
the airport operations may have to
be stopped during the construction
of tunnel by TBM. Through detailed
and continuous meetings it was
agreed that the final settlement will
be brought down to less than 5mm by
employing technical and engineering
solutions. 280 monitoring stations
were fixed in areas such as villages/
Taxiway/Apron and were continuously
monitored by deploying 12 staff.
Through such proactive measures the

Electrical panels at an underground station

airport operation was not hampered


even for a single day during the
construction of the tunnel.
Cross Passages
Tunnels

inside

Bored

Construction of cross passages


in between bored tunnel is done
as per NFPA guidelines for fire
escape. This is done at intermediate
distances of 250 m from tunnel /
station. The cross passage was
completed quickly and efficiently
through monitoring of works and

by adapting the methodology of


NATM.
Miscellaneous services at Arrival
Shaft
Services like water pipeline, Sewer line,
Electrical line were encountered during
construction of Arrival Shaft near IGI
Airport which affected the completion
of Shaft by 2 months. Continuous
interaction with concerned authorities/
agencies resulted in the shifting of
utilities. Unique techniques such
as trenchless boring methods were
adopted to enable the continuous flow
of vehicular traffic above the restricted
working area.
Interface problems/issues with
adjoining sections
Regular
meetings
with
the
representatives of adjoining sections
were held to complete the activity as
per schedule and to avoid any joint
connection.
Control of Oxygen Level and Air
Quality

Inaguration of Central Secretariat - Qutab Minar section at Udyog Bhawan underground station

28

ECC CONCORD Oct - Dec 2010

Systems and gadgets to provide


emergency respiratory protection
was ensured through self-rescuers,
personal breathing apparatus, tunnel
gas monitoring and 60 HP ventilation

View of metro on an elevated corridor

fan systems were provided for a


continuous flow of fresh air into the
tunnel.
Social issues between Indian
and Chinese team - this was
resolved by assigning clear roles
and responsibilities for each team.
Major Achievements
yy

Tunneling works completed


within tolerance - 40 days ahead
of schedule

yy

Very cordial relationship with


local residents helped in closure
of 34 Bore Wells identified on
the alignment line.

yy

Total settlement in DIAL/


Taxiway/Apron achieved within
International parameters

yy

No cracks/settlement observed
in old houses of nearby villages

yy

Taxiway/Apron was not closed


even for a single day during
construction

yy

yy

Terminal 3 building that was


under construction in DIAL went
ahead smoothly without any
settlement/disturbance
Consistent customer rating of
Excellent for Safety standards

Project Safety Statistics

No. of Observations complied : 430


No. of HSE Meetings conducted : 30
No. of HSE Risk Assessments done :43
No. of safe work procedures made : 45

Awards
yy

RoSPA -2010 Silver Award for


Occupational Health & Safety
Standards

yy

ISO 14001-2004 certification for


implementation of environmental
management systems

yy

Certificate for 1million and 2


million safe man hours from
Airport Line Consultant ALC
(DMRC)

Total Man - Hours Worked : 3475821


No. of workmen screened till date :
4655 (May 2010)
No. of medical examination
conducted : 4655 (May 2010)
No. of Tool Box Talks Conducted
: 2196 (May 2010)
No. of External Audits Conducted : 08
No. of Internal Audits Conducted : 06
No. of Mars Audits Conducted : 30
No. of Electrical Audits Conducted : 30
No. of NCR Generated : 775
No. of NCR Complied with : 775
No. of site Observations : 430

Compiled by
Gopi Kannan. S
with inputs from Project Managers D.D. Khot, Jatinder Shukla,
Dharmendra Kumar Sharma,
R.G. Saini & S.V. Rao

ECC CONCORD Oct - Dec 2010

29

Buildings for gearing up production


Maruti is a household name in
India and is the countrys largest
passenger
car
manufacturer
offering 14 different models
with over 160 variants. Presently
Maruti Suzuki India Limited
(MSIL) is producing 1.2 million
vehicles annually and as part of
enhancing their production to 1.5
million, MSIL have ventured to
expand their existing diesel car
assembly plant at IMT Manesar,
30 km from the existing factory
located at Gurgaon, in the state
of Haryana, India.

Scope of work
MSIL invited L&Ts Construction
Division to participate in the bid
for Civil Works related to vehicle
assembly plant and awarded

View of Maruti assembly line

30

ECC CONCORD Oct - Dec 2010

the Contact on a Design &


Construct basis in the month
of February 2010. The contract
was on an item rate basis with
a stipulated schedule of 11
months from the contractual
date of commencement. The
scope for Design & Engineering
includes
preparation
and
submission of detailed structural
and architectural drawings and
follow-up for obtaining the
statutory approvals from local
authorities and submission of
As-Built drawings on project
completion.
The construction scope includes
detailed planning, mobilization
of required resources, sequencing
and monitoring of the operations
and completing the project within

Major Quantities
Description
Earthwork

Quantity

: 1231969 cu.m

Concrete work : 65860 cu.m


Reinforcement

: 4826894 kg

Formwork

: 149597 sq.m

Masonry

Flooring

: 139842 sq.m

Structural steel
work

: 9501544 kg

Aluminium work :

3691 cu.m

22094 kg

Sheeting works : 60000 sq.m


Road work

: 649238 sq. m

the specified contract duration.


Major structures in the contract
aggregating to a total shop area

Excavation adjacent to the existing plant in progress

of 70000 sq.m includes building


of Press shop (9000 sq.m built-up
area), Weld shop (12000 sq.m),
Body Paint shop (10000 sq.m),
Assembly shop (22000 sq.m), KD
Ware house, Bumper Paint shop,
Road work and Utility structures.
During peak periods the project
site
employed
about
2000
labourers and 64 staff.

Construction Highlights
Press Shop: Two press pits involving
deep excavation of 7 m with 2450
cu.m of raft concreting.
Weld Shop: Trusses of 24 m (weight
- 9 t) span to be fabricated and
erected in a single piece.
Paint Shop: 38 steel columns of 21

m height and 96 plate girder of span


upto 16.5 m. It also has three sludge
pits which are 6 m deep.
Assembly: Involves conveyor pit and
shower pit for total area of 1200 m.

Plant
and
deployed

Machinery

yy

Batching Plant - 30 cu.m/hr

yy

Transit Mixer 7 nos

yy

Hydra (14 t capacity) 15 nos

yy

Welding Machine 276 nos

yy

Tyre mounted crane


capacity) 3 nos

yy

Silent Generators - 9 nos with


combined capacity of 2000 KVA

(75

Challenges
faced
Brownfield Operation

One of the major challenges faced


was that the project site was located
adjacent to the existing plant that
was operational. Hence construction
activities had to planned in such
Structural works in progress

ECC CONCORD Oct - Dec 2010

31

a manner that it did not disrupt


or inconvenience the day-to-day
operation of the existing unit.
Another aspect of concern was that
the soil condition was silty where
excavations upto a depth of 7 meters
(for construction of press pit) posed a
major challenge. This challenge was
mitigated after several discussions
with the client and it was decided to
adapt the methodology of steep cut
with shoring.
Another crucial challenge in terms
of delivery was that MSIL required
demanding interim milestones viz.
handing over of fifty percent area
of paint shop by the middle of
December 2010 and KD shop phase
II by November 2010. In order to
achieve such demanding targets
extra manpower and resources were
planned in advance and mobilized.

Safety
In order to emphasize the importance
of safety, all new employees getting

Work in progress at the KD shop

on-board the MSIL project site, be


it staff or labourer, were made to
attend a Safety Induction training
programme on the very first day of
joining. Safety meetings were held
on a daily basis headed by the
Safety incharge and a representative

Workers cleaning the floor after completion of building

32

ECC CONCORD Oct - Dec 2010

from each site to discuss safety lag,


if any, at a particular site or any
other safety concerns which can
prove hazardous to the workforce.
The basic aim of such meetings was
to proceed towards an objective of
zero accident. To a large extent these

Aerial view of construction activities

measures were effective in resolving


numerous safety issues. By ensuring
safety awareness, the project site was
able to achieve 2.82 safe million
hours as on December 2nd 2010.
MSIL site has also been awarded the
Bi-annual EHS Rolling Trophy for the
period April10 to September10.

Another view of the structure

Quality control
The QC team worked towards
ensuring proper quality standards
of the raw materials such as cement,
sand, aggregates, admixture, fly-ash
as well as the finished products i.e.
concrete and fabricated steel. The

quality laboratory was well equipped


with scientific instruments calibrated
to conform to Indian Standards and
to test the materials at the required
testing frequencies.

Future
In order to have close monitoring
on the demanding schedules and
desired quality, MSIL had deployed a
dedicated team from Japan. The high
level of quality, timely delivery and
close rapport with the MSIL team has
helped build a credible and strong
rapport with the client. By virtue of
such strong relationship management
and as a gesture of confidence, MSIL
has awarded another order for the
further expansion of plant to L&T
directly without any tendering. There
are further expansion projects in the
pipeline with MSIL which L&T hopes
to convert to orders.
Mukesh Goel
Project Manager

ECC CONCORD Oct - Dec 2010

33

Burning the midnight oil at Barmer


The Underbelly of the Thar Desert
in Rajasthan, India, has been found
to contain millions of tonnes of oil
and natural gas. It is only a matter
of time before this inhospitable and
arid desert region would evolve to
become a booming economy with
many leading companies queuing
up to establish their energy projects.
Apart from oil and gas, the Thar
desert is also fast becoming a hotspot for lignite coal and coal bed
methane. Another striking feature
is that this landscape is considered
most ideal for establishing large
tracts of solar and wind energy
fields for tapping green power.
Exploration for oil and gas in the
western Rajasthan region began right

Plant cable tray & lighting

34

ECC CONCORD Oct - Dec 2010

from 1954. In January 2004,Cairn


Energy of UK, announced the discovery
of 450 to 1,100 million barrels of
good quality light crude oil at the
well, N-B-1, in block RJ-ON-90/1 in
northern Rajasthan. Cairn Energy has
till date has made 25 discoveries with
Mangala being the largest of all.
Cairn India, the operator of the
Rajasthan block, holds a 70 percent
participating interest with ONGC,
its joint venture partner, holding
the balance 30 percent. This JV has
already invested approximately USD
2 billion in the Rajasthan project
and has plans to invest a further
USD 1.8 billion by 2011, making it
one of the largest onshore oil and
gas projects in the country.

Rajasthan oil fields are considered


one of the largest oil discoveries
in India in more than 20 years.
Located at Barmer in North
Rajasthan, the Barmer basin
has a production capacity of
approximately 0.18Million Barrels
of Crude Oil Per Day (BOPD)
in peak period. The Mangala,
Bhagyam
and
Aishwariya
(collectively known as MBA) fields
once on peak plateau production
of 175,000 BOPD, will contribute
to more than 20 percent of Indias
domestic crude production. The
Mangala Processing Terminal
(MPT) will act as the hub for
processing crude oil from all the
Rajasthan fields.

Mangala Process Terminal - Overview

Having explored the availability


of Oil, Cairn was challenged
with the task of partnering with
a strong EPC contractor who can
enthusiastically work in the inclement
desert conditions of Thar, mobilise
thousands of workmen and procure
massive machinery necessary to carry
out the operations smoothly. Given
its impressive track record, L&Ts
Hydro Carbon Division became the

Area

obvious choice of Cairn for executing


a project of this magnitude and
complexity.

for Construction of Northern Area


Developmental project was awarded
to E&GP Operating Company.

Electrical & Gulf Projects have been


closely associated for electrical and
instrumentation works with most
of the projects executed by Hydro
Carbon division. In the Cairn project,
the entire package of Electrical,
Instrumentation & Telecom works

The project comprised of setting up


of various systems and sub systems
with three major elements such as
Oil, Gas and Water. Apart from this,
captive power plant generation unit
should also be developed to provide
power for operational needs.

: Scope of Work

Mangala Process Terminal (MPT) : All facilities required for production of 0.18mill. bpd
Mangala Oil Wells (MWP)

: 160 wells spread over 18 wellpads

RGT

: All facilities to meet the requirement of MPT operations

RGT Gas wellpads

: 4 gas wellpads

Thumbli Water Field (NR1)

: All facilities to meet the requirement of MPT operations

Optical connectivity link


: 185 km Optical Fiber work along
connect MPT to RGT, NR1 & Oil Wellpads
33KV Over-head line
: Power transmission from MPT to
(38 km) RGT to Gas Wellpads (6 km)

with
NR1

Inter-field
and

Oil

pipeline
Well

to

pads

ECC CONCORD Oct - Dec 2010

35

The project is spread over four


distinct locations interconnected
through pipelines
yy

Mangala Processing Terminal


(MPT)

yy

Raageswari Gas Terminal (RGT)

yy

Thumbli Water Field (NR1)

yy

Mangala Oil Field Well Pads

Electrical power is generated from


4sets of captive power plants
each having 12MW 11kV power
generator and 3sets of emergency
diesel generator having 2.75MVA
6.6kV for plant start-up purpose.
The generator power is distributed
to various sub-stations inside
MPT, Oil well pads & Water
field. Along with typical electrical
works, the following specialized
electrical jobs were executed for
this project.
yy

Power Management system


(PMS) : This is the heart of the
electrical system which provides
the system Integration of all
captive power stations, diesel
generator and electrical drives
into the DCS (Distributed Control
System). A Central Control
Centre controls the entire power
system through DCS

yy

yy

Steam
&
E m e r g e n c y
Diesel Generator
: Installation of
Automatic Voltage
Control Panel (AVR),
synchronization
panel
and
associated control
cabling is completed
for integration and
commissioning
of Steam Turbine
Generator
(STG)
and
Emergency
Diesel
Generator
(EMDG) system
Power Distribution
to Water Field
: The generated
power from MPT
is stepped upto
33kV system and
distributed through
transmission
line
to Thumbli water
field located 22
km
away.
This
line is connected
to Thumbli substation and further
connected
to
the Electro Static

Scope of work
Electrical
Cable laying

: 1700 km

Cable tray Installation

: 112 km

Earthing

: 150 km

Equipment Erection

: 476 nos

Lighting

: 3400 nos

Instrumentation
DCS Panel

: 350 nos

Cable laying

: 1210 km

Instruments

: 1250 nos

Loop checking

: 4350loops

Telecommunication Works
Fiber Optical cabling

: 185 km

Pipeline Intrusion system

: 97 km

Access Control System

: 190 controllers

CCTV System

: 86 cameras

Fence Intrusion System

: 36 km

MET System (MPT & RGT) : 2 locations


PAGA System
: 800 speakers
105 km cable
Telephone Data Network : 800 phones
Trunk Mobile Radio system : Two 45 m Tower
with 3 Repeater
Stations
Precipitator (ESP) transformer
by special L type HT
termination kit
yy

Power
Distribution
to
Mangala Oil Well pads : The
power generated from MPT is
stepped-up to 33kV system and
distributed to individual well
pads through transmission lines
having route length of 15 km

Instrumentation System
At any oil well or refinery the
instrumentation systems forms the
nerve centre of the entire processing
cycle. All the processing and
production activities are controlled
Night View of Boiler Commissioning

36

ECC CONCORD Oct - Dec 2010

Control room

and
monitored
through
the
instrumentation system. The accuracy
of these systems needs to be very high
and they have to be versatile enough
to provide uninterrupted support with
absolutely minimal or no down-time.
Since the instrumentation used at the
oil and gas refineries have to deal
with highly inflammable substance,
they come with very high standards
and world-class certifications that
permit them for use in such highly
hazardous environment.
At Barmer, instrumentation of
very high accuracy have been
imported, supplied, installed and
commissioned at the MPT terminal as
well as various well pad locations for
measurement, control and extraction
from the well pads and in separation
of crude to Oil, Gas and Water. All
the instruments required for the plant
have been imported from Europe/
USA with certifications for use in
highly explosive and hazardous
environment. The following are
the special instruments provided at
various locations of the project:

yy

Nucleonic
type
level
profiler : For highly accurate
measurement of interface levels
between Gas, Oil & Water in the
storage tanks

yy

Multi-phase flow meter :


Used for measurement of oil
and water content from well
pads. Crude oil extracted from
the well pads is generally a
combination of oil, water,
gas and impurities. The multi
-phase flow meter helps
measure the content of the
oil, water and gas in the oil
extracted from the well pads

yy

yy

Special Analyzers are used to


measure the content of Oil
in Water, Oxygen and water
conductivity analyzers, Base
Sediment and Water (BSW)
analyzer for measurement of
sediments and water in the Oil
Hundreds of pressure transmitters,
temperature transmitters and
level Instruments on various tanks
and pipelines

View of CCTV operator workstation

Telecommunication
System
A strong telecommunication system
is most essential for the smooth
flow of data, communication and
security in the processing units as
well as the well pads. All upstream
facilities were therefore provided
with the following specialized
telecommunication
systems
for
data, voice communication, security
surveillance, access control and
intrusion detection:
yy

Fiber
optic
transmission
system consisting of 185 km
of 12F, 24F, 48F & 120 fiber
optic cables between various
well pads to MPT acting as
backbone for data and voice
communication between the
facilities
ECC CONCORD Oct - Dec 2010

37

Metrology System

Telecom panels

yy

As FO cables are traversing


along the pipeline, these are
also used as a means to detect
pipeline intrusion detection
using suitable computers at
either ends of the FO cable

yy

CCTV
system
consisting
of PTZ and fixed cameras
are provided at various
well pads and the MPT and
RGT terminals. The video is
streamed from various well
pads to the MPT central control

Sub station

38

ECC CONCORD Oct - Dec 2010

room through the fiber optic


network. The MPT perimeter
area is fully covered by the
CCTV system using 86 PTZ
CCTV cameras for security
and surveillance
yy

Fence Intrusion System for


surveillance of MPT / RGT
fence through the use of a
fence mounted fiber optic
cable which has start and
end sensor for detecting and
locating intrusion on the

perimeter fence. Intrusion


system is fully integrated
with CCTV system to provide
seamless security monitoring
of the environment
yy

Public Address and General


Alarm System consisting of
loud
speakers,
beacons,
sounders,
announcement
consoles etc., for delivering
messages and instructions to
the personnel working in the
plant

The Worlds longest-of-its-kind, Barmer - Salaya Pipeline Project


Cairn India has commissioned the worlds longest
heated insulated pipeline project that carries crude oil
from Barmer in Rajasthan to Salaya located at Gujarat.
This crude oil pipeline that measures over 600 km
has earned the credit of being the longest of its kind
pipeline in the world over similar such pipeline projects
in Russia and Indonesia.
The unique feature of this pipeline is that the entire
pipeline is designed to carry crude oil at temperatures
above 65 degree C for reduced viscosity and free flow.
In order to maintain temperatures across the length
of the pipe, 1 MW gas engine generators have been
installed at approximately every 18 kilometers.

Location
The BSPL pipeline, the associated 29 heating stations
and the 3 terminals are passing through one of the
countrys toughest and rugged desert tracts. Such
terrains, coupled with the hostile weather conditions
have posed several challenges for logistics and
productivity. Such challenges were overcome through:
yy

yy

Minimising the travelling distance for work force


and maximising their productivity during cooler
hours of the day
Using double tractors to haul heavy Gas
Generators and accessories over sandy dunes to
remote stations

Project Highlights
yy

Worlds longest, 600+ km of continuous heat


insulated pipeline that travels between two states
covering approximately 200 villages

yy

SEHMS conductor and accessories installation


attached to 24 Insulated crude oil pipeline and

OFC backbone network, besides 8 gas pipeline


at 1.25 m depth
yy

29 heating stations, each having capacity to


generate 1 MW power installed across the length
of the pipeline for enabling continuous heating

yy

3 terminals with launcher and receiver facility

yy

Instrumentation and controls integration with


control rooms to prevent the temperature of crude
oil falling below 65 degree C

Construction Methodology
Heat tracing a method where the viscosity of the crude
oil is maintained at low levels in order to facilitate
the flow of the liquid through the pipeline. Unlike the
conventional method of heat tracing by wrapping
heating coils over the pipe, Cairn India has introduced
a more energy efficient solution, from M/s. TYCO
Thermals, called Skin Effect Heat Management System
(SEHMS). This new technology provides uniform heating
by using eddy current losses
In this technology an electrically insulated conductor
is installed inside the heat tube and connected to the
tube-end at the designed distance. The conductor and
the tube are connected in series to AC voltage. The
return path of the circuit current is pulled to the inner
surface of heat tube by skin effect and with the proximity
effect between the heat tube and the conductor. The
outer surface of the tube remains grounded. This
arrangement constructs the restive impedance circuit,
which generates heat in the heat tube walls and
additional heat is also generated due to eddy current
flow through the insulated conductor.
Arjun Rana
Project Manager

Heating station electrical control room

ECC CONCORD Oct - Dec 2010

39

the extreme weather conditions


prevalent in the region throughout
the year. Apart from this, sourcing
of even basic resources such as
water and power was difficult as
the sources lie scattered in and
around 70 km in the region.

Launcher receiver facilities at Viramgam terminal

yy

yy

Access Control System to


provide controlled access to
plant operators, subcontractor
personnel and visitors to
various areas of MPT, RGT
buildings
Trunked Mobile Radio System
for
voice
communication
between operators at various
locations of the facilities

Hot line communication

40

ECC CONCORD Oct - Dec 2010

yy

yy

Telephone and Data Network


System
and
Network
Supervisory System
Aero
Radio,
HF-SSB,
Metrological systems

Challenges
The primary and most critical
challenge at the Barmer site is

Unprecedented
engineering
changes witnessed an enormous
increase in the scope of work
just after a few months of
commencement. This change had
increased major quantities way
beyond the initial projections. For
instance, cable laying executed at
site alone increased between 80%
to 200%(from 1200 km to 2600
km).
The non-availability of both
skilled and un-skilled workforce
also posed a great challenge.
In order to achieve the project
completion target, an average of
more than 1300 workmen were
mobilized during the peak period.
Though this was a tough task,

Heating station (SEHMS) with 1 MW gas engine generator

it greatly helped in mitigating


any possibility of delay due to
shortage of workforce. Inspite of
stiff resistance from the locals, the
fiber optic cabling between MPT
to RGT (90 km) was completed as
per project schedule

Innovation

with
mechanical
mounting
arrangement using beam and
pitch clamps. Cable laying being
the most critical activity in the
entire project, meticulous route
planning was studied and an
alternate route was suggested in
order to make faster and effective
progress. In order to achieve
the target, a totally different
organization structure was placed
at the site to monitor the rapid
progress of cable laying.

The E&IC package was originally


to be completed in a period of
18 months. However, during
the course of engineering, there
was a significant increase in the
scope and the revised estimated
completion was fixed at 26 months.
There was a great pressure to
innovate the processes and
techniques in order to overcome
the enormous increase in scope
and the demanding time lines.

Achievements

The innovation started with


installation of cable tray in
pipe rack. It was implemented

Executing a project of such large


a scale calls for the best-in-class
efforts and commitment, and

Most of the foundation required


for supporting the field equipment
was
pre-cast
instead
of
conventional construction in situ.
This was implemented considering
the scattered network.

when one does that -records are


bound to come by.
yy

65 km of cable laying in a
single day

yy

Completed
5
Electrical
Substations in a month for
energisation

yy

3.5 million LTI free safe man


hours achieved

yy

Successful
Commissioning
and integration of Electronic
Fence Intrusion Detection
System (8 km) with CCTV
system and commissioning of
Pipeline Intrusion Detection
System (90km) First-of-itskind system in India for Oil &
Gas sector

yy

18 km of OFC blowing in a
single day
M. Shanmuganathan
Project Manager, E,I & T

ECC CONCORD Oct - Dec 2010

41

Rajpura Dariba - The Zinc Thing


The Rajpura Dariba mine perhaps
represents the oldest mining and
smelting operations in the world
for extraction of zinc. Timber
supports recovered from extensive
ancient workings (some timber was
intersected by boreholes at a depth
of 265 m) have been carbon dated
to 2,100 - 2,500 years ago. Early
written records available show that
in 1382 Maharana Laxman Singh
of Mewar reactivated zinc and lead
mining near Udaipur. This goes
to prove that certainly zinc metal
production in India predated that in
Europe by several centuries.
The Rajpura-Dariba deposit was
rediscovered in 1925 by the
Geological Survey of India, and by
1934 it had been shown to extend
on strike for a distance of 17 km.
In 1970 a lease was granted to
Hindustan Zinc Limited (HZL) and
thereafter, with the aid of consultancy
services from RTZ Consultants, U.K, a
mining project was started in 1977,
a capital investment of Rs 728.4
million having been sanctioned
by the Indian Government. HZL
is Indias largest and the worlds
second largest integrated producer
of zinc and lead, with a global share
of approximately 6.0% in zinc. It is a

Panoramic view of plant

42

ECC CONCORD Oct - Dec 2010

subsidiary of Sterlite Industries (India)


Limited and the London based,
Vedanta Resources plc.
The HZL plant is located at RajpuraDariba, a small town in the state
of Rajasthan. Dariba holds the
distinction of being the capital of
the former kingdom of Mewar in
Rajputana Agency and is reputed
as the city of lakes worldwide.
The total reserves of deposits were
estimated at 18 Mt with grades of
7.2% zinc and 1.8% lead. The mine
was commissioned in 1983 with a
planned production of 40,600 t/y
of zinc, 10,500 t/y lead, 445 t of
copper, 175 t/y of cadmium and 16t
of silver. The first Indian occurrence
of renierite is reported from the Curich basal zone of the poly metallic
deposit at Rajpura-Dariba.

Scope of work
Civil & Structural works, Design
and Engineering of EPC 4
Package, Project Management,
Procurement and Supply of various
equipment, Fabrication, Inspection,
Transportation, Unloading including
Free Issue Material, Storage,
Construction, Installation, Testing,
Pre-commissioning, Assistance in
commissioning and Handing Over

Major quantities
Works

Quantity

Excavation

: 485000 cu.m

Backfilling / Disposal

: 575000 cu.m

Concrete

: 201585 cu.m

Formwork

: 380000 sq.m

Brickwork

: 11225 cu.m

Plaster

: 88000 sq.m

Reinforcement

Miscellaneous Flooring

: 32590 sq.m

Doors & Windows

3249 sq.m

Structural Fabrication

10076 t

Structural Erection

10076 t

Grating

: 11850 sq.m

Sheeting

: 53392 sq.m

Sand blasting & Painting :

10750 t

10076 t

Water Proofing

9186 sq.m

Sanitary & Plumbing

680 nos

Mastic Lining

: 42715 sq.m

PVC Lining

: 28650 sq.m

AR Brick Lining

: 28950 sq.m

Cell Casting & Alignment :

132 nos

of the Leaching, Purification and Cell


House Package with other common
utilities of Phase-III 210000 TPA Zinc
Smelter at Dariba Smelter Complex.

Plant and Machinery


Description

Overview of Leaching Area - During Construction

Upon
commissioning
this
210,000 tonnes per annum Hydro
metallurgical Zinc Smelter, &
100,000 tonnes per annum Lead
Smelter and 160 MW Thermal
Power Plant at Rajpura Dariba,
Hindustan Zinc Limited is poised
to become the worlds largest
producer of integrated zinc-lead.

Challenges faced
One of the most crucial challenges
was the cold bending of SS904L
/ CS pipes which were used as
heating coils in leaching tanks. The
cold bending process was needed

to be done in plenty during the


peak season. For resolving this
issue a Pipe Rolling Machine was
designed in-house and custom
built by the plant and machinery
team of L&T on the site. The
addition of this unique machine
had increased productivity greatly
and helped in completing the
project on time.
Among the other challenges,
there was a land acquisition issue
between the client and the local
villagers. After several discussions
a suitable commitment was given
to villagers that employment

Nov09 (Peak Period)

Excavator

: 3

Rock Breaker

: 3

Dumper

: 4

JCB

: 2

Dozer

: 2

Wheel Loader

: 1

Vibro Max Roller

: 2

Water Tanker

: 4

Mixer Machine

: 2

Batching Plant (30 Cum / Hr)

: 2

Stone Crusher Plant

: 1

Transit Mixer

: 11

Concrete Pump

: 3

Concrete Boom Placer

: 1

Bar Shearing Machine

: 4

Surface Planer

: 6

Circular Saw

: 3

Crane - TATA 320

: 5

Crawler Crane 75 / 80 MT

: 5

Crane Tyre Mounted 75 T

: 1

Crane Tyre Mounted 40 T

: 1

Gantry Crane

: 1

Hydra

: 9

Plate Bending Machine

: 2

MIG Welding Machines

: 2

Welding Machines

: 234

Radial Drilling Machine

: 1

Submerged Arc Welding Machine : 1


Trailer 40 Ft

: 6

Tractor Trailer

: 2

Truck

: 4

Lathe

: 1

will be provided and new subcontractors will be appointed


along with additional amount per
man day as site allowances to all
Sub-Contractors.
Pipe Bending Machine - designed In-house

ECC CONCORD Oct - Dec 2010

43

Overview of Leaching Area - After Construction

The location being a dry and arid


region there was an acute scarcity of
proper potable water and water for
construction activities. The heat was
also quite unbearable during most
parts of the year. Windy conditions
would create a lot of dust pollution
which was mitigated by sprinkling
water at site to suppress dust. The
terrain was also rocky in nature
which posed a major challenge for
construction.

Sustainability
The mining industry has been
an area of concern for the
environmentalists because of
the potential harm the mining
activities causes to the surrounding
environ and bio-diversity in the
mining and the processing areas.
But on the contrary, when one
visits Rajpura Dariba, the mining
town presents a picture of sheer
delight and one will change
his/her perception towards mining
companies.
Rajpura
Dariba
presents a surprisingly pleasant
picture of a dust-free and green
ambience surrounding the mines.
44

ECC CONCORD Oct - Dec 2010

Inside View of Cell House

The growing concern for sustainable


environment to meet the present
needs without disturbing the assets
for the future generation has
become a key concept in seeking to
integrate the environmental, social
and development goals of societies
everywhere. As such, the future
of mining is inseparable from the
pursuit of sustainable environment.
Therefore L&T has taken all measures
to ensure that the natural resources in
the project area remain sustainable.
There has been a constant effort
towards environmental preservation
and recycling. During construction,
rocks dumped at a dumping yard
were re-used by crushing and
utilizing it for further construction
work. Waste water was recycled for
use in plantation and landscaping.

Land has been used effectively by


setting up the plant considering a
location away from cultivable land.

Contribution
nation building

towards

What was once a rural area with


scanty vegetation and rainfall patterns
has now transformed into a fully
developed and thriving town with the
construction activity alone offering
employment to close to 6500 people.
The construction work being carried
out by L&T has attracted workers from
neighboring villages, giving them an
alternative source of income. Earlier
Dariba only had a dysfunctional
colony and a small shop for serving
the needs of the society prior to the
initiation of construction of the smelter.

With the construction of the plant, the


old colony has been re-utilized by
L&T and made fully functional with
a bustling market place, providing
major commodities and a new stateof-the-art residential complex. The
plant is also expected to infuse a
trickle-down effect providing economic
and infrastructural development in the
neighboring towns.
Rajpura Dariba has a hospital run by
Hindustan Zinc Ltd. and a Kendriya
Vidyalaya school for providing
quality education to the children
of the town. The Government of
Rajasthan has also recently signed
a MOU with Hindustan Zinc Ltd.,
to upgrade the heart hospital
in Udaipur. Through Vedanta
Bal Chetna Anganwadi project
Hindustan Zinc provides nutrients
to the children in the neighboring
rural areas by adopting 400
Anganwadis in the four districts
of Udaipur, Rajsamand, Bhilwara
and Chittorgarh. Today these
Anganwadis have a planned diet
for the children, water filter for safe
drinking water, hygienic toilets, toys

Kendriya Vidhyalaya at Dariba

and colourful books to read. Apart


from these initiatives, HZL has also
helped set up self-help groups to
empower women below poverty
level to earn a monthly household
income of INR 2500.

Today this erstwhile remote village


can boast of amazing amenities
such as uninterrupted power supply
and internet connectivity, copious
water supply and good roads. L&T,
by partnering with HZL has brought
about a massive
transformation in
Major Quantities EPC Package
the nearby regions.
(Mechanical works)
Contributing
Mechanical
Quantity
towards the Nation
Equipment erection
:
2350 t
Building exercise,
this will be yet
FRP Tanks
:
13 nos
another landmark
FRP Stacks
:
48 nos
for L&T in bringing
FRP Launders
:
1730 m
prosperity to rural
India
Piping (CS-IBR, CS-Non IBR, SS & PPH)
Fabrication

: 90000 inch dia

Erection

: 150000 inch m

SS316L (Tanks & Equipment)

380 t

MS Plates & Structural

2100 t

Rubber Lining
(Inside Tanks & Thickeners)

23200 sq.m

Acid Proof Brick Lining


(Inside Tanks & Thickeners)

23200 sq.m

prevention of accidents) - 2010


Gold Award
yy

Certificate of Merit award for


achieving 20 Million lost time
injury free man-hours during
the period : 24th Oct2008 to
31st Mar2010

yy

Quality trophy award 2010

Achievements
yy

New world record of 21 para


liners erection done
in a
single day. This record had
surpassed the earlier L&T
record of 19 para liners done
in a day at HZL, Chanderiya
site

yy

Successful commissioning of
210,000 TPA zinc plant in a
record period of 38 days.

yy

Highest concrete quantity in a


month, 12862 cu.m

yy

Highest piping erection in a day,


5380 Inch Meter

yy

Highest piping erection in a


month, 46934 Inch Meter

yy

444
sq.m
rubber
lining
completed in a day and 5441
sq.m in a month

Awards
yy
B r i t i s h
Safety
Council
(International Safety
Awards) 2009
(for two consecutive
years)
yy
ROSPA (The
Royal Society for the

Mr. J. Suresh
Project Manager

ECC CONCORD Oct - Dec 2010

45

I N A U G U R AT I O N
L&T completes first phase of Mahatma Mandir in 182 days

Perspective of the Mahatma Mandir

L&T has set a benchmark by executing the phase I of Mahatma


Mandir in a record time of just182 days on design and build
basis covering all civil, mechanical, electrical and IT system
works. This facility spread Over 4 lakh sq.ft was inaugurated
by Honble Chief Minister of Gujarat Shri Narendra Modi,
on 12th January 2011 to host the 5th Global Summit, as a
part of Vibrant Gujarat 2011 programme.
Thanks to the innovative methods like precast technology,
sophisticated construction equipment, tandem lifting using
heavy lift cranes (15 cranes and 25 other lifting devices), this
remarkable feat was achieved in just 182 days. Design and
execution works were carried out in parallel at the project

Shri Narendra Modi, Chief Minister, Gujarat, unveiling the Vibrant


Gujarat 2011plaque

site, which has achieved 6 million safe man hours with a


battalion of 4000 strong work force.

View of the convention centers with a statue of Mahatma

46

ECC CONCORD Oct - Dec 2010

Phase I project of Mahatma Mandir consists of spacious


Convention and Business Centre, well-equipped Exhibition
halls and service buildings. In the second phase, memorial
Salt Mound, a unique Gandhi Sculpture Garden, a Dandi
March suspension Bridge with landscaping and water bodies
will be taken up. When fully completed, it will host, one of
the worlds largest public roof garden, atop the large span
column free convention and exhibition centres.

CSTC at SSU Campus, Bidyadharpur, Cuttack - Odisha, inaugurated

Sri Sri Ravi Shankar along with L&T officials during the inauguration of Vidya

A Vocational Training Centre called VIDYA was set up on


15th November, 2010 at Sri Sri campus, Bidyadharpur,
Cuttack, Odisha. This centre has been established by L&T
and Sri Sri University as a joint venture. This centre aims
to provide vocational training to 200 persons per annum
by inducting school dropouts and socially backward
youths from rural areas of Odisha in Masonry and Barbending trade.

This three months residential training program is


supported by L&T - Construction Skills Training Institute
(CSTI) as knowledge partner, Larsen & Toubro Public
Charitable Trust (LTPCT) as a donor and Sri Sri University
as training provider including infrastructural facilities.
Revered Guruji Sri Sri Ravi Shankar along with senior
functionaries of L&T inaugurated this centre officially on
17th December, 2010.

New facilities unveiled at CSTI


Jadcherla
The inauguration of a new unit for the welding trade
was held at the Construction Skills Training Institute in
Jadcherla on 24th November 2011. The event also
marked a bhoomi pooja for the construction of additional
hostel blocks, staff quarters and a ceremony to present
the course completion certificates to the CSTI trained
skilled workmen. Mr. B Ramakrishnan (BR), Vice President
& Head Divisional Corporate FA& A, presided over
the events along with Mr. D V V S K Chowdary Regional
Manager, ECC Hyderabad.
Speaking on the occasion BR said that the new state of the art
welding unit will enable the students gain complete knowledge
on the subject in the construction industry. He added that the
construction of the new blocks will help in accommodating
over 300 students from the current capacity of 157.

Mr. B Ramakrishnan, Vice President & Head Divisional Corporate FA& A,


inspecting the facility along with Mr. D V V S K Chowdary Regional
Manager - ECC Hyderabad

ECC CONCORD Oct - Dec 2010

47

L&T inaugurates Systems Integration Facility at Jebel Ali, UAE

Left to Right: Tariq Saqer Bin Ghalaita, Vice-President, Global Commercial Customer Relations, Jebel Ali Free Zone Area, Mr. Ibrahim Al Janahi,
Deputy CEO & Chief Commercial Officer, Jebal Ali Free Zone Area, Mr. R. N. Mukhija, President -Operations & Member of L&T Board, Mr. S.C.
Bhargava, Senior Vice-President & Head of Electrical and Auomation Operating Company, His Excellency Mr. M. K. Lokesh, the Ambassador of India
to UAE, Mr. Deepak Morada, Head of L&Ts Corporate Communications and Mr.J.P. Singh, Director of L&T Electrical & Automation FZE.

L&T inaugurated a new Systems Integration Facility on a


floor space area of 11249 sq. meters at the Jebel Ali Free
Zone (JAFZA) in Dubai on October 11, 2010.
The Jebel Ali facility is a significant step for tapping
the automation driven business opportunities in oil and
gas, power, water and infrastructure space in the GCC
region that would contribute to growing L&Ts Electrical
and Automation business outside of India. L&T has
applied for Green Building - Gold Certification for
this facility to the US Green Building Council and,
when approved, will be the first company to receive the
Gold Certification in the Electrical, Automation and
Telecom sectors in JAFZA. Listing in the Green Building
category confirms that the Systems Integration facility
is designed and built for environment-compatibility
and sustainable future, providing a healthy work
environment and reducing operating costs by making
it more energy efficient.

48

ECC CONCORD Oct - Dec 2010

L&Ts President Operations & Member of the Board,


Mr. R. N. Mukhija, unveiled the plaque to declare open
the facility in the presence of Indian Ambassador to UAE,
Consul General of India in Dubai, Dy. CEO & Chief
Commercial Officer of JAFZA, key customers including
ADNOC group of Companies, DEWA, Dolphin Energy
Limited, ADWEA, FEWA, SEWA, Oman Gas Co, Emarat
Petroleum, ENOC, PHEW, OOT ODFJELL, technology
partners, delegates, business associates, companys
senior executives and employees.
Speaking on the occasion Mr. Mukhija said, The Middle
East continues to be a focus area for L&T and we have
enhanced our footprint in the GCC region with this new
venture. Systems Integration and in-house electrical
equipment manufacturing capabilities contribute to offering
total integrated solutions in automation, electrical and
telecom space into the region. As a professionally managed
Indian multinational, we are committed to total

NEW ORDERS
` 2200 Crore Salalah Airport
L&T led Consortium bags First Overseas Airport
EPC Order in Oman
The Buildings & Factories Operating Company has
secured its largest overseas EPC order for the design and
development of the New Salalah International Airport
in the Sultanate of Oman. L&T-Galfar Consortium has
been awarded the project by the Ministry of Transport &
Communications of the Sultanate of Oman in the face
of stiff International competition. The order has a total
value of RO 294,109,999 (USD 764 Million). L&T is the
leader of the consortium. L&Ts scope of works will be
approximately USD 500 Million (Apprx. ` 2200 crore) to
be completed in 30 months.
L&Ts scope of works involves complete design including
airside and land side works, and construction of the 6.6
lakh sq.ft Passenger Terminal Building, Air Traffic Control
Tower, ancillary buildings including MEP Systems and
airport wide system networks.
The Consortium partner Galfar Engineering & Contracting
SAOG is a major company in Oman. L&T has a significant
presence in Oman through L&T Oman LLC a JV company
of L&T and Zubair corporation.
Upon completion the airport will have a capacity to
handle 2 million passengers per annum.
L&T has experience of completing major Airport
projects like Delhi International Airport (T3), Bengaluru
International Airport, Hyderabad International Airport
and is currently executing the brown field development of
the Mumbai International Airport.

` 1030 Cr orders in Buildings &


Factories Segment
The Buildings & Factories Operating Company has secured
orders aggregating ` 1030 crore for the construction of
commercial and residential buildings including metro
depot facilities and add on orders from various on-going
projects. L&T has secured new orders worth ` 385crore
for the construction of residential buildings from leading
developers.

It has further secured orders worth ` 645 crore from


esteemed clients for construction of commercial buildings
including design and construction of metro depot facilities.

` 1181 Cr order for residential Buildings


& Factories
Larsen & Toubros Buildings & Factories Independent
Company has secured new orders aggregating to
` 1181 crore during the third quarter for the construction
of residential buildings, factories including a specialised
support facility building.
L&T has secured new orders aggregating to ` 558 crore
for the construction of residential buildings in major
cities from leading developers. In yet other development,
new orders worth ` 298 crore has been secured for the
construction of factories from esteemed clients. A turnkey
project has been secured from a major client worth
` 325 crore for the design & construction of a specialized
support building facility.

` 716 Cr Infrastructure order from UAE


Larsen & Toubros Infrastructure Operating Company,
has made a major breakthrough in the international
infrastructure segment by bagging an AED 592 Million
(approx. ` 716 crore) contract from the Department of
Transport, Abu Dhabi for the construction of Sheikh
Khalifa Interchange. The site is located at a distance
of 75 km from Abu Dhabi on the Sheikh Rashid road
leading to Dubai and gains significance as it intersects
with the Abu Dhabi Dubai main road linking the two
emirates.
To be completed in 24 months, the project involves
construction of 4 bridges with multi-spans and
multi-cells (from 2 to 8 in-situ box girders); one 62m
long, 20m wide tunnel with single cell voided slab
and 12 km of 4 to 6 lane roads with connector /
distributor networks including associated electrical,
water and drainage networks as well as landscaping
and irrigation. Set to meet the highest International
standards, this project is expected to significantly
improve traffic conditions in the Al Samha region,
especially the truck traffic from the new Sheikh
Khalifa port.
ECC CONCORD Oct - Dec 2010

49

` 1164 Crore Orders from


Metallurgical and Water sectors
Larsen & Toubros Metallurgical, Material Handling
& Water Operating Company has secured orders
aggregating ` 1164 crore from various customers.
Metallurgical Sector: L&Ts Minerals and Metals
Business Unit has secured a major order worth ` 523 crore
from Tata Steel Limited for a 600000 TPY Continuous
Annealing & Processing Line (CAPL). This project will be
implemented through a JV of Tata Steel and a technology
partner for producing high grade cold rolled steel sheet
for automotive application, including skin panels and
high tensile steel. Nippon Steel Engineering will provide
the technology and imported line equipment. L&Ts scope
encompasses technical and project management services,
design and engineering, supply of plant & equipment,
utilities, civil & structural works and complete erection of
the plant. The project is scheduled to be completed in 30
months.
Water Sector: L&Ts Water & Effluent Treatment Business
Unit has secured orders worth ` 530.84 crore from Tamil
Nadu Water Supply & Drainage Board for water supply
schemes in Hogenakkal. The scope includes supply and
laying of 83 km MS pipelines, 948 km DI pipelines and
3488 km HDPE pipelines. The project, funded by Japan
International Cooperation Agency, has a contract execution
period of 24 months. The scope also includes operation
and maintenance of the scheme for 60 months.
In another development, the Company received orders
worth ` 110.60 crore from Punjab Water Supply &
Sewerage Division for the development of a sewerage
network and construction of Sewage Treatment Plant in
Hoshiarpur and Jalandhar. The scope includes supply and
laying of 356 km of RCC, SW & DI pipes. The contract
period is 12 months.

` 2503 Crore Electrical Projects from


Domestic and International Markets
The Electrical & Gulf Projects Operating Company
(E&GP OC) has secured a slew of orders aggregating to
` 2503 crore from Transmission, Substation & Railway
Construction projects in the domestic and international
markets during the third quarter of 2010-11.
In the domestic market, the following orders aggregating
to ` 1516 crore were secured.
50

ECC CONCORD Oct - Dec 2010

a. Electrical Balance of Plant (E-BoP) packages associated


with 10x270 MW Thermal Power Projects at Amravati
& Nashik, Maharashtra for Indiabulls valued at ` 290
crore.
b. A 765 kV Transmission Line from Anta to Phagi and
220/132 kV Gas Insulated Substation at Mansarovar
from Rajasthan Rajya Vidyut Prasaran Nigam Limited,
valued at ` 375 crore. Also a 400 kV transmission line
in Chattisgarh for KSK Mahanadi Power Company
Limited valued at `103 crore.
c. A turnkey project valued at ` 300 crore from GMR,
for 400 kV substations at Alwar and Deedwana in
Rajasthan along with the associated transmission
lines.
d. Track doubling work between Ariyalur and Valadi,
Tamil Nadu including overhead electrification,
signalling & telecommunication works for Southern
Railway valued at ` 190 crore.
e. Grid connected Solar Photo voltaic plant of 20 MW at
Patan, Gujarat, for Kiran Energy Solar Power Private
Limited on a turnkey basis valued at ` 258 crore.
In the GCC Countries, E&GP OC has bagged the
following major EPC orders aggregating to ` 987 crore
for seven substation projects and 153 km of transmission
line projects.
a) In UAE, L&T has bagged two EPC orders valued at
` 269 crore (USD 58.5 Mn/ AED 214.91 Mn) for two
132 kV substations from Abu Dhabi Water & Electricity
Authority (ADWEA).
b) Further, its Joint Venture company, L&T Oman LLC,
has secured orders worth ` 471 crore (USD 102.39
Mn/ OMR 39.38 Mn) which include two 220 kV
substations from Oman Electricity and Transmission
Company, and three 33 kV substations for Dhofar
Power Company & Royal Court Affairs in Oman.
c) Also, Larsen & Toubro Saudi Arabia
owned subsidiary of L&T has bagged
transmission line projects of 100 km
valued at ` 247 crore (USD 53.8 Mn/
Mn) from Saudi Electricity Company.

LLC, a fully
two 380 kV
and 53 km
SAR 201.74

L&T has been making significant strides in electrical projects


both in the domestic and international markets through its
well-established capabilities in execution of EPC Projects.
The above projects augur well with the Companys plan
for expanding the business geographically.

EVENTS
L&T scores high at Green Building Congress 2010

Mr.S.Kanappan, Vice President, Head-EDRC and Mr. R.Nagalingam, Principal Architect, L&T with IGBC dignitaries

Green Building Congress 2010, an International


Conference & Exhibition on Green Buildings was held at
Chennai Trade Centre between 6th& 9th October 2010.
L&T showcased its Energy efficient and Environment
friendly practices at the exhibition while at the conference
three of L&Ts prestigious projects - Cognizant IT facility,
MEPZ Campus, Chennai; Cognizant IT facility, Bantala
Campus, Kolkata and TC-II Building at ECC HQ Campus,
Chennai achieved the Green Building standards required
for certification under LEED India IGBC & USGBC
Rating system.
As part of the tour organized by the IGBC committee,
delegates from India and other countries attending the
conference, visited L&T campus and had an insight into
the green techniques the Company has adopted in the
spectacular buildings in the campus. They were guided
by L&Ts green experts who explained the various green
features incorporated and the accrued benefits.

IGBC delegates at L&T Manapakkam Campus

ECC CONCORD Oct - Dec 2010

51

Connect 2010
L&T participated in Connect 2010 held at Chennai
Trade Centre on 8th & 9th September 2010. The annual
conference and exhibition organized by the Confederation
of Indian Industry (CII) is Indias premier ICT Event to
create a vision for the next ten years of the ICT sector and
a strategy for 4X growth of this sector. Connect 2010 was
hosted by Government of Tamil Nadu and co-hosted by
Ministry of Communications & Information Technology,
Government of India. As the Technology Track sponsor,
L&T displayed its capabilities in fields like automotive
and allied services, healthcare, spaces for modern living
& green building concepts, infrastructure for seamless
commutation, IT & IT SEZ etc.

Hospital Infrastructure India 2010


Indias premier exhibition on hospital infrastructure,
planning, supplies and healthcare development was
held at the Bombay Exhibition Centre between 7th and
9th December 2010. L&T projected its comprehensive
capabilities in providing EPC services for the Healthcare
sector through its participation in this major hospital
exposition.
Panels displaying hospital projects, the architecture,
interior and finishing works with installation of
medical equipment along with the green initiatives
taken by L&T in hospital construction were exhibited
at this show.

Surface Transport 2010


L&T was the platinum sponsor for Surface Transport 2010,
a transport infrastructure show organized by CII, which
was held at Bombay Exhibition Centre from December
21 to 23, 2010.
In an aesthetically designed 60 sq.m stall, lifesize pictures of signature projects including roads,
bridges, railway, metro, ports and other urban
infrastructure projects executed by the Infrastructure
Independent Company & promoted by L&T IDPL
were displayed.

52

ECC CONCORD Oct - Dec 2010

L&T Metro Rail (Hyderabad) Limited selects Owners Engineers

Seated L to R: K V Rangaswami, President, Construction, L&T, Ho Yin Fred Ng, Executive Vice President, Infrastructure, Asia, AECOM
Asia Company Limited, Vinayak Chaterjee, Chairman, Feedback Ventures Private Limited, Avinash Mishra, Country Head, AECOM India
Private Limited, V B Gadgil, Chief Executive and Managing Director, L&T Metro Rail (Hyderabad) Limited, K Venkatesh, Chief Executive,
L&T Infrastructure Developmental Projects Limited
Standing L to R: N Subramanian, Sr. DGM, Business Development, L&T IDPL, Akhileshwar Sahay, President Transportation Division,
FVPL.A Soundararajan, Head Emerging Business, L&T IDPL

L&T Metro Rail (Hyderabad) Limited (L&T Metro), an


SPV formed for developing the Hyderabad Metro
Project has selected the consortium of AECOM India
Private Limited (AECOM) and Feedback Ventures
Private Limited (FVPL) as their Owners Engineers.
The Contract was signed between the two parties in
Chennai on 21st December 2010.
The Owners Engineer (OE) is responsible for
providing Preliminary designs, Design Review of
Detailed design, Documentation, System integration
and System Assurance for the Project and will be
working with L&T Metro till the commissioning of
the Project. Hyderabad Metro Project is one of the
most prestigious & the biggest PPP contract in Metro

Sector in the world involving the construction of 71.6


km of elevated metro rail in three lines criss-crossing
the city of Hyderabad. The project is expected to be
completed in five years.
AECOM, the lead member of the consortium, is
the industry leader in Design of Mass Rapid Transit
Systems and is ranked as the No. 1 design firm in
The Top 500 Design Firms as per ENR 2010. FVPL
is Indias leading integrated infrastructure services
company providing Strategic & Financial Advisory,
Planning & Engineering, Project Management and
Operations & Maintenance services.

ECC CONCORD Oct - Dec 2010

53

L&T signs MOU with the Royal Govt. of Bhutan to train Bhutanese youth
A Memorandum of Understanding (MoU) was entered
between L&T ECC Division and the Ministry of Labour
and Human Resources (MoLHR), the Royal Government of
Bhutan at Chennai on 25th Oct10 to train the Bhutanese
youth.
Under a joint venture agreement between the Royal
Govt of Bhutan and Government of India, Bhutan
is going to produce 10,000 MW of hydropower for
India by 2020 and hence there is a strong demand
for skilled work force as well as good opportunity
for developing local population to meet the demand
and challenges. The Royal Government of Bhutan is
committed to develop skilled workforce and provide
employment opportunities to Bhutanese youth.
In line with this commitment, the MoLHR, being
the focal agency coordinating human resources
development activities, decided to avail the support
of L&T both in terms of resources & expertise for
the development of skilled workforce in various
Construction trades. This MoU embodies the
basic conditions under which L&T cooperates with

MoLHR in establishing Construction Skills Training


Centers (CSTCs) aimed at training the Bhutanese
youth in certain disciplines/trades pertaining to
the Construction Industry and also training and
developing a skilled faculty for conducting such
training activities in Bhutan.
Subject to terms of this MoU, L&T shall provide
training in the trades of System Formwork Carpentry,
Bar Bending & Steel Fixing and Masonry (brick /
block work) at the identified Vocational Training
Institutes in Bhutan and/or at the L&Ts Construction
Skill Training Institutes. MoLHR shall establish
CSTCs in collaboration with L&T at different places /
locations in Bhutan to facilitate skill development in
construction trades.
The MoU was signed by Dr. Sonam Tenzin, Secretary,
Ministry of Labour and Human Resources, the Royal
Government of Bhutan and K.P. Raghavan, Executive Vice
President & Head (Divisional Corporate Centre), L&T ECC Division.

Mr. K.P Raghavan, EVP & Head - Divisional Corporate Centre (sitting second from left) signing the MoU along with Dr. Sonam Tenzin (sitting third from left)

54

ECC CONCORD Oct - Dec 2010

L&T Oman celebrates 15 Years of operations

The celebration was inaugurated with a ceremonial cake cutting by


Mr. A M Naik, Mr. K V Rangaswami and Mr. Rashad Zubair in presence
of H E Mohammed Zubair, H E Maqbool bin Ali Sultan & H E Anil
Wadhwa. Inset : Memento presentation

On 8th November L&T Oman celebrated 15 years of


its successful operation in Oman with a grand event
held at Shangri-Las Barr Al Jissah Resorts. This event
was attended by more than 700 invitees including L&Ts
Chairman & Managing Director Mr. A. M Naik and its
President Mr. K.V Rangaswami along with His Excellency
Maqbool bin Ali Sultan, Minister of Commerce & Industry,
Sultanate of Oman who graced the occasion as the Chief
Guest.
The event was also attended by Public Authority of Electricity
& Water Chairman - H.E. Mohammed Bin Adbullah Al
Mahrouqi, Undersecretary Ministry of Civil Aviation - H E
Said Ali Nafal Al Mashali, Founder of Zubair Corporation
- H E Mohammed Zubair, Ambassador of India - H E Anil
Wadhwa and Associates of L&T Oman including Clients,
Consultants, Vendors & Bankers.
AMN shared his delight at L&Ts business relationship
with Oman and said that Zubair Corporation holds a

special status with L&T. He also mentioned about L&Ts


growth and assured that it will continue to play a vital
role in strengthening the infrastructure of Oman. KVR in
his keynote address walked down the memory lane of
15 glorious years from 1994 to 2009, highlighting the
successful partnership of Larsen & Toubro & The Zubair
Corporation. He thanked His Majesty for his prudence
and policies that have helped the organization flourish.
He also thanked all the customers, vendors, bankers,
employees and well-wishers for their support.

ECC CONCORD Oct - Dec 2010

55

Book on 20 landmark years of Sai Service released

Mr. A. Ramakrishna and K. V. Rangaswami briefing about the book

On 18th Nov 2010, the Corporate Communications


department released a book titled Service to Man is
Service to God on Sathya Sai Projects at Prasanthi
Nilayam, Puttaparthi in the presence of Bhagwan Sri
Sathya Sai Baba.
Lead by Mr. A. Ramakrishna - Former President and
Deputy Managing Director L&T, Mr. K V Rangaswami
presented the first copy of the book to Bhagwan during
the evening prayer at Sai Kulwanth Hall in Puttaparthi
Prashanthi Nilayam. L&T dedicated this prestige
publication to Swami on the occasion of His 85th
birthday on 23rd Nov 2010 for rendering yeoman
service to the society.
The book highlights L&Ts association with Bhagwan
Sri Sathya Sai Baba and the Sathya Sai Central
Trust since 1990 and the 20 landmark years of Sai
Service chronicling every major project L&T has
executed for the trust.

56

ECC CONCORD Oct - Dec 2010

L&T at Chennai Open

Tennis player Rajeev Ram along with the winners of L&T Quiz in the presence of KVR and CCD team

L&T was the Gold Sponsor for Chennai Open 2011, the annual tennis tournament held at SDAT Tennis Stadium
in Chennai. L&T has been a part of this event for the past five years and has gained good brand visibility through
on-court brand promotions and stall displays. This year L&T displayed its comprehensive capabilities in building
infrastructure for sports and games including on court display of banners & signages as well as stall for conducting
brand promotional activities.

Bhoomi Pooja for new L&T - Prayas Medical Centre


The Bhoomi Pooja of the new Prayas Medical Centre complex was held
on 17th October 2010 at CRR Puram, Virugambakkam in the midst
of a good gathering of Prayas Trustees, members and their spouses
from ECC.Mr. K.V Rangaswami presided over the event and laid the
foundation stone for the new Medical Centre along with senior officials
including Mr. V.B Gadgil, Mr. B Ramakrishnan, Mr. S Kanappan,
Mr. S Anantha Subramanian, Mr. T.S Sundaresan and Veterans of
ECC. The bhoomipooja was performed in the morning hours of the
day with the President of Prayas Trust Mrs. Chitra Rangaswami lighting
the lamp along with Mrs. Uma Gadgil, Vice President and Mrs. Shoba
Radharaman, Secretary. Other senior members of Prayas joyfully
participated in the event.

Perspective of the proposed medical centre

The new Medical Centre will have a full-fledged laboratory with modern diagnostic equipment handled by specialized
doctors and it will serve both L&Ts staff as well as the outside patients, at a nominal fee. The project is likely to be
completed by April 2011.
ECC CONCORD Oct - Dec 2010

57

Safety month inauguration at L&T ECC, Manapakkam

Administration of safety pledge

Customary to L&T construction divisions tradition


of welcoming the New Year, the month of January
is being celebrated as safety month across ECCs
domestic and overseas project sites and offices to
reaffirm its commitment towards Safety.
Mr. K.V. Rangaswami, President (Construction)
inaugurated the proceedings at ECC HQ Campus,
Chennai in the presence of senior executives from
the respective ICs on 3rd January 2011. KVR
hoisted the safety Flag to mark the inauguration of
month long celebrations followed by administration
of safety pledge. Speaking on the occasion, KVR
reviewed ECCs safety performance and emphasized
Mr. K.V. Rangaswami addressing the gathering
that much needs to be done to meet the world class
standards. Highlighting some of the recent incidences, KVR said that safety reviews are taken up at the
board level for the first time in L&T and it also needs to be discussed in details at the IC board. He
complimented the safety team for their hard work and urged the team to focus more on EHS issues and
work towards achieving a zero accident year which is the objective of the organisation.
The month long celebration involves include safety awareness and promotional activities such as; First Aid
Training, Fire-fighting Demos, Safety Exhibition, Safety Poster Competition, Slogan Competition, Safety
Essay Competition, Safety Quiz, Tree Plantation, Blood Donation Camp, Medical Camp, etc.

58

ECC CONCORD Oct - Dec 2010

C O R P O R AT E S U S TA I N A B I L I T Y
L&T Sustainability Report 2010 released by Mr. A.M. Naik

Mr. A.M. Naik releasing the Sustainability Report 2010 along with Mr. K. Venkataraman and Mr. M.V Kotwal

L&Ts Sustainability Report 2010 was released by L&Ts Chairman &


Managing Director, Mr. A.M. Naik, along with Mr. K. Venkataramanan,
Member of the Board and President (E&C Projects), and Mr. M.V. Kotwal,
Member of the Board and Sr. Executive Vice President (Heavy Engineering),
at Powais Learning Centre on December 14, 2010. The function was
webcast live across all L&T establishments in India and overseas.
Speaking on the occasion, Mr. Naik offered insights into the multiple
challenges that would be encountered on our sustainability journey.
Providing a pragmatic assessment of the prevailing situation in the corporate
world, Mr. Naik said it was imperative for L&T to deliver targeted returns
to shareholders while remaining in consonance with the company s value
system. He added that rigorous implementation of the new organisational
structure would prove to be another major step in ensuring sustainability
since it replaced an older structure that was clearly out of step with the
enlarged size of the Company s businesses.

ECC CONCORD Oct - Dec 2010

59

L&T-ECC the largest Corporate Blood Donor in Chennai

Mr. V S Ramana, GM & Head Corporate Communications, receiving the Rolling Trophy and Certificate from, His Excellency Sri Surjit
Singh Barnala Governor of Tamil Nadu

L&T employees through the ECC Recreation Club have been active Blood Donors to the Indian Red Cross Society,
Chennai for many years. The Club has been organizing blood donation camps once a year during the month of
May when the requirement for blood is very high in the city. ECC has been the recipient of the Red Cross Rolling
Trophy for 2007 08 and 2008-09 and now for the third consecutive year the Indian Red Cross Society, Chennai
presented the Rolling Trophy for Largest Corporate Donors to L&T-ECC for the year 2009 10.
This award was presented by His Excellency Sri Surjit Singh Barnala, Governor of Tamil Nadu, on 1 st October
2010 at an event marking the National Voluntary Blood Donation Day at Raj Bhavan. Mr. V S Ramana, GM
& Head Corporate Communications, who also oversees the CSI initiatives at ECC received the Rolling Trophy
and Certificate from the Governor, on behalf of ECC and its Recreation Club.

CSR activities at Vizag


The Vizag Steel Plant Blast furnace #3 Project
of E&GP OC organized a CSR activity at Mandal
Parishad Primary School in Dimili Village, near
Yelamanchili. L&T distributed dual desk benches,
school bags, books and stationeries for the children
of MPP School on 19th October 2010.

Mr. D V V S K Chowdary, Regional Manager- ECC Hyderabad


distributing books and stationery to a child

60

ECC CONCORD Oct - Dec 2010

Awareness Campaign at MIAL

organized a Blood Donation Camp on October 27, 2010


in association with Indian Red Cross Society, New Delhi.
Mr. S. Raghunath, Deputy Project Director, DIAL Site,
L&T along with Dr. Agarwal, Indian Red Cross Society
spearheaded this event. The entire team at DIAL
enthusiastically came forward and donated blood. Over
138 units of blood were collected in this third such blood
donation drive since the project commenced in 2007.

Blood donation drive at Cairn MPT

The L&T staff at Mumbai International Airport Limited site


organized an awareness programme for the site workmen
on contagious diseases like tuberculosis, malaria and
AIDS. Over 1050 workmen participated in this one hour
program at MIAL site. The message on awareness and
prevention of disease was conveyed to the site workers
through a play enacted by an NGO called Sanwad.
Stories and songs from popular Hindi movies were also
played by the artist to educate the masses on different
ways and means to cure TB and Malaria as well as
preventive measures for HIV transmission.
This awareness campaign proved beneficial to thousands
of workmen and their families in disease prevention
especially at the time of the year when numerous air and
waterborne diseases spread rapidly.

Blood Donation Drive at DIAL

Staff donating blood during the camp

The staff at L&Ts Delhi International Airport Project

The staff at E&GP OCs Cairn MPT project site (BarmerRajasthan) organized a blood donation camp in
association with Jodhpur Medical College on 16th October
2010. Over 31 staff enthusiastically donated blood and
supported this blood donation drive spearheaded by the
Project Manager and his team.

Kanyakumari Medical College lauds


L&Ts blood donation drive

L&Ts NPCIL project has been awarded by the


Kanyakumari Medical College, Nagercoil for having
donated over 267 units of blood in Kanyakumari
district in the year 2009.
ECC CONCORD Oct - Dec 2010

61

At an event held on 1st October 2010 in celebration of


National Voluntary Blood Donation Day, Mr. N. Suresh
Rajan, Minister for Tourism and Registration along with
Mr. Rajendra Ratnoo, District Collector presented the
award to Mr. R. Govindarajan, Project Manager NPCIL.
So far, the NPCIL project has received nine blood
donation awards from Kanyakumari Medical College
since 2006.

Old age home @ Ahmedabad renovated


As a part of L&Ts Corporate Social Initiative, the
Ahmedabad Regional office renovated Manilal
Tribhuvandas Matru Gruh, Ahmedabad, an old age home
that provides shelter to sixty aged women who have been
abandoned by their kith and kin.

the less privileged students in their education and also


added that special efforts are being taken in providing
infrastructure support for neighbouring schools so that
the children can get quality education.

Health camp at RSP, Rourkela


A two day health camp was organized at L&Ts
RSP Rourkela site on 18th and 19th November
2010.The workmen were screened for common
health issues as well as for advanced disorders

The home established in 1969, is situated on the


banks of the Sabarmati River in an area of 9000
square yard and it also runs a physiotherapy clinic
adjoining the home.

ECC supports Government Primary


School at Jadcherla
As part of L&Ts CSR efforts, the ECC Hyderabad
Regional office reached out to the students of the
Government Primary School at Jadcherla on 16th
November 2010.L&T distributed uniforms and school
bags to over forty children and also provided almirahs
and chairs to the school management towards
improving the schools infrastructure. Mr. D.V.V.S.K
Chowdary, Regional Manager HYRO who spearheaded
the event spoke about L&Ts involvement in supporting

62

ECC CONCORD Oct - Dec 2010

like respiratory, cardiovascular, nervous and


stomach related problems. The screening was
conducted by Dr. P.K. Bhutia M.D, Chest Physician,
National Safety Council, Orissa Chapter and his
team. Over 259 workmen engaged at the site
in Electrical projects benefitted from this health
camp.

L&T supports students at Jamshedpur


As part of L&Ts Corporate Social Initiative, L&Ts
Tata Steel Site, Jamshedpur, reached out to the
students of elementary schools on November
21, 2010. The event was organized to felicitate
Childrens Day. Mr. T Kumaresan, Cluster Head
Jamshedpur Cluster, MMH&W OC presided over

HIV /AIDS, STIs, Psycho sexual issues, Information


about referral services were covered during the
session.

AIDS awareness drive at MIAL

the function along with cluster and site staff. During


the event L&T distributed school kits (school bags
& water bottles) to students who attend evening
and night schools to complete their elementary
education. Around 265 students from across
16 centers benefitted from the initiative. The
programme was supported by Jharkhand Project
Education Council & Bal Mazdoor Mukti Seva
Sansthan. District Education Officer and Council
officials attended the programme and appreciated
the good work done by L&T in assisting the
students.

Aids awareness camps


The MMH&W OC conducted HIV & AIDS and
Health Awareness programme for workmen in
many Project sites across the country on 4th
December 2010. The programme was conducted
using skit performed by professionals, video
film and interaction with workmen.
The main objective of the initiative was to increase
the awareness level and improve the attitude,
behavior and practices of the construction workers
on issues related to health & hygiene. Basics of

On 1st December 2010, L&T staff at the MIAL site


organized an AIDS awareness programme for the
site workmen on event of World Aids Day. Over 5800
workmen at the site participated in this awareness
drive. EHS/IR representatives organized a lecture on
AIDS - dos and donts to create an awareness among
the workmen. Leaflets in Hindi and Marathi on HIV
transmission and prevention were distributed to the
workmen along with badges. Posters were also displayed
in prominent places. This programme not only helped
in generating awareness among the workmen but also
cleared many myths about the disease.

ECC CONCORD Oct - Dec 2010

63

28 volunteers from ECC help provide a roof for a family at Mangadu, Chennai
As a part L&Ts CSR activity, a team of 18 staff from Construction Division and 10
students from CSTI Manapakkam joined hands with Habitat for Humanity and WEEDS
on 7th January 2010 to construct the staircase slab as well as concrete the roof of a
380 sq.ft house at Mangadu in Chennai.
The owner of the house, Ms. Selvarani, could not complete the construction from the
money given to her through the Governments BSUP scheme. Hence, the NGOs granted
interest free loan and also welcomed volunteers to help complete the house. Therefore,
L&T staff volunteered to complete the house by concreting the roof by preparing concrete
with sand, cement, aggregate, water and manually mixing and laying the same.
The event was initiated by Ms. Judy Vinodhini, Mr. George Abraham, Mr. Nitin
Shenoy, Mr. Desigan and it was led by Mr. V S Ramana - Head for the CSI of Chennai.
Mr Pandian from CSTI supported this activity to very large extend. At the end of the day,
the satisfaction of constructing a home was multi fold to all the participants. The CSTI
trainees prided themselves in working on site and set an example for many villagers
who expressed their interest and inclination towards joining L&Ts Construction Skills
Training Institute.

The team that made a difference

64

ECC CONCORD Oct - Dec 2010

Making a difference on New Year

L&T staff during the rally

On 1st January 2011, a group of 50 L&T-ites from Chennai went forward and participated in a rally at Marina beach
organized by Isha Foundation for creating awareness on afforestation. While many were celebrating New Year with
friends and relatives, this team of 50 staff actively participated in creating awareness on planting trees for creating a
greener Chennai.
The rally was flagged off by the famous film director Mr. K.S. Ravikumar and more than 4000 people from various
walks of life including volunteers of Isha foundation participated enthusiastically. At the end of 3 km rally, tree saplings
were distributed, free of cost. Around 10000 saplings will soon be planted within city limits by the volunteers of ISHA
to conserve the environment.
This small step towards environmental conservation taken right at the beginning for the year 2011 will certainly pave
way to reduce the effects of global warming.

Health initiative for staff and


workmen at EWL, Kanchipuram
L&T - ECC Workshop, Kanchipuram organized an Annual
Refraction Eye Camp on 8th October 2010 for the staff
and workmen in association with Aravind Eye Hospital,
Pondicherry. Over 415 staff and workmen were screened
for visual defects and over 107 people were recommended
spectacles that were given at discounted rates. The
workmen greatly benefited from this programme where
they were given instant feedback.
ECC CONCORD Oct - Dec 2010

65

AWA R D S
CII-ITC Sustainability Awards 2010

Mr. M.V. Sathish Vice President & Head - Institutional & Commercial Buildings receiving the certificate from Mr. Pawan Kumar Bansal, Honble
Union Minister of Water Resources & Parliamentary Affairs

ECC won the Certificate of Commendation for


Significant Achievement as a part of the CII-ITC
Sustainability Excellence Awards 2010. L&T won
this award after a rigorous two-stage assessment
including a site visit, followed by scrutiny by
the Awards Jury. Nearly 68 companies were in
the fray; however L&T is the first Engineering &
Construction Company to receive this award.
58 independent assessors spent about 1000
hours for each entry company supported by a
13-member jury led by Mr. Suresh Prabhu, the
Former Union Minister.
Mr. M.V. Satish, Vice President & Head Institutional & Commercial Buildings BU, (B&F
OC) received the Certificate from Mr. Pawan

66

ECC CONCORD Oct - Dec 2010

Kumar Bansal, Union Minister for Water Resources


& Parliamentary Affairs, Government of India,
at the presentation ceremony as part of the 5th
Sustainability Summit: Asia 2010 held at The
Grand, New Delhi, on November 30, 2010. The
CII-ITC Sustainability Awards recognizes efforts
of companies that contribute to creation of social
and environmental capitals, thus going beyond
creating shareholders wealth. This award is
beginning to gain lot of credibility through large
participation from many companies.
For the fifth successive year, L&T has made it to
Forbes Asias Fabulous 50 list of Asia-Pacifics
publicly-traded companies with revenues or
market capitalization of at least US$5 billion.

L&T Ranks Among Top 10 in Carbon


Disclosure
Only Indian Engineering & Construction
Company in Leadership Index

HITEC City bags the Best IT Park Award


The HITEC City (Hyderabad Information Technology and
Engineering Consultancy City) developed by L&T Infocity
Limited has won the prestigious IT Park of the Year 2010
award.
Spread over a land area of 151 acres, HITEC City is the
largest Information Technology park in India, which offers
world class state-of-the-art IT infrastructure under one
roof to companies operating in the field of IT services, IT
enabled services, Telecom, Engineering Consultancy and
other related domains.
L&T received this recognition at the first edition of the
Property World Awards held at ITC Maratha Hotel,
Mumbai recently. The other nominees in this category
were DLF Cyber City, Gurgaon, Infosys campus Bangalore
and HCC 247 Software Park, Mumbai. L&T was chosen
for Property World Awards 2010 by a collegium of
over 60 industry leaders from the real estate developer
community, banking and finance industry, international
and domestic property consultants.

IPLOCA awards L&Ts Pipeline Project

L&Ts Sustainability team has another feather in its cap.


The UK based Carbon Disclosure Project (CDP) has ranked
L&T among the Top 10 companies in its annual survey
of Indian companies. Carbon disclosure plays a critical
part in determining the commitment of an organisation
to climate change challenges. CDP is a widely respected,
independent international organisation with the largest
database of corporate climate change information.
It assesses companies on their CDP disclosures and
management practices for understanding greenhouse
gas emissions including energy use. CDPs annual
survey, now in the fourth year, surveyed 200 top market
capitalisation companies of India.
L&T is the only company in the engineering and
construction segment to have made it to the list. CDP
Report 2010 was released on October 28, 2010
in India, and introduced the Carbon Disclosure
Leadership Index. The Report provides a perspective
on how Indian companies are driving innovation and
taking action to embrace a low carbon future.

L&T is a runner-up for the 2009 International Pipeline


& Offshore Contractors Association (IPLOCA) Health
and Safety Award (sponsored by Chevron). IPLOCA has
awarded L&Ts Barmer (Rajasthan) Salaya (Gujarat)
Pipeline Project for its commitment towards health and
safety practice and performance systems at site. The
project has achieved six million safe man hours.

From left to right: Mr. C. Chokkalingam, General Manager, HCP,


Mr. Chitta Ranjan Sahoo, Project Manager, Barmer-Salaya Pipeline
Project and Mr. Krishna Nirmalya Sen, In-charge, HSE, HCP & TPPC with
the IPLOCA Health & Safety Award.

ECC CONCORD Oct - Dec 2010

67

Safety Awards 2010 from the Institution of Engineers India


The Institution of Engineers India (IEI) awarded Mr. K.N. Sen, Head HSE, HCP & TPPC for his outstanding
contribution to Safety in the Engineering sector, at the 25th Indian Engineering Congress held on 17th
December 2010.
Mr. K.N. Sen received this prestigious award from
Shri. S.Sharma, Minister for Fisheries & Registration,
Govt. of Kerala during the inaugural session of the
Indian Engineering Congress at Kochi, Kerala. The
Safety and Quality Awards have been instituted by
the Safety and Quality Forum (SQF) of IEI with a view
to encourage professionals from manufacturing and
service sectors to strive for excellence. This year, the
award has been presented to Mr. K.N. Sen recognizing
his achievements in this field and thereby setting an
example for others.
Mr. K. N. Sen receiving the award from Shri. S. Sharma

L&T wins IAD Awards 2009


Best Builder & Best Structural Engineer

Integrated Management System


(IMS) Accreditation for Electrical
Construction (Domestic)
The Electrical Construction Business (Domestic)
received accreditation for its Integrated
Management System (IMS) by qualifying
for the following International Standard
Certifications.

The IAD Awards instituted by Sun Designs & Interiors Pvt.


Ltd. for recognizing novel and laudable work in the field of
Architecture, Interiors, Engineering, Construction & Town
Planning, in association with Professionals Club India
which constitutes members from Industry of Infrastructure,
Information Technology, and Legal & Accounting etc.

yy

ISO14001:2004
System)

yy

OHSAS 18001:2007 (Occupational Health &


Safety Assessment Series)

yy

ISO 9001:2008 (Quality Management System)

yy

68

Best Builder (Commercial) for the project TCS


Techno Park phase-1, Chennai
Best Structural Engineer for Mr. S. Balaji for the
Jindal Law School Project

ECC CONCORD Oct - Dec 2010

Management

This Management System Certification will add


value to the Electrical Construction operations
by:
yy

Systematically improving operations to International


standards

yy

Providing external recognition for systems.

yy

Adding credential to the organization and help in


securing more orders

At the IAD awards 2009 held on 24th October 2010,


Larsen & Toubro has bagged two awards:
yy

(Environment

Delhi Airport Wins British


Construction Industry Award

L&T wins Excellence in construction


of high rise building

CTS Kolkata
Mr. M.P. Naidu along with the award

The Delhi International Airport has won one of the most


rigorously judged and coveted international awards
in the construction industry the British Construction
Industry award for 2010. Already a recipient of high
praise from different quarters for its scale, state-of-theart features and for the speed in which it was built, the
British Construction award, is further affirmation that
the Delhi Airport can join the ranks of the finest airports
in the world.
In the case of the Delhi Airport, the entry
was submitted by the principal architect,
Mott MacDonald, UK. The construction of the
airport regarded as an icon of infrastructure
represented the successful outcome of a team
effort involving GMR; L&T, the principal contractor;
the commissioning authority, Mott MacDonald; and
HOK, the principal architect.
As part of the citation, the jury remarked: The delivery
of the New Delhi Airport is a project of unprecedented
scale in India. The new 4.4 km runway and 35 million
passenger capacity terminal were completed on time in
38 months.
Mr. M.P. Naidu, Vice President & Project Director, DIALProject, L&T, received the British Construction Industry
award on behalf of L&T.

The ACCE (Association of Consulting Civil Engineers


India) Billimoria awards instituted by the B.E. Billimoria&
Co. Ltd, Mumbai, are presented every year, to give
recognition to Civil engineering consultants, planners,
designers, students etc. for their outstanding contribution
to the construction industry. The ACCE awards are
presented in various categories for innovative design,
excellence in the field of construction and significant
contribution to Civil engineering consultancy. This year
the Excellence in Construction of High rise building
was awarded to Cognizant, Kolkata in an awards
function held in Hyderabad on 22nd October 2010.

NABL accreditation for L&T


Construction Research & Testing
Centre
L&T Construction Research & Testing Centre (LTCRTC),
Chennai, has been accredited by NABL (National
Accreditation Board for Testing and Calibration
Laboratories) for the third consecutive time in the field
of Mechanical and Chemical Testing. The accreditation
granted to LTCRTC is valid up to 2012 and it covers a total
of 125tests on construction materials like reinforcement,
pre-stressing strands, cement, fine &coarse aggregate,
brick, fresh & hardened concrete, concrete blocks,
timber, bitumen & pavement material, water, chemical
admixture, soil & rock. LTCRTC is the first testing centre
of a construction company in India accredited by NABL
since 2006 for a wide scope of testing on construction
materials.

ECC CONCORD Oct - Dec 2010

69

Gulf Projects (E & GP-OC) bags Best presented Accounts Award for 2009-10

Mr. V. Gopinath receiving the award from Mr. B. Ramakrishna in the presence of Mr. Y. M Deosthalee

Gulf Projects (E&GP) Operating Company has


bagged the Best presented Accounts Award 200910, for the second consecutive year. Considered as
one of the most prestigious in-house awards, the
evaluation measures the value delivered to business
through proactive accounting systems and processes.
For the second time in succession, Mr. V. Gopinath

(VG), Head - (Finance, Accounts and Admin.), Gulf


Projects OC has received this award from Mr. Y.M.
Deosthalee, Chief Financial Officer, L&T &Mr. B.
Ramakrishna, Vice President & Head Finance
Accounts & Administration, ECC Division at the
32nd Accountants Conference held at Goa on 7th
December, 2010.

Corporate Communications Team Bags 10 Awards


At the 50th Annual Awards Competition organised
by the Association of Business Communicators of
India (ABCI), the Corporate Communications team
bagged 10 awards. The awards were presented at a
glittering presentation ceremony held in Mumbai on
November 11, 2010. The annual awards contest of
ABCI this year was a special one. It was the fiftieth
annual awards function of ABCI. The association
had received a record number of 900 entries from
around 150 companies this year.
CCD Chennai team had won a total of four awards for
photography, L&T Panchangam wall calendar, multimedia presentation on CSTI in Gujarati and for the
Sustainability issue of ECC Concord.

70

ECC CONCORD Oct - Dec 2010

Mr. A.M. Naik Wins Golden Peacock Award for Lifetime Achievement in
Business Leadership

Mr. A.M. Naik receiving the Golden Peacock Award from Justice P. N. Bhagwati (centre). Mr. Madhav Mehra of IoD is on the left.

Mr.A. M. Naik, has been conferred the Golden Peacock Award for Lifetime Achievement in Business Leadership.
Mr. Naik received the award from the former Chief Justice of India, Justice P. N. Bhagwati, at a specially organised
Awards Nite on November 12, 2010 in New Delhi.

Mr. A.M. Naik Wins CNBCs Asia


Business Leader Award
Yet another international dimension was added to L&Ts
Chairman & Managing Director, Mr. A.M. Naiks array of
awards with the presentation of the prestigious Asia Business
Leader Award for 2010 by CNBC Asia. The award from the
internationally reputed TV channel was presented to him at a
glittering ceremony in Singapore on 25th November 2010.
The ceremony was hosted by CNBCs award-winning
anchor, Ms. Maria Bartiromo, and was broadcast
live globally on CNBC Asia, CNBC Europe
and CNBC US.
The Asia Business Leader Awards (ABLA) is regarded as
the most prestigious business leadership award in the
Asian continent. It recognises the business leader who
makes his or her vision a reality for the company he/she
heads driving growth, success and profitability. Qualities
including innovation, community service, management

Mr. A.M. Naik with the award

skills and the leaders ability to formulate strategies and


capitalise on key trends are the key judging criteria.

ECC CONCORD Oct - Dec 2010

71

ECC bags Top Honours at Construction World Awards

Mr. S.N Subrahmanyan Sr. V.P. Buildings & Infrastructure receiving the award from Mr. Sankaranarayanan, Governor of Maharashtra

L&T secured top honours at the 8thConstruction World Annual Awards 2010 in Mumbai
on 19thOctober 2010.L&T featured as one of Indias Most Admired Companies in
the annual contest organised by Construction World, a leading trade journal. L&T was
in the limelight again, being ranked as the Largest & Most Profitable Construction
Company.
As Indias leading Construction Company, L&T has been consistently featured at the top
of the rankings. This is the eight year in succession that L&T has secured the award.
Mr. S.N Subrahmanyan- Senior Vice President, Buildings & Infrastructure, received the
trophies and certificates from Mr. K Sankaranarayan, Governor of Maharashtra, amidst
a large gathering of leading players from the infrastructure and construction sector.
Construction World Annual Awards is the flagship event under the CW (the No. 1
construction business magazine in India since last 14 years) umbrella. It is the most
prestigious set of awards which recognizes and facilitates the achievers in the Construction
and Allied Industry

72

ECC CONCORD Oct - Dec 2010

L&T on Forbes Asias Fabulous 50 List Fifth Time in a Row

From left to right: Mr. Tanawat Wansom, President - MCOT Public Company Limited, Mr. Christopher Forbes, Vice Chairman of Forbes,
Mr. S.N. Subrahmanyan, Sr. V.P Buildings and Infrastructure, Mr. Surapon Nitikraipot, Chairman - MCOT Public Company Limited,
Mr. Tevin Vongvanich, CFO - PTT Public Company Limited

L&T is the only engineering and construction company in India to feature in this list. This is Forbes Asias sixth annual
Fabulous 50 list. As many as 16 Indian companies were listed this year as against 13 last year. Forbes Asia selected the
winners based on long-term profitability, sales and earnings growth, stock price appreciation and projected earnings
for every company in the region. Mr. S.N. Subrahmanyan, Senior Vice President (Buildings & Infrastructure), L&T
received the award at Bangkok on December 8, 2010.

Years on List
4
Industry
Construction

engineering services
Country
India
Size
Market Value
$23.7bil
Sales
$9.8bil
Valuation
Forward P/E
26
Price to Sales
2.5
Dividend Yield
0.7%
Performance
5 yr avg ROC1
17%
EPS Growth Est2
22%

The five-time Fab 50 honoree isnt slowing down - revenue grew


24% and net profits jumped 61%, to reach $1.2 billion. The
Mumbai companys bulging order book stands at $22.3 billion,
up 62% in a year. Founded in 1938 by two Danish engineers, it
boasts an uninterrupted history of paying dividends back to 1946.
Challenges include rising raw-material costs, sluggish growth in the
Middle East and tougher competition from mid-size construction
outfits. Its now building a shipyard in South India for the repair of
naval ships, submarines and commercial vessels.
More details on : http://www.forbes.com/lists/2010/37/fab-5010_Larsen-Toubro_ZUM5.html

ECC CONCORD Oct - Dec 2010

73

Mr. A.M. Naik Honoured at CNBC TV18s India Business Leader Awards

CNBC Asias Outstanding Business Leader of the Year, Mr. A.M. Naik, CMD, received the award from Mr.Pranab Mukherjee.
Also seen (from left to right) are M/s Joseph Massey, Udayan Mukherjee, Raghav Bahl, Senthil Chengalavarayan and
Sanjay Pugalia.

A little over a week after L&Ts Chairman & Managing Director, Mr. A.M. Naik received
the Asia Business Leader Award from CNBC Asia in Singapore, CNBC TV18 India
honoured him with the CNBC Asia - Outstanding Business Leader Award for 2010.
The glittering awards ceremony, held in Mumbai on Saturday, December 11, 2010, was
presided over by the Union Finance Minister, Mr. Pranab Mukherjee.
CNBCs India Business Leader Award is recognised by the Indian corporate sector
as one of the most prestigious awards. It acknowledges the strategic leadership and
direction that the award-winning business leader has given to the organisation that
he heads, and the visible and vibrant impact he has made on industrys prospects for
growth. Every award winner is a visionary who has set an inspirational example for
peers in the industry.
CNBC -TV 18 stated that the awards sought to honour business legends who
have made India proud. Few leaders have been so strongly committed to
national values and interests as Mr. Naik. The awards also celebrate values
that exemplify the core pillars of leadership such as strength, innovation,
ingenuity and foresight.

74

ECC CONCORD Oct - Dec 2010

L&T Wins ICSI National Award for Excellence in Corporate Governance

Mr. Y. M. Deosthalee (left) receiving the ICSI National Award from Mr.Pranab Mukherjee. Mr. N. Hariharan is at right

Appreciating L&Ts good corporate governance practices, the Institute of Company Secretaries of
India (ICSI) has conferred the National Award for Excellence in Corporate Governance on L&T.
Mr. Y.M. Deosthalee, CFO, L&T, received the award from Mr. Pranab Mukherjee, Union Finance
Minister, at a glittering function in New Delhi on December 16, 2010.
The ICSI jury, headed by Justice R.C. Lahoti, former Chief Justice of India, comprised a galaxy of
eminent personalities from government bodies, academicians and senior executives of Fortune
500 companies. The parameters of selection included: Board independence and governance,
Board systems and procedures, Transparency and disclosure compliances, Consistent shareholder
value enhancement, Stakeholders value enhancement, Corporate Social Responsibility, and
Sustainable relationship building with major stakeholders in the corporate family.
The Award also took into account the feedback from Independent Directors and major regulatory
bodies like MCA, SEBI, ROCs, Stock Exchanges, Provident Fund Commissioners and Income Tax
Authorities to confirm the credentials of the company. The process also analysed the credentials
of the company through reports about the company in press, electronic media, web sites, etc.
Apart from the award to the corporate, L&Ts Company Secretary, Mr. N. Hariharan, was also
felicitated by ICSI for excellence in corporate governance.

ECC CONCORD Oct - Dec 2010

75

L&T Wins The Economic Times Company of


the Year Award - 2010

Mr. A. M. Naik receiving the award from Mr. Pranab Mukherjee

Union Finance Minister, Mr. Pranab Mukherjee


presented L&T, The Economic Times Company
of the Year Award 2010 at a function in
Mumbai attended by the elite of business and
industry, leading political figures including Mr.
Jairam Ramesh, Environment Minister, Mr. Kapil
Sibal, HRD & Telecom Minister, Mr. Salman
Kurshid, Corporate Affairs Minister, Mr. Prithviraj
Chavan, Chief Minister of Maharashtra, and
other celebrities. The award was received on
behalf of L&T by Mr. A.M. Naik, Chairman &
Managing Director.

Indian industry. L&T was the overwhelming choice of


the jury due to its achievements on several fronts.

The Economic Times is Indias largest selling business


daily, recognised internationally for its reach and
coverage, and the awards that the newspaper
presents annually are among the most coveted in

With this award, L&T has been voted Company


of the Year by Indias two most reputed business
dailies. It had won the Business Standard Company
of the Year award in 2010.

The Award Jury had cited that L&T has been


involved in almost all of Indias prestigious
engineering creations, including roads, power
plants, buildings, bridges, ports and nuclear
reactors. Describing L&T as the bellwether of
Indias engineering sector , The Economic Times
said the company has just completed a fiveyear programme of restructuring its operations
and is well poised to take advantage of the
opportunities that lie ahead.

Printed by Lokavani Southern Printers Pvt. Ltd., Chennai. Edited by Mr. V.S. Ramana for Larsen & Toubro Limited ECC
Division, from ECC-HQ, Manapakkam, Chennai 600089. The views expressed in this magazine are not necessarily
those of the management of Larsen & Toubro. The contents of this magazine should not be reproduced without the
written consent of the editor. Not for sale - only for free circulation to employees of L&T group and subscribers.

You might also like