Professional Documents
Culture Documents
Cost Criteria For Trenchless
Cost Criteria For Trenchless
INTRODUCTION
This Technical Memorandum presents the methodology used to develop estimated costs for project shed areas
proposed in the Sacramento Area Sewer District System Capacity Plan 2010. The estimated costs may then be
incorporated into SASDs rate and fee study.
- Final.Docx
Page 1 of 18
November 29, 2011
Description
Unit Cost
Range
Section
Reference
Baseline Construction
Open Cut Gravity Sewer
$160 to
$680/lf
3.1.1
$140 to
$430/lf
3.1.2
$305 to
$1,700/lf
3.1.3
Geotechnical Factors
Additional Dewater
$45 to $60/lf
3.2.1
$30 to $710/lf
3.2.2
Developed Areas
100% of
baseline cost
Undeveloped Areas
20% of
baseline cost
100% of
baseline cost
3.2.3
$45/lf
3.3
Congested Traffic/Utility
Corridor
15% of
baseline cost
3.4.1
25% of
baseline cost
3.4.2
Cobble Areas
3.2.3
Traffic Control
Additional Traffic Control
Productivity Factors
- Final.Docx
Page 2 of 18
November 29, 2011
Description
Unit Cost
Range
Section
Reference
Surface Restoration
Pavement Restoration
$100/lf
3.5.1
Landscape Restoration
$3.00/sf
3.5.2
Revegetation
$0.25/sf
3.5.2
Creek Restoration
$12/sf
3.5.2
Junction Structures
$25,000 to
$850,000 per
structure
3.6.1
Pump Stations
$0.5 to $6.1M
3.6.2
Sewer Structures
Mobilization/Demobilization
% of subtotal
5%
3.7
Contingencies
30%
3.8
Easement Acquisition
Acquisition Cost
$7,000 per
parcel
3.9
Easements in Newly
Constructed Development
No Cost to
SASD
3.9
Temporary Construction
Easements
80 feet width
$0.80/sf
3.9
Permanent Easement
20 feet width
$4.00/sf
3.9
25%
3.10
- Final.Docx
Page 3 of 18
November 29, 2011
- Final.Docx
Page 4 of 18
November 29, 2011
16 to 20
feet depth
20 to 24
feet depth
24 to 28
feet depth
160
185
______
______
10
190
210
______
______
12
220
235
260
285
15
255
275
300
325
18
285
310
340
370
21
330
355
385
415
24
365
390
420
450
27
395
420
455
490
30
430
460
495
530
33
465
495
530
565
36
495
530
570
610
530
565
605
645
42
565
600
640
680
- Final.Docx
Page 5 of 18
November 29, 2011
10 to 16 Feet Deep
Cost ($/lf)
140
200
150
205
160
210
10
170
225
12
180
240
15
245
325
18
275
355
21
300
380
24
355
430
- Final.Docx
Page 6 of 18
November 29, 2011
Microtunneling mobilization/demobilization, bore holes less than 24-inches will cost $110,000; bore
holes 24 to 48-inches will cost $180,000; and bore holes 48 to 72-inches will cost $260,000.
3.1.3.1 Trenchless Construction Cost
The recommended unit costs for trenchless pipe construction are the following:
Table 4 Trenchless Pipe Construction Unit Cost
Pipe Size
(in)
Direct Jack
(No Casing)
Casing Required
Cobble Area
Microtunneling*
($/lf)
Casing Size
(in)
Microtunneling*
($/lf)
Casing Size
(in)
Pipe Ramming
($/lf)
820
36
1025
615
37
305
10
820
36
1035
625
40
345
12
820
36
1040
630
42
380
15
845
36
1060
655
47
460
18
845
42
1025
670
55
505
21
895
43
1030
720
56
510
24
895
49
1060
795
61
545
27
980
51
1125
845
63
615
30
980
56
1155
890
68
660
33
980
59
1240
945
71
720
36
980
64
1335
1040
76
820
39
980
68
1470
1105
80
890
42
980
72
1700
1165
84
960
* Unit pricing for microtunneling does not include mobilization and demobilization.
Use the following for microtunnel mobilization and demobilization cost:
Bore holes less than 24-inches $110,000,
Bore holes 24 to 48-inches $180,000,
Bore holes greater than 48-inches $260,000.
- Final.Docx
Page 7 of 18
November 29, 2011
Microtunneling
8 to 10-inch
1,200
12 to 24-inch
700
27 to 33-inch
400
150
Pipe Ramming
All Diameters
300
Pit Cost
16 feet or less
Jacking Pit
$80,000
Receiving Pit
$25,000
$115,000
Receiving Pit
$40,000
- Final.Docx
Page 8 of 18
November 29, 2011
For the purpose of this System Capacity Plan, dewatering cost from Table 7 will be applied in areas of the County
with known high groundwater as shown in Figure 2.
200 GPD/Acre
$45/LF of pipe
500 GPD/Acre
$60/LF of pipe
- Final.Docx
Page 9 of 18
November 29, 2011
groundwater. For pipeline constructed in areas without high groundwater, it is assumed that hydraulic shores or
trench boxes will be used. This cost is included in the baseline pipe construction cost.
The recommended sheeting and shoring costs for the three conditions and various pipeline depths are
presented in Table 8. The cost of the solid shoring ranges from $1 to $3 per square foot. The cost of the sheet
piles ranges from $20 to $40 per square foot. These costs have been used to also assume that any excavation
deeper than 8 feet in areas of high groundwater area of the County, where the subsurface profile typically
consists of 10 feet of clay over clean sands. Therefore, additional dewatering costs will also be required for open
cut construction in areas of high groundwater (except where sheet piles are used), as indicated in Table 8.
Table 8 Shoring and Dewater Unit Cost for Various Groundwater Conditions
Depth to
Invert (ft)
8 to 16
16 to 20
20 to 24
24 to 28
No Groundwater
High Groundwater
Undeveloped Area
Baseline
$30/LF + dewatering
$75/LF + dewatering
$60/LF + dewatering
$110/LF + dewatering
$90/LF + dewatering
Partially laid back trench with
trench box and dewatering wells.
High Groundwater
Developed Area
Shoring: $135/LF
$135/LF + dewatering
Interlocking sheet piles
$710/LF
$120/LF + dewatering
- Final.Docx
Page 10 of 18
November 29, 2011
For the System Capacity Plan, use the following as construction factors:
Cobble Construction Factor:
Developed Areas: 100% of Baseline Pipe Construction Costs
Undeveloped Areas: 20% of Baseline Pipe Construction Costs
Note: Areas within the cobble area but south of Elder Creek Road, reduce the cobble construction factor
by 50%.
Hard Rock Construction Factor:
100% of Baseline Pipe Construction Costs
- Final.Docx
Page 11 of 18
November 29, 2011
- Final.Docx
Page 12 of 18
November 29, 2011
- Final.Docx
Page 13 of 18
November 29, 2011
Cost
$25,000
$50,000
$165,000
$230,000
$850,000
- Final.Docx
Page 14 of 18
November 29, 2011
Medium Head
60 to 120 feet
High Head
Greater than 120 feet
$560,000
$680,000
$850,000
1 MGD to 2 MGD
$810,000
$980,000
$1,200,000
2 MGD to 3 MGD
$1,200,000
$1,400,000
$1,800,000
3 MGD to 4 MGD
$1,700,000
$2,000,000
$2,400,000
4 MGD to 5 MGD
$2,100,000
$2,400,000
$2,900,000
5 MGD to 6 MGD
$2,700,000
$3,000,000
$3,700,000
6 MGD to 7 MGD
$3,100,000
$3,500,000
$4,200,000
7 MGD to 8 MGD
$3,800,000
$4,300,000
$5,100,000
8 MGD to 9 MGD
$4,200,000
$4,700,000
$5,600,000
9 MGD to 10 MGD
$4,700,000
$5,100,000
$6,100,000
Often times, pump stations are upgraded to increase the pumping and storing capacity. For increasing the
capacity of an existing station, use the following cost factors:
Table 11 Rehab Pump Station Cost Factor
Pump Station Capacity Increase
25%
0.5 to 2 MGD
50%
2 MGD to 4 MGD
75%
100%
- Final.Docx
Page 15 of 18
November 29, 2011
3.8 Contingencies
This contingency is used to adjust the Estimated Construction Cost Subtotal such that the total cost will account
for unforeseen economic variables that are difficult to quantify or cover portions of work that were not
estimated. The percentage used for an overall project will vary depending upon level of effort at various stages
of the project. The percentage used is adjusted based upon detailed or lack of detailed geotechnical, utility, and
other project details and information. Due to a lack of detailed information during the planning phase, a
contingency factor of 30 percent is considered appropriate for planning level costs.
Contingencies for Unknown Conditions: 30% of the Estimated Construction Cost Subtotal.
- Final.Docx
Page 16 of 18
November 29, 2011
- Final.Docx
Page 17 of 18
November 29, 2011
4. REFERENCES
Tabula Version 3.1.2 King County, Washington, November 10, 2010
CSD-1 Master Plan 2000, Technical Memorandum No. 8B, August 1, 2000
CSD-1 Master Plan 2006, Master Plan TM No. 8B - Cost Research Results, February 23, 2006
SASD Standards and Specifications, June 22, 2011, Version 1.0
County of Sacramento Construction Standard Specification, January 2008
SASD New Construction Bid Summary 2000 to 2010
2010 RSMeans Heavy Construction Cost Data, 24th Annual Edition
Ebidboard.com for public agency construction bids from 2008 to 2010
Engineering News-Record, Construction Cost Index
SASD Sewer Ordinance, April 8, 2011.
Sacramento County Assessors Office Commercial and Land Sales for 2010
Interceptor Sequencing Study
- Final.Docx
Page 18 of 18
November 29, 2011
COSTAPPENDIX
ENRCONSTRUCTIONCOSTINDEX
Assumption:
AdjustcosttoJanuary2011dollarsusingEngineeringNewsRecordConstructionCostIndex(ENRCCI)
Outofthe20citiesENRproducescostindicesfor,SanFranciscoisthecityclosesttoSacramento.
However,SacramentocostsaretypicallylowerthankSanFrancisco'scost.Thereforetodeterminethe
ENRCCIforSacramento,taketheaverageENRCCIofSanFranciscoandthe20citiesaverage.
January2011ENRCCI =averageofSanFranciscoENRCCI(10116)and20CitiesENRCCI(8938)
=9827
Year
2010
2009
2008
2007
2006
2005
2004
SanFanciscoCCI
9896
9738
9363
9096
8618
8309
8228
20CitiesAverageCCI
8802
8570
8310
7966
7751
7446
7115
AverageCCI
9350
9150
8840
8530
8180
7880
7670
2011CostMarkUpFactor
1.02
1.04
1.08
1.12
1.16
1.21
1.24
GRAVITYPIPELINECOST
CostingRange
Year Description
Project
2010
LowerSilverCreekFloodProtection
andCreekRestorationProject
6inchVCP Interstate680toMossPointDrive
(Reaches4,5,&6A)
2010
8inchVCP
2007
8inchVCP ParkeBridgeTrunkSewer
SacramentoHousingand
8inchVCP
RedevelopmentAgency
LagunaRidgeWhitelockParkway
8inchVCP
Segment1
LagunaRidgeWhitelockParkway
8inchVCP
Segment2
OliveAvenueSewerTrunkExtension
8inchVCP
2006
2006
2006
2006
2006
2005
2010
2010
FranklinCrossingMajorRoadsPhase1
8inchVCP NVSPhaseA1Infrastructure
8
inchVCP LagunaRidge(NorthShedC)
8inchVCP
GravitySewerInstallationandSewer
LiftStationDemolitionatOceanhill
8inchVCP LanefromOceanhillLanetoBeach
BoulevardatAdamsAvenue
8inchVCP
2007 8inchVCP
2007 10inchVCP
2006 12inchVCP
2006 12inchVCP
2006 12inchVCP
2010 12inchVCP
2010 15inchVCP
2008 15inchVCP
2006 15inchVCP
CastroValleySanitaryTrunkSewer
Project
ElkGroveMajorRoads
ElkGroveMajorRoads
LagunaRidgeWhitelockParkway
Segment1
LagunaRidgeWhitelockParkway
Segment2
NVSPhaseA1Infrastructure
LowerSilverCreekFloodProtection
andCreekRestorationProject
Interstate680toMossPointDrive
(Reaches4,5,&6A)
FranklinCrossingMajorRoadsPhase1
LagunaRidgeBrucevilleRoadPhaseII
OliveAvenueSewerTrunkExtension
Weighted
150% Average
Adjusted2011
Cost(ENRCCI
9527)
ConstructionBid
Jurisdiction
Length
Unit
Median
SantaClaraValley
WaterDistrict
405
LF
$145
$73
$218
$158
$162
$145
$130
$200
CityofElkGrove
636
LF
$69
$34
$103
$65
$66
$58
$70
$67
CityofElkGrove
50%
$112
124
LF
$160
$80
$240
$155
$174
$150
$116
$375
$194
$160
1890
LF
$125
$63
$188
$126
$146
$125
$225
$125
$110
$145
CityofElkGrove
254
LF
$166
$83
$249
$166
$193
$166
CityofElkGrove
1787
LF
$145
$73
$218
$145
$168
$145
CountyofSacramento
274
LF
$275
$138
$413
$306
$354
$275
$336
$93
Sacramento
Sacramento
192
1730
LF
LF
$290
$135
$145
$68
$435
$203
$247
$130
$287
$157
$150
$84
$302
$130
$290
$165
$140
CityofHuntington
Beach
335
LF
$210
$105
$315
$206
$210
$175
$210
$120
$310
$215
CountyofAlameda
254
LF
$200
$100
$300
$187
$191
$130
$140
$260
$131
CityofElkGrove
CityofElkGrove
5726
1021
LF
LF
$50
$62
$25
$31
$75
$93
$50
$65
$56
$73
$48
$55
$46
$52
$50
$54
$57
$62
$48
$54
CityofElkGrove
835
LF
$195
$98
$293
$195
$226
$195
CityofElkGrove
1584
LF
$170
$85
$255
$170
$197
$170
Sacramento
269
LF
$250
$125
$375
$249
$289
$166
$331
$250
SantaClaraValley
WaterDistrict
290
LF
$180
$90
$270
$193
$197
$150
$180
$250
CityofElkGrove
1143
LF
$91
$46
$137
$87
$89
$75
$92
$90
CityofElkGrove
1254
LF
$96
$48
$144
$95
$103
$145
$94
$96
CountyofSacramento
521
LF
$190
$95
$285
$168
$194
$190
$190
$123
CityofElkGrove
Sacramento
649
557
LF
LF
$170
$165
$85
$83
$255
$248
$170
$156
$197
$189
$170
$115
$170
$180
$92
$160
$55
$63
CostingRange
Year Description
2006 15inchVCP
Project
AerojetInterceptor1B
Jurisdiction
Length
Unit
Median
50%
Weighted
150% Average
Adjusted2011
Cost(ENRCCI
9527)
ConstructionBid
CountyofSacramento
106
LF
$358
$179
$536
$346
$402
$255
$330
$415
$385
4048
LF
$193
$96
$289
$190
$229
$138
$195
$190
$235
2005 24inchVCP
NatomasPhase2
CastroValleySanitaryTrunkSewer
Project
CastroValleySanitaryTrunkSewer
2010 24inchVCP
Project
2009 24inchVCP LakeMurrayTrunkSewer
2005 27inchVCP LagunaRidge(NorthShedC)
AerojetInterceptor1B
2006 27inchVCP
2010 24inchVCP
2691
LF
$200
$100
$300
$212
$216
$200
$180
$200
$252
2549
LF
$147
$74
$221
$132
$138
$92
$120
$160
$150
$92
1340
LF
$175
$88
$263
$164
$167
$121
$140
$150
$183
2075
LF
$185
$93
$278
$184
$188
$134
$162
$185
$173
1191
4631
LF
LF
$225
$279
$113
$139
$338
$418
$225
$263
$273
$318
$181
$209
$250
$286
$200
$277
$270
$280
2904
LF
$391
$196
$587
$393
$476
$391
$348
$440
CountyofSacramento
1058
LF
$600
$300
$900
$526
$636
$451 $1,100
$600
CountyofAlameda
1161
LF
$300
$150
$450
$299
$305
$320
$260
$240
$389
CountyofAlameda
2265
LF
$251
$126
$377
$267
$272
$250
$260
$250
$263
CityofSanDiego
Sacramento
1163
1130
LF
LF
$200
$343
$100
$171
$300
$514
$197
$320
$204
$387
$167
$224
$200
$335
$190
$350
$225
$370
CountyofSacramento
201
LF
$438
$219
$656
$428
$496
$425
$375
$450
$460
Sacramento
CityofSanDiego
Sacramento
1929
3668
222
LF
LF
LF
$290
$247
$410
$145
$124
$205
$435
$371
$615
$292
$234
$390
$338
$244
$472
$303
$152
$229
$282
$250
$450
$290
$205
$370
$240
$510
2940
LF
$705
$353 $1,058
$693
$804
$720
$640
$535
$705
$867
910
LF
$500
$250
$750
$465
$540
$830
$500
$456
$440
$867
705
LF
$565
$283
$848
$493
$571
$930
$565
$473
$440
$867
Sacramento
6123
LF
$325
$163
$488
$353
$410
$425
$325
$310
CountyofSacramento
2677
LF
$453
$226
$679
$483
$560
$415
$400
$490
$625
PipeCostvsPipeDiameter
$1,000
PipeCost
$800
$600
$400
Series1
$200
Linear(Series1)
$0
0
10
15
20
25
30
35
40
y=14.45x+25.07
R=0.538
PipeDiameter(in)
MANHOLECOSTPERLINEARFOOT
Manholes
48inchManhole<16feetdeepPipe821
48inchManhole>16feetdeepPipe1221
60inchManhole<16feetdeepPipe24<
60inchManhole>16feetdeepPipe24<
72inchManhole>16feetdeep
AverageCost
7500
13500
8000
16000
19000
Spacing400 Spacing500
19
15
N/A
27
N/A
16
N/A
32
N/A
38
CheckOkay
VCPGRAVITYPIPELINECOST
PipeSize
Cost
6
111.77
8
140.67
10
169.57
12
198.47
15
241.82
18
285.17
21
328.52
24
371.87
27
415.22
30
458.57
33
501.92
36
545.27
Depth
8to16
8to16
8to16
8to16
8to16
16to20
16to20
16to20
16to20
20to24
20to24
20to24
USETHISFORGRAVITYPIPELINECOST
PipeSize
8'to16'
16'to20'
VCP6
135
160
VCP8
160
185
VCP10
190
210
VCP12
220
235
VCP15
255
275
VCP18
285
310
VCP21
330
355
VCP24
365
390
VCP27
395
420
VCP30
430
460
VCP33
465
495
VCP36
495
530
RCP39
530
565
RCP42
565
600
8'to16'
$131
$160
$189
$213
$257
16'to20'
20'to24'
24'to28'
$312
$356
$404
$447
$491
$534
$577
20'to24'
260
300
340
385
420
455
495
530
570
605
640
24'to28'
285
325
370
415
450
490
530
565
610
645
680
CHECKMASTERPLAN2006ADJUSTEDVALUES(ENRCCI8064)
8'to16'
16'to20'
PipeSize
Adjusted
AdjustedValue
Variance
Variance
Value
6
N/A
N/A
8
$177
$17
N/A
10
$201
$11
N/A
12
$224
$4
$236
$1
15
$260
$5
$284
$9
$10
$319
$9
18
$295
21
$331
$1
$354
$1
24
$366
$1
$390
$0
27
$402
$7
$425
$5
30
$437
$7
$461
$1
33
$473
$8
$508
$13
36
$508
$13
$543
$13
39
$532
$2
$579
$14
42
$567
$2
$614
$14
20'to24'
Adjusted
Variance
Value
N/A
N/A
N/A
$0
$260
$5
$295
$3
$343
$7
$378
$7
$413
$6
$461
$1
$496
$13
$543
$9
$579
$9
$614
$22
$662
24'to28'
Adjusted
Variance
Value
N/A
N/A
N/A
$284
$1
$319
$6
$366
$4
$402
$13
$449
$1
$496
$6
$532
$2
$579
$14
$626
$16
$662
$17
$709
$29
FORCEMAINCOST
Assumption:
Forcemainstobeindepthrangeof4to16feet.Forcemainslocateddeeperthan16feet,useunitcostforgravitypipe.
Forcemaintobeductileironpipe.
Airreleasevalvesandmanholevaulttobeinstalledevery3000feet(includedinunitpriceforforcemain).
Description
Pavement
Removal/Temporary
Replacement
CY
$/CY
Trench
Excavation
Dewatering
ARVInstallation
andManhole
Pipeand
Installation
PipeBedding
Intermediate
Backfill&
Compaction
CY
$/CY
Backfill&
Compaction
Haulingof
CostPer
ExcessNative TotalCost Linear Use
Material
Foot
LS
$/LS
$/LF
$
$/LF
CY
$/CY
CY
$/CY
LF
$/LF
LF
$/LF
CY
$/CY
CY
$/CY
4"DIPlessthan10feetdeep
500
$4.00
1222
$28.70
444
$15.00
1000
$4.00
1000
$36.41
110
$45.00
170
$28.70
942
$45.00
367
$12.00
$140,783
$141
4"DIP10to16feetdeep
500
$4.00
1889
$28.70
1111
$15.00
1000
$4.00
1000
$36.41
110
$45.00
170
$28.70
1609
$45.00
567
$8.00
$200,050
$200
$200
6"DIPlessthan10feetdeep
500
$4.00
1222
$28.70
444
$15.00
1000
$4.00
1000
$42.24
110
$45.00
170
$28.70
942
$45.00
367
$12.00
$146,613
$147
$150
6"DIP10to16feetdeep
500
$4.00
1889
$28.70
1111
$15.00
1000
$4.00
1000
$42.24
110
$45.00
170
$28.70
1609
$45.00
567
$8.00
$205,880
$206
$205
8"DIPlessthan10feetdeep
500
$4.00
1222
$28.70
444
$15.00
1000
$4.00
1000
$46.20
110
$45.00
170
$28.70
942
$45.00
367
$12.00
$150,573
$151
$160
8"DIP10to16feetdeep
500
$4.00
1889
$28.70
1111
$15.00
1000
$4.00
1000
$46.20
110
$45.00
170
$28.70
1609
$45.00
567
$8.00
$209,840
$210
$210
10"DIPlessthan10feetdeep
500
$4.00
1222
$28.70
444
$15.00
1000
$4.00
1000
$62.70
110
$45.00
170
$28.70
942
$45.00
367
$12.00
$167,073
$167
$170
10"DIP10to16feetdeep
500
$4.00
1889
$28.70
1111
$15.00
1000
$4.00
1000
$62.70
110
$45.00
170
$28.70
1609
$45.00
567
$8.00
$226,340
$226
$225
12"DIPlessthan10feetdeep
500
$4.00
1222
$28.70
444
$15.00
1000
$4.00
1000
$78.10
110
$45.00
170
$28.70
942
$45.00
367
$12.00
$182,473
$182
$180
12"DIP10to16feetdeep
667
$4.00
1889
$28.70
1111
$15.00
1000
$4.00
1000
$78.10
110
$45.00
170
$28.70
1609
$45.00
567
$8.00
$242,407
$242
$240
15"DIPlessthan10feetdeep
667
$4.00
1630
$28.70
593
$15.00
1000
$4.00
1000
$107.80
150
$45.00
220
$28.70
1260
$45.00
489
$12.00
$245,740
$246
$245
15"DIP10to16feetdeep
667
$4.00
2519
$28.70
1481
$15.00
1000
$4.00
1000
$107.80
150
$45.00
220
$28.70
2149
$45.00
756
$8.00
$324,762
$325
$325
18"DIPlessthan10feetdeep
667
$4.00
1630
$28.70
593
$15.00
1000
$4.00
1000
$138.38
150
$45.00
220
$28.70
1260
$45.00
489
$12.00
$276,315
$276
$275
18"DIP10to16feetdeep
667
$4.00
2519
$28.70
1481
$15.00
1000
$4.00
1000
$138.38
150
$45.00
220
$28.70
2149
$45.00
756
$8.00
$355,337
$355
$355
21"DIPlessthan10feetdeep
667
$4.00
1630
$28.70
593
$15.00
1000
$4.00
1000
$163.13
150
$45.00
220
$28.70
1260
$45.00
489
$12.00
$301,065
$301
$300
21"DIP10to16feetdeep
667
$4.00
2519
$28.70
1481
$15.00
1000
$4.00
1000
$163.13
150
$45.00
220
$28.70
2149
$45.00
756
$8.00
$380,087
$380
$380
24"DIPlessthan10feetdeep
667
$4.00
1630
$28.70
593
$15.00
1000
$4.00
1000
$214.88
150
$45.00
220
$28.70
1260
$45.00
489
$12.00
$352,815
$353
$355
24"DIP10to16feetdeep
667
$4.00
2519
$28.70
1481
$15.00
1000
$4.00
1000
$214.88
150
$45.00
220
$28.70
2149
$45.00
756
$8.00
$431,837
$432
$430
Usethesecostforforcemains
ForceMainDiameter(in)
4
6
8
10
12
15
18
21
24
Lessthan10Feet
Deep
Cost($/lf)
140
150
160
170
180
245
275
300
355
10to16Feet
Deep
Cost($/lf)
200
205
210
225
240
325
355
380
430
Forcemain
60inchManhole<16feetdeep
AirReleaseValveARINylonD20
CostperLFBasedonSpacingof3,000feet
Cost
$8,000
$2,500
$4
$140
BOREANDJACKCOST
Assumptions:
Boreandjackunitcostincludemobilizationanddemobilizationcostandcarrierpipeand
installationcost.
Boreandjackunitcostdoesnotincludejackingandreceivingpitcost.
CarrierPipe
Diameter
(in)
SteelCasing
PipeDiameter
(in)
BoreandJack
Cost
($/lf)
8
10
12
15
18
21
24
27
30
33
36
39
42
36
36
36
36
42
43
49
51
56
59
64
68
72
575
575
575
575
625
675
735
765
800
845
925
980
1030
Pipeand
TotalBoreand UsethisforBoreand
Installation
JackCost
JackUnitCost
Cost
($/lf)
($/lf)
($/lf)
$40.50
$616
$615
$51.50
$627
$625
$56.00
$631
$630
$78.00
$653
$655
$42.50
$668
$670
$46.50
$722
$720
$58.00
$793
$795
$79.00
$844
$845
$87.50
$888
$890
$100.25
$945
$945
$113.00
$1,038
$1,040
$124.00
$1,104
$1,105
$135.00
$1,165
$1,165
MICROTUNNELINGCOST
Assumptions:
Averageproductionrateis32to60feetperday.
Unitpriceofmicrotunnelincludesthecostofboreandcarrierpipe.Mobilizationanddemobilizationisseparate.
Smallerpipelines(15inchdiameterorsmaller)willbeusingmicrotunnelingforforcemains,pipematerialwillbe
ductileiron.
Largerpipeline(18inchdiameterorgreater)willbeusingmicrotunnelingfortrunksewers,pipematerialwillbe
reinforcedconcrete.
Jackingandreceivingpitswillbeseparateitemsandarenotincludedintheunitcostofpiperamming.
MOBILIZATIONANDDEMOBILIZATION
Typicalmobilizationcostapproximately$44,000perday.
BoreHoleDiameter
Mobilization/
Demobilization($/Day)
Traveling
Days
Mobilization/DemobilizationCost
(Job)
Lessthan24inch
24to48inch
Greaterthan48inch
$44,000
$44,000
$44,000
2.5
4
6
$110,000
$180,000
$260,000
MICROTUNNEL
Pipe
Tunnel
Diameter Diameter
(in)
(in)
8DIP
10DIP
12DIP
15DIP
18RCP
21RCP
24RCP
27RCP
30RCP
33RCP
36RCP
39RCP
42RCP
8
10
12
15
18
21
24
27
30
33
36
39
42
36
36
36
36
42
43
49
51
56
59
64
68
72
Tunnel
ProductionRate
(lf/day)
Tunnel
Equipment
($/lf)
60
60
60
58
58
55
50
50
50
50
50
50
50
50
50
50
50
50
50
49
48
47
44
41
37
32
$75.00
$75.00
$75.00
$77.59
$77.59
$81.82
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$90.00
$91.84
$112.50
$114.89
$122.73
$131.71
$145.95
$168.75
Equipment
Casing
Technician Installation
($/lf)
($/lf)
$10.33
$10.33
$10.33
$10.69
$10.69
$11.27
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.40
$12.65
$15.50
$15.83
$16.91
$18.15
$20.11
$23.25
$733.33
$733.33
$733.33
$758.62
$758.62
$800.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$880.00
$897.96
$916.67
$936.17
$1,000.00
$1,073.17
$1,189.19
$1,375.00
Carrier
Pipe
($/lf)
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$40.50
$51.50
$56.00
$78.00
$42.50
$46.50
$58.00
$79.00
$87.50
$100.25
$113.00
$124.00
$135.00
Usethisfor
Microtunnel
Microtunnel
UnitCost
UnitCost
($/lf)
($/lf)
$819
$820
$819
$820
$819
$820
$847
$845
$847
$845
$893
$895
$982
$980
$982
$980
$982
$980
$982
$980
$982
$980
$982
$980
$982
$980
$1,023
$1,025
$1,034
$1,035
$1,038
$1,040
$1,060
$1,060
$1,025
$1,025
$1,029
$1,030
$1,060
$1,060
$1,124
$1,125
$1,154
$1,155
$1,240
$1,240
$1,336
$1,335
$1,479
$1,470
$1,702
$1,700
PIPERAMMINGCOST
Assumptions:
Piperammingismostusefulinshortdrivesandshallowapplications.
Mobilizationanddemobilizationcostwillbeincludedintheunitpriceofpiperamming.
Pipeinstallationcostwillalsobeincludeinthepriceofpiperamming.
Duetothelackofavailablecostinformationonpiperamming,unitpricecostforpiperammingwillbe
obtainedfromENRCCIadjustmentsfromMasterPlan2000.
Casingtoaccommodatecarrierpipebellplus12inches.
Smallerpipelines(15inchdiameterorsmaller)willbeusingpiperammingforforcemains,pipematerialwill
beductileiron.
Largerpipelines(18inchdiameterorgreater)willbeusingpiperammingfortrunksewers,pipematerial
willbereinforcedconcrete.
Jackingandreceivingpitswillbeseparateitemsandarenotincludedintheunitcostforpiperamming
Pipeand
PipeRamming AdjustedPipe
Cost2000(ENR RammingCost
Installation
CasingSize
PipeSize
Cost
(ENRCCI9527)
CCI6474)
($/lf)
($/lf)
($/lf)
37inch
$180
$265
8inch
$40.50
40inch
$200
$294
10inch
$51.50
42inch
$220
$324
12inch
$56.00
47inch
$260
$383
15inch
$78.00
55inch
$315
$464
18inch
$42.50
56inch
$315
$464
21inch
$46.50
61inch
$330
$486
24inch
$58.00
63inch
$365
$537
27inch
$79.00
68inch
$390
$574
30inch
$87.50
71inch
$420
$618
33inch
$100.25
76inch
$480
$706
36inch
$113.00
80inch
$520
$765
39inch
$124.00
84inch
$560
$824
42inch
$135.00
PipeType
DIP
DIP
DIP
DIP
RCP
RCP
RCP
RCP
RCP
RCP
RCP
RCP
RCP
TotalPipe
Ramming
Cost
($/lf)
$305
$346
$380
$461
$506
$510
$544
$616
$661
$718
$819
$889
$959
Usethisfor
Pipe
Ramming
Cost($/lf)
$305
$345
$380
$460
$505
$510
$545
$615
$660
$720
$820
$890
$960
ADDITIONALSHEETINGANDSHORINGCOST
Assumption:
Thereislimitedinformationonprojectcostforsheetingandshoring.Projectsaretypicallybidonalumpsumbasisandthereforemakingit
difficulttodetermineactualsheetingandshoringcost.
AdjustunitpricingfromSASDMasterPlan2000basedonENRCCI.
MasterPlan2000(ENRCCI6474)
UnitCostAdjustment(ENRCCI9827)
UsetheseUnitCostforSystemCapacityPlan
High
High
High
High
High
High
Groundwater Groundwater
No
Groundwater Groundwater
No
No
Groundwater Groundwater
Depth(ft)
Groundwater Undeveloped Developed Groundwater Undeveloped Developed Groundwater Undeveloped Developed
Area(LF)
Area(LF)
Area(LF)
Area(LF)
Area(LF)
Area(LF)
Baseline
20
50
Baseline
$29
$74
Baseline
$30
$75
8to16
Baseline
40
75
Baseline
$59
$110
Baseline
$60
$110
16to20
Baseline
60
90
Baseline
$88
$132
Baseline
$90
$135
20to24
Baseline
80
480
Baseline
$118
$706
Baseline
$120
$710
24to28
CheckSheetPilesat24to28feet
Pipedepthat26feet,excavationdepthat27feet
SheetPiles25'deepexcavationrange
drive,extract,andsalvage
SheetPiles=
=$26.50sf
$715.50 comparedto$710/lf
okay
ADDITIONALTRAFFICCONTROLCOST
Assumptions:
Minortrafficcontrolconsistingoftwowayflagging,constructionareasigns,trafficcones,and
channelizersareincludedinthepipeinstallationcost.
Additionaltrafficcontroltobeusedonmajorroads.Majorroadshave4ormorelanes.
Becausetrafficcontrolisusuallybidasalumpsumitem,itisdifficulttodeterminetrafficcontrol
costsfrompreviousprojectbids.Thereforetrafficcontrolcostareobtainedfromcataloguedunit
items.
Typicalcostfor2000feetofpipelineinstallationonmajorroad
Description
TrafficControlDesign
KTypeRail
PortableChangeableMessage
Channelizer/Crashbarrels
Quantity
1
2000
1
1
UnitCost
$25,000.00
$24.00
$10,000.00
$5,000.00
Unit
LS
LF
EA
LS
Total
Cost
$25,000.00
$48,000.00
$10,000.00
$5,000.00
$88,000.00
PriceperLinearFoot
$44.00
Usethisfortrafficcontrol
$45/LF
REVEGETATIONCOST
CostRange
Bid
Year
Description
2010
Hydroseeding
2010
Hydroseeding
2010
Hydroseeding
2010
Hydroseeding
2009
Hydroseeding
2009
Hydroseeding
Project
Jurisdiction
SantaClara
LowerSilverCreekFloodProtection
ValleyWater
andCreekRestorationProject
District
SantaClara
LowerSilverCreekFloodProtection
ValleyWater
andCreekRestorationProject
District
SantaClara
LowerSilverCreekFloodProtection
ValleyWater
andCreekRestorationProject
District
SantaClara
LowerSilverCreekFloodProtection
ValleyWater
andCreekRestorationProject
District
Countyof
MetroAirParkGravityConnector
Sacramento
Countyof
MetroAirParkForceMain
Sacramento
Quantity Unit
Median
50%
150%
Adjustedto2011
Weighted
Cost(ENR9527)
Average
($/SF)
ConstructionBid
84330
SF
$0.25
$0.13
$0.38
$0.27
$0.27
$0.28
$0.10
$0.25
38500
SF
$0.15
$0.08
$0.23
$0.13
$0.13
$0.15
$0.10
$0.25
7900
SF
$0.13
$0.07
$0.20
$0.12
$0.12
$0.13
$0.10
$0.25
26200
SF
$0.12
$0.06
$0.18
$0.11
$0.11
$0.10
$0.12
$0.25
AC
$2,500.00
$1,250.00
$3,750.00
$2,266.67
$0.05
$2,500.00
$1,800.00
$6,000.00
$2,500.00
12
AC
$1,700.00
$850.00
$2,550.00
$1,764.05
$0.04
$1,700.00
$1,600.00
$2,000.00
$1,250.00
Average
Use
$0.12
$0.25
perSF
$1,900.00
PUMPSTATIONCOST(1MGDto10MGD)
Assumption:
Minimumforcemainvelocityis3feetpersecond.Maximumforcemainvelocityis8feetpersecond.
Maximumdischargepressureis80psi.
Pump
Station
Flow
(MGD)
Flow
(GPM)
Velocity
(fps)
1MGD
1MGD
1MGD
1MGD
2MGD
2MGD
2MGD
2MGD
3MGD
3MGD
3MGD
3MGD
4MGD
4MGD
4MGD
4MGD
5MGD
5MGD
5MGD
5MGD
5MGD
5MGD
6MGD
6MGD
6MGD
6MGD
6MGD
6MGD
6MGD
6MGD
1.00
1.00
1.00
1.00
2.00
2.00
2.00
2.00
3.00
3.00
3.00
3.00
4.00
4.00
4.00
4.00
5.00
5.00
5.00
5.00
5.00
5.00
6.00
6.00
6.00
6.00
6.00
6.00
6.00
6.00
694
694
694
694
1,389
1,389
1,389
1,389
2,083
2,083
2,083
2,083
2,778
2,778
2,778
2,778
3,472
3,472
3,472
3,472
3,472
3,472
4,167
4,167
4,167
4,167
4,167
4,167
4,167
4,167
7.9
7.9
4.4
4.4
5.7
5.7
3.9
3.9
5.9
5.9
3.8
3.8
5.0
5.0
3.5
3.5
6.3
6.3
4.4
4.4
3.2
3.2
7.6
7.6
5.3
5.3
3.9
3.9
3.0
3.0
Nominal
PipeSize
(in)
6
6
8
8
10
10
12
12
12
12
15
15
15
15
18
18
15
15
18
18
21
21
15
15
18
18
21
21
24
24
PipeInside
Diameter
(in)
6.0
6.0
8.0
8.0
10.0
10.0
12.0
12.0
12.0
12.0
15.0
15.0
15.0
15.0
18.0
18.0
15.0
15.0
18.0
18.0
21.0
21.0
15.0
15.0
18.0
18.0
21.0
21.0
24.0
24.0
PipeLength
(ft)
500
3,600
500
14,300
500
12,000
500
20,000
500
13,800
500
20,000
500
20,000
500
20,000
500
15,700
500
20,000
500
20,000
500
11,300
500
20,000
500
20,000
500
20,000
FrictionHead
(ft)
C=130
19
136
5
134
6
137
2
94
5
137
2
67
3
114
1
47
4
135
2
71
1
34
6
137
2
100
1
47
1
25
StaticHead
(ft)
MinorHead
(ft)
TDH
(psi)
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
65
183
51
180
52
183
49
140
51
183
48
114
49
161
48
94
51
182
48
118
47
80
53
183
49
146
48
94
47
71
Discharge
Pressure
(psi)
29
80
22
79
23
80
21
62
23
80
21
50
22
70
21
41
22
80
21
52
21
35
23
80
21
64
21
41
21
31
Pump
HorsePower
(hp)
23
64
18
63
37
128
34
98
54
193
51
119
69
225
67
131
89
319
85
206
83
140
111
385
103
307
100
197
99
150
Pump
Station
Flow
(MGD)
Flow
(GPM)
Velocity
(fps)
7MGD
7MGD
7MGD
7MGD
7MGD
7MGD
8MGD
8MGD
8MGD
8MGD
8MGD
8MGD
8MGD
8MGD
9MGD
9MGD
9MGD
9MGD
9MGD
9MGD
9MGD
9MGD
10MGD
10MGD
10MGD
10MGD
10MGD
10MGD
10MGD
10MGD
7.00
7.00
7.00
7.00
7.00
7.00
8.00
8.00
8.00
8.00
8.00
8.00
8.00
8.00
9.00
9.00
9.00
9.00
9.00
9.00
9.00
9.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
4,861
4,861
4,861
4,861
4,861
4,861
5,556
5,556
5,556
5,556
5,556
5,556
5,556
5,556
6,250
6,250
6,250
6,250
6,250
6,250
6,250
6,250
6,944
6,944
6,944
6,944
6,944
6,944
6,944
6,944
6.1
6.1
4.5
4.5
3.4
3.4
7.0
7.0
5.1
5.1
3.9
3.9
3.1
3.1
7.9
7.9
5.8
5.8
4.4
4.4
3.5
3.5
6.4
6.4
4.9
4.9
3.9
3.9
3.2
3.2
Nominal
PipeSize
(in)
18
18
21
21
24
24
18
18
21
21
24
24
27
27
18
18
21
21
24
24
27
27
21
21
24
24
27
27
30
30
PipeInside
Diameter
(in)
18.0
18.0
21.0
21.0
24.0
24.0
18.0
18.0
21.0
21.0
24.0
24.0
27.0
27.0
18.0
18.0
21.0
21.0
24.0
24.0
27.0
27.0
21.0
21.0
24.0
24.0
27.0
27.0
30.0
30.0
PipeLength
(ft)
500
20,000
500
20,000
500
20,000
500
16,000
500
20,000
500
20,000
500
20,000
500
13,000
500
20,000
500
20,000
500
20,000
500
20,000
500
20,000
500
20,000
500
20,000
Basedonthetableabove,TDHrangesforlow,medium,andhighpumpstationsare
Lowheadpumpstation
=lessthan60TDH
Mediumheadpumpstation
=60to120THD
Highheadpumpstation
=120orgreaterpumpstation
UseTabula3.1.2tocalculatepumpstationcost
UseTDHof50feet,100feet,180feettorepresentlow,medium,andhighhead
FrictionHead
(ft)
C=130
3
132
2
63
1
33
4
136
2
80
1
42
1
24
5
137
2
100
1
52
1
29
3
121
2
63
1
36
1
21
StaticHead
(ft)
MinorHead
(ft)
TDH
(psi)
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
50
179
48
109
47
79
51
182
49
127
48
88
47
70
52
183
49
146
48
98
47
76
50
167
48
110
47
82
47
68
Discharge
Pressure
(psi)
22
78
21
48
21
35
22
80
21
56
21
39
21
31
23
80
21
64
21
43
21
33
22
73
21
48
21
36
21
30
Pump
HorsePower
(hp)
122
439
118
268
116
194
142
511
136
355
133
248
132
197
163
579
155
461
151
311
149
239
174
587
169
385
166
288
165
238
PumpStationCostUsingTabula3.1.2
50feetTDH(ENRCCI8815)
PSFirm
Capacity
<1MGD
1to2MGD
2to3MGD
3to4MGD
4to5MGD
5to6MGD
6to7MGD
7to8MGD
8to9MGD
9to10MGD
WetWellDepth
15feet
$430,000
20feet
$430,000
$739,000
25feet
30feet
35feet
$751,000
$1,040,000 $1,170,000
$1,490,000 $1,670,000
$1,790,000 $2,010,000
$2,350,000
$2,680,000
*Add20%markuptoaccountforvariabilityinsmallpumpstations
100feetTDH(ENRCCI8815)
PSFirm
Capacity
<1MGD
1to2MGD
2to3MGD
3to4MGD
4to5MGD
5to6MGD
6to7MGD
7to8MGD
8to9MGD
9to10MGD
WetWellDepth
15feet
$522,000
20feet
$522,000
$896,000
25feet
30feet
35feet
$912,000
$1,250,000 $1,380,000
$1,740,000 $1,920,000
$2,080,000 $2,310,000
$2,680,000
$3,040,000
*Add20%markuptoaccountforvariabilityinsmallpumpstations
180feetTDH(ENRCCI8815)
PSFirm
Capacity
<1MGD
1to2MGD
2to3MGD
3to4MGD
4to5MGD
5to6MGD
6to7MGD
7to8MGD
8to9MGD
9to10MGD
WetWellDepth
15feet
$653,000
20feet
25feet
30feet
35feet
$653,000
$1,130,000 $1,140,000
$1,570,000 $1,710,000
$2,150,000 $2,330,000
$2,580,000 $2,810,000
$3,260,000
$3,700,000
*Add20%markuptoaccountforvariabilityinsmallpumpstations
CheckPumpStation1mgdLowHead
DESCRIPTION
Mobilization
ClearingandGrubbing
Grading,Excavation,SitePreparation
Dewatering
AggregateBaseforPSPad(120'x120')
AsphaltforPSPad(120'x120')
Chainlinkfence
20'ChainlinkSwingGate
5'ChainlinkManEntryGate
WashPad
ElectricalPanelCanopy
Bypassing
SewerGravityPipe(8inchdiameter)
DischargeManhole(MH+PVCLining)
WetWell
ValveVaultandBypassVault
Electrical,Lighting,andInstrumentation
SitePiping
Pump20Hp
StartUpandTesting
Generator
OdorControl
QUANTITY
1
1
1600
1
1600
522
435
2
1
1
1
1
100
1
1
1
1
1
2
1
UNITCOST
20000
4000
1.01
10000
26.28
71.5
47.5
3600
800
5000
4000
85000
160
8500
75000
25000
100000
50000
15000
10000
UNIT
LS
LS
SY
LS
SY
Ton
LF
EA
EA
EA
EA
LS
LF
EA
LS
Total
COST
$20,000
$4,000
$1,616
$10,000
$42,048
$37,323
$20,663
$7,200
$800
$5,000
$4,000
$85,000
$16,000
$8,500
$75,000
$25,000
$100,000
$50,000
$30,000
$10,000
$0
$0
$552,150 comparedto$560,000
okay
CheckPumpStationCostAgainstPreviouslyBuiltProjects
AcceptableBidRange
BidYear
2004
2004
2007
2007
2008
2008
2008
2008
2011
BidYear
2004
2004
2007
2007
2008
2008
2008
2008
2011
PumpStation
Capacity
S132ChrysanthyPumpStation
S129FruitridgeCenterPumpStation
S144WilsonRoadPumpStation
S145LambertRoadPumpStation
S142ElkGrovePromenade
3.6mgd
8.7mgd
.7mgd
.7mgd
2mgd
S143FlorinMallLiftStation
0.5mgd
S146WalnutGrovePumpStation
S147CameronRoadPumpStation
CreekProtectionProjectArcadeCreek
PumpStation
S132ChrysanthyPumpStation
S129FruitridgeCenterPumpStation
S144WilsonRoadPumpStation
S145LambertRoadPumpStation
S142ElkGrovePromenade
S143FlorinMallLiftStation
S146WalnutGrovePumpStation
S147CameronRoadPumpStation
CreekProtectionProjectArcadeCreek
1.6mgd
1.6mgd
0.5mgd
Capacity
3.6mgd
8.7mgd
.7mgd
.7mgd
2mgd
0.5mgd
1.6mgd
1.6mgd
0.5mgd
PSHead
Low
High
High
Low
High
High
Low
Weighted
AverageBid
1,242,361
5,227,223
1,065,596
911,765
736,823
560,557
1,353,081
1,301,271
482,633
MediumBid
1,225,000.00
5,557,945.50
1,046,460.00
875,580.00
727,000.00
50%
612,500
2,778,973
523,230
437,790
363,500
+50%
1,837,500
8,336,918
1,569,690
1,313,370
1,090,500
511,195.00
1,395,050.00
1,358,775.00
508,700.00
255,598
697,525
679,388
254,350
766,793
2,092,575
2,038,163
763,050
AdjustedAverage
ComparisonPump
WeightedAverage
Bid2011(ENRCCI
StationCost
Bid
20119527)
PumpStationBids
1,242,361
5,227,223
1,065,596
911,765
736,823
1,540,528
6,481,756
1,193,467
1,021,177
795,769
1,700,000
5,600,000
710,000
710,000
810,000
1,011,637
3,566,500
895,454
840,330
767,270
1,127,349
4,938,641
1,268,410
900,460
716,200
1,205,000
6,177,250
875,540
804,300
727,000
560,557
1,353,081
1,301,271
482,633
605,401
1,461,328
1,405,373
482,633
460,000
1,200,000
1,200,000
460,000
697,264
1,436,300
1,425,675
290,500
511,195
1,328,566
1,234,855
429,800
473,211
1,384,200
1,380,050
512,700
Adjusted
Adjusted
ActualCost
ActualCost ComparisonPump
AverageBid
ofPump
ofPS(ENR
2011(ENRCCI
StationCost
Station
CCI2011)
20119527)
1,540,528
1,011,637
1,254,430
1,700,000
6,481,756
3,566,500
4,422,460
5,600,000
1,193,467
875,540
980,605
850,000
1,021,177
804,300
900,816
850,000
795,769
767,270
828,652
970,000
605,401
697,264
753,045
550,000
1,461,328
1,297,320
1,401,106
1,200,000
1,405,373
1,258,575
1,359,261
1,200,000
482,633
454,000
454,000
550,000
Variance
26.21%
21.03%
15.37%
5.98%
14.57%
36.92%
16.76%
13.27%
17.45%
1,058,500
6,226,500
1,261,250
1,064,900
1,193,700
1,142,200
940,200
850,700
1,152,720
1,009,900
1,466,200
1,376,650
572,000
1,593,960
1,473,100
330,000
950,530
1,024,350
508,700
1,309,000
1,372,725
1,225,000
1,399,000
1,348,818
1,351,194
1,297,320
1,258,575
595,000
1,152,399
1,083,392
454,000
1,247,300
1,102,800
651,000
1,536,199
1,488,133
1,438,100
1,340,900
1,405,900
1,426,775
1,406,573
REALESTATECOST
COMMERCIALLANDSALES
Address
SalePrice
6451StocktonBl
AugustaWy
0000ReeseRd
$615,000
$72,500
$46,500
SaleDate
SF
7/23/2010 107,288
10/29/2010
2/17/2010
10,683
12,000
1200CreeksideDr
$2,200,000
6/22/2010 151,589
0000CreeksideDr
$820,620
0000IronPointRd
0000RecycleRd
$2,475,000
$250,000
6/24/2010 584,531
6/30/2010 53,302
6915ElkGroveBl
$2,000,000
7/30/2010 176,804
8706WStocktonBl
8706WStocktonBl
8980GrantLineRd
8980GrantLineRd
8980GrantlineRd
$1,250,000
$1,250,000
$602,000
$602,000
$602,000
LagunaGroveDr
$1,300,000
3/24/2010 240,887
9770AutoCityDr
$1,084,000
5/21/2010 246,550
8/13/2010
6/8/2010
6/8/2010
10/15/2010
10/15/2010
10/15/2010
68,389
629,573
629,573
171,191
171,191
171,191
$/SF
Notes
Subjectpropertyisavacant,level,infillcommerciallot.Plansapprovedfora24,700
$5.73 sqftretail/officecenter.
BrokeredallcashsaletotheCatholicChurchwhichownstheadjacentparceltothe
$6.79 westofthesubject.Subjectpropertyhasbeenmarketedandlistedasapartment
$3.88
AcrossthestreetfromMercyHospitalFolsom,planstoconstructionmedicaloffice
$14.51 bldg.
Armslengthtransactionthrubroker.Vacantofficelandacrossthestreetfrom
$12.00 MercyFolsomHospital.Purchasedforinvestment.
ThiswasanREOsale.Thebuyerdoesnothaveimmediateplansforthelandatthis
$4.23 time.
$4.69 Autosalvageyard.
Unimproved4acreparcelonnorthsideofElkGroveBlvdabout1/4milewestof
Bruceville.Buyerplans110,000sqft,2storyseniorassistedlivingresidentialcare
$11.31 facility.Sellerpaidallexpensesrelatingtonewparcelmapandentitlements.Seller
11702200250000toholdforreentitlementandsell.Purchasewithtentativemap
perComps.MP03Proposedresidentialdevelopmentsoldwithtentativemapto
$1.99 developerforreentitlementandresaletobuilder.Buyeralsopurchasedadjacent
$1.99
$3.52
$3.52
$3.52
BrokeredallCashSale.Firstopenmarketsaleafterinternal(Chrysler)CIOS
conveyancepursuanttoUSBankruptcyCourt.PerBlakeSnider(4058000),sales
$5.40 pricebaseduponnegotiations.Listed@$11psf.Nofreewayvisibility.
BrokeredcashREOSale.Confirmedw/AndrewPfeiferVP3057794075armslength
transaction.ProposedHyundaidealershiprelocatingfromFlorinRd.MP03
$4.40 contiguousvacantparcels.
0000SunriseBl
$29,900
11/22/2010
22,758
$1.31
GreenbackLn
$100,000
2/25/2010
25,657
$3.90
4/27/2010 560,182
$8.93
100PromenadeCir
$5,000,000
10635FairOaksBl
$350,000
9/3/2010
36,590
$9.57
1544HoodRd
$368,000
2/19/2010 75,460
AverageCommericialCost
$4.88
$5.80
MP2Brokeredcashsale.Oneparcelinfloodzone.Theparcelslocatedinbusyand
noisyintersection.Pertelephoneconversationwiththelistingagent,Carlos
SkozlowsatColdwellBanker.Theotherparcelneedsoffsitesimprovements.
Nobrokerinvolvedinthepurchasedofthesubjectproperty.Thesubjectvacant
landhasnostreetfrontageandislandlockedbehindparcel#22301420440000.
Currently,thevacantlandisusedforstorageofcontainersandcars.Theownersof
parcel#22301420440000,purchasedthesubjectvacantland.Unabletoverified
Assemblage,saleoutofforeclosure,Fulloffsites,PurchasedbyKaiserFoundation
forfuturemedicalofficebuilding.Buyerstatesthereisnoparticulartimelinefor
construction.SubjectislocatedinthePromenadeatGatewaySacramentowhichis
Directfromseller.Subjectlocatedonavery,busystreet.Thetopographyismostly
levelwithsomesloping.Nositeimprovements.Vacantlandlocatedonthecorner
ofFairOaksandCentralAve.Thiscornerhasa4waystopandisverybusy.The
developedforapartments.Someinfrastructureinplace,road,someelectricaland
water.Propertywasforeclosedon20091001andtakenbyUniteCommercialBank
asReceiverforEastWestBank.PropertywaslistedthruMLSandLoopnet.Buyer
perSF
RESIDENTIALLANDSALES
Address
SalePrice
21006ThSt
$100,000
057ThSt
$75,000
293139ThSt
$30,000
383336ThSt
$20,000
408273RdSt
$29,000
444052NdSt
$45,000
4208SierraVistaAv
$5,000
0EnricoBl
$50,000
511564ThSt
$4,000
29BunrattyCt
$35,000
978BriarcrestWy
$60,000
0PocketRd
$850,000
7713EShoreDr
$219,000
6565LangAv
$75,000
0HingAv
$10,000
0CitrusAv
$20,000
0CitrusAv
$19,000
7419PersimmonAv
$200,000
7471DellaCr
$75,000
8596UnsworthAv
$230,000
0BirchRanchDr
$225,000
11867CountryGrdnDr $1,470,000
4831BirchValleyWy
$2,441,000
12295ElPortalWy
$2,144,000
0MormonSt
$80,000
659HancockDr
$55,000
801CristinaCt
$67,000
805CristinaCt
$87,500
1514GionataWy
$52,500
810CristinaCt
$80,000
784LorenaLn
$75,500
0TrowbridgeCt
$198,000
107KempCt
$150,000
498ListoweDr
$190,000
729HeritagePl
$245,000
$210,000
700GlenMadyWy
$148,000
1731LakeVistaWy
1763BarrheadCt
$185,000
539SerpaWy
$172,000
1804RuanCt
$182,500
414TobrurryWy
$150,000
449SerpaWy
$250,000
365TobrurryWy
$122,000
369TobrurryWy
$130,000
335TobrurryWy
$130,000
264TobrurryWy
$148,000
323TobrurryWy
$160,000
12785ThornbergWy
$262,000
10856WraysburyWy
$246,000
10820AtherstoneDr
$237,000
6442LagoCr
$84,000
6334Cazador
$25,000
0CottonwoodLn
$300,000
7894IonaWy
$216,000
0GerberRd
$362,500
0GerberRd
$280,000
8800BradshawRd
$500,000
$1,840,000
8891CobbleCrestDr
10651HalfwayRd
$66,000
0LeeSchoolRd
$143,000
0SimpsonRanchCt
$250,000
0SimpsonRanchCt
$188,000
$130,000
8900GoodShepherdLn
$240,000
8920GoodShepherdLn
0BradshawRd
$280,000
9135ShireOaksLn
$156,500
9136ShireOaksLn
$340,000
0MeissRd
$45,000
0WashingtonAv
$50,000
$6,000
3136AcademyWy
52MorellCt
$79,000
$30,000
0CottageWy
6232GobernadoresLn
$152,000
1235JacobLn
$150,000
SaleDate
4/20/2010
6/11/2010
6/28/2010
12/6/2010
5/7/2010
3/10/2010
10/13/2010
6/30/2010
12/6/2010
7/19/2010
3/23/2010
11/29/2010
2/10/2010
12/27/2010
4/14/2010
8/27/2010
8/10/2010
8/4/2010
12/29/2010
5/7/2010
12/2/2010
6/3/2010
12/30/2010
5/28/2010
7/30/2010
11/17/2010
12/28/2010
12/14/2010
12/8/2010
9/14/2010
8/31/2010
4/12/2010
9/21/2010
6/22/2010
1/28/2010
2/10/2010
12/10/2010
5/6/2010
3/25/2010
9/3/2010
7/25/2010
12/21/2010
10/21/2010
9/30/2010
4/20/2010
7/28/2010
2/5/2010
12/22/2010
9/15/2010
9/14/2010
6/23/2010
4/6/2010
9/7/2010
2/19/2010
11/12/2010
9/10/2010
6/16/2010
3/31/2010
5/24/2010
8/10/2010
8/2/2010
4/22/2010
6/17/2010
3/2/2010
1/15/2010
12/6/2010
3/1/2010
5/21/2010
10/20/2010
12/6/2010
12/23/2010
10/19/2010
6/30/2010
6/30/2010
$/SF
$31.25
$9.26
$5.30
$3.83
$4.76
$7.20
$0.96
$2.61
$0.46
$5.39
$6.56
$8.20
$18.62
$0.68
$0.54
$2.99
$2.84
$3.18
$10.34
$3.52
$1.08
$173.99
$3.79
$5.15
$15.31
$6.65
$2.93
$3.81
$3.72
$5.35
$6.21
$8.93
$19.13
$7.79
$17.32
$13.39
$9.34
$7.15
$7.64
$9.79
$7.00
$20.83
$4.90
$4.54
$6.70
$8.65
$8.37
$3.90
$183.45
$169.89
$7.14
$7.23
$0.52
$5.61
$0.60
$0.46
$63.77
$8.22
$0.82
$0.70
$0.30
$0.23
$1.91
$0.46
$1.35
$1.88
$3.12
$0.34
$3.83
$0.98
$1.27
$3.34
$4.26
$9.44
AverageResidentialCost
AverageofCommercialandResidential
TemporaryConstructionEasements(10%)
UseforTCE
PermanentEasement(50%)
UseforPermanentEasement
$10.02
$7.91
$0.79
$0.80
$3.96
$4.00
Address
5411LambertRd
8244WymarkDr
9990WinkleCr
11201KetchersideLn
14059DiabloviewCt
0TwinCitiesRd
13067StocktonBl
0KostRd
9768PringleAv
13459JohnRochaCr
13570JohnRochaCr
13500JohnRochaCr
13444JohnRochaCr
13472JohnRochaCr
13585JohnRochaCr
13542JohnRochaCr
13514JohnRochaCr
712UnionSt
708TylerIsBrRd
0SorentoRd
8341NathalieWy
8340NathalieWy
8336NathalieWy
73418ThSt
07ThAv
637OSt
0ElkhornBl
674018ThSt
0USt
7720NelsonLn
7129WalnutAv
231ESt
0RioLindaBl
02NdSt
340PinedaleAv
5041SullySt
4320SantaAnaAv
855RioRoblesAv
0PeerlessAv
0TelegraphAv
148LostCreekDr
126FlatRockDr
164TemperanceRvCt
5425CollegeOakDr
5425CollegeOakDr
0WalnutAv
5234BellWoodWy
1335GraceAv
4337MarysvilleBl
4024AstoriaSt
4332PoseidonLn
0HopeLn
4040BraxtonLn
6350MariposaAv
8000SunsetAv
8261WindingWy
4350ChicagoAv
51MoreyAv
3637PresidioSt
0SouthAv
8672OldVillaCt
3410MontclaireSt
8178StrengAv
0BryanWy
3925HollisterAv
0FairOaksBl
0SutterHillLn
6148SutterAv
6146SutterAv
0FairOaksBl
8490LondonPlainCt
8551HeatherCrossWy
2741AltosAv
1035SonomaAv
1027OpalLn
perSF
perSF
perSFperyear
perSF
SalePrice
$180,000
$3,700,000
$1,528,000
$110,000
$75,000
$75,000
$675,000
$102,500
$95,225
$95,225
$95,225
$95,225
$95,225
$99,950
$99,950
$99,950
$99,950
$35,000
$52,500
$45,000
$60,000
$58,000
$58,000
$112,000
$18,000
$55,000
$40,000
$70,000
$590,000
$50,000
$125,500
$58,000
$87,000
$25,000
$27,000
$50,000
$50,000
$18,000
$5,000
$170,000
$155,000
$100,000
$52,500
$39,500
$35,000
$57,000
$96,500
$50,000
$20,000
$35,000
$72,500
$160,000
$707,000
$382,000
$200,000
$25,000
$195,000
$500,000
$21,500
$6,000
$89,000
$130,000
$375,000
$207,000
$121,900
$91,500
$25,000
$235,000
$98,000
$100,000
$135,000
$60,000
$15,000
$10,000
$12,500
SaleDate
12/2/2010
12/30/2010
3/31/2010
12/30/2010
1/28/2010
11/2/2010
9/29/2010
7/7/2010
6/4/2010
6/4/2010
6/4/2010
6/4/2010
6/4/2010
5/10/2010
3/15/2010
1/19/2010
1/15/2010
3/3/2010
10/13/2010
10/15/2010
5/3/2010
4/9/2010
3/29/2010
8/19/2010
2/26/2010
12/23/2010
12/6/2010
5/14/2010
8/16/2010
12/20/2010
3/25/2010
11/12/2010
1/12/2010
12/7/2010
5/19/2010
2/16/2010
10/5/2010
7/19/2010
9/16/2010
8/18/2010
4/5/2010
7/26/2010
9/23/2010
1/5/2010
5/13/2010
2/17/2010
2/10/2010
1/14/2010
7/12/2010
6/15/2010
5/28/2010
3/2/2010
10/6/2010
6/11/2010
10/14/2010
2/19/2010
5/14/2010
7/27/2010
12/6/2010
3/10/2010
12/7/2010
9/7/2010
1/14/2010
8/6/2010
6/30/2010
2/11/2010
4/23/2010
8/31/2010
4/30/2010
5/6/2010
5/25/2010
8/25/2010
10/14/2010
12/6/2010
5/21/2010
$/SF
$0.13
$6.41
$179.45
$0.25
$1.90
$0.97
$1.22
$0.97
$1.35
$1.32
$1.11
$1.16
$1.16
$1.17
$1.32
$1.22
$1.22
$10.03
$2.68
$0.19
$6.63
$7.01
$6.88
$2.89
$1.17
$0.54
$0.53
$1.12
$2.28
$1.77
$2.32
$0.67
$0.21
$1.25
$1.24
$1.97
$1.01
$2.02
$0.36
$1.70
$13.46
$4.25
$3.75
$2.32
$2.05
$2.84
$13.03
$0.46
$1.70
$2.00
$4.76
$5.17
$3.16
$50.40
$4.69
$3.38
$4.54
$0.98
$3.53
$1.15
$7.05
$16.15
$18.20
$7.09
$3.33
$4.73
$1.18
$11.88
$10.97
$1.23
$7.08
$9.37
$1.86
$1.78
$1.91