Professional Documents
Culture Documents
14
( Time & Work)
1.A and B together can do a piece of work in 12 days ,while B alone can finish it in 30 days. A alone can
finish the work in
1)15days
2)18 days
3)20 days
4)25 days
5) None of these
Solution : (3).
(A+B) s 1 days work = 1/12
Bs 1 days work = 1/30
Therefore As 1 dayss work = 1/12 1/30
= 5-2 / 60 = 1/20
2.A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In
what time can A alone do it?
1)80 days
2) 100 days
3)120 days
4)150 days
Solution : (3).
( A+B)s 1 dayss work = 1/72
( B+C)s 1 days work = 1/120
(A+C)s 1 days work = 1/90
2((A+B+C)s 1 days work
= 1/72 + 1/120 + 1/90
Therefore ( A+B+C)s 1 days work
= (5+3+4) / (360 x 2) = (12/360 x 2 ) = 1/60
Therefore As 1 dayss work = (A+B+C)s 1 days work ( B+C)s 1 days work
= 1/60 1/120 = 2 1 /120 = 1/120
5)None of these
3.Acan do a piece of work in x days and B can do the same work 3x days. To finish the work together
they take 12 days. What is the value of x ?
1)8
2)10
3)12
4)16
5)None of these
Solution : (4).
As 1 days work A = 1/x
Bs 1 days work B = 1/3x
( A+B)s 1 days work
= 1/x + 1/3x = 4/3x
And given one day work of both A and B = 1/12
= 4/3x = 1/12 = 3x = 48 = x = 16
4.A can do a piece of work in 10 days and B in 20 days . They begin together but A leaves 2 days before
the completion of the work. The whole work will be done in
1)8 days
2) 7 2/3
3)7 days
4) 6 days
5)None of these
Solution : (1).
Here, a = 10 , b = 20 and x = 2
Therefore required time = ( a + x) *b / (a + b)
= (10 + 2) *20 / 30 = 8 days
5.A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of
them worked together for 8 days and then A left. The number of days B will take to complete the
remaining job is
1)16
2)32
3)64
4)128
Solution : (3).
Let B will take x days to complete the remaining job .
5)None of these