INDIABULLS POWER LTD, AMRAVATI

INSTRUCTION
Following equipment changeover schedule is to be followed for Unit-1:1.

1st of every month

1. Vapour Extraction. Fans of MOT /


Generator / and Seal steam.

2.

1st and 15th of every month

1. D/A level controllers CD-14 / CD17 in B shift.


2. Generator Seal Oil Pump
3. DMCW PUMP

3.

Every Monday

1. LOP of Mill A
2. CEPs.
3. ECO Hopper Pump
4. DMCW BOOSTER PUMP

4.

Every Tuesday

1. LOP of Mill B, LOP Of PA Fan-A


2. DMCW pump / Service water pump.
3. Boiler Feed Pump ( IN PRESENCE
OF ELECT & C&I IN CASE OF BFPC)

5.

Every Wednesday

1. LOP of Mill- C, LOP Of PA Fan-B


2. Vacuum pump of condenser.
3. BALP
4. ACW PUMP U-1

6.

Every Thursday

1. LOP of Mill D, LOP Of ID Fan-A,


LOP Of ID Fan-B
2. Fire water pump (Trial To Be Taken).
3. BAHP.
4. ACW PUMP U-2

7.

Every Friday

1. LOP of Mill E, LOP Of FD Fan-A,


LOP Of FD Fan-B
2. Air compressor.
3. ESP vacuum pumps depending on
availability.
4. HP/ LP Seal Water Pump In ASPH-I

INDIABULLS POWER LTD, AMRAVATI


8.

Every Saturday

1. HFO pumps.
2. LDO Pump.
3.
LOP Of APH-A, B Both Guide
Bearing & Support Bearing
4. HP/ LP Seal Water Pump In ASPH-II