DOC No.

: 29040-PI-UFR-0019

TRAINING MANUAL- PIPING


UNIT PLOT PLAN
Uhde India Limited

5.0

Rev.

: R0

Page

: 5

PLATFORMS:

Towers, vertical and horizontal vessels:


Distance of platform below centerline of manhole flangeside platform
Width of manhole platform from manhole cover to outside
edge of platform - side platform
Platform extension beyond centerline of manhole - side
platform
Distance of platform below underside of flange - head
platform
Width of platform from three sides of manhole - head
platform

6.0

900
900
175
750

HORIZONTAL EXCHANGER:

CLEARANCE IN FRONT OF CHANNEL


OR BONNET FLANGE
HEAT EXCHANGER TUBE BUNDLE
REMOVAL SPACE
MINIMUM CLEARANCE FROM EDGE
OF FLANGES

7.0

MM
800-1050

1200
BUNDLE LENGTH + 1.25 M
300

VERTICAL EXCHANGER:

DISTANCE OF PLATFORM BELOW


TOP FLANGE OF CHANNEL OR
BONNET
WIDTH OF PLATFORM AT SIDES OF
HORIZONTAL AND VERTICAL TUBE
FURNACE
WIDTH OF PLATFORM AT END OF
HORIZONTAL TUBE FURNACES

1500

750 (MIN.)

1000(MIN.)