Professional Documents
Culture Documents
The minimum elevation of the bottom of overhead piping shall be in accordance with
DEP 80.00.10.11-Gen.
The minimum elevation of the bottom of overhead obstructions shall be:
• 6.0 m (20 ft) over railways
• 6.0 m (20 ft) over main roads
NOTE: In some situations the lower side of the pipe supports or the supporting steel dictates the minimum
elevation of overhead piping
It is recommended to always have one route to each unit and to the expansion areas
without pipe rack crossings.
6.2.5 Piping/cabling
The minimum elevation of the bottom of overhead piping shall be:
• 4.0 m (13 ft) for crane access
• 4.0 m (13 ft) for truck access
• 2.7 m (9 ft) for fork-lift truck access
NOTE: In some situations the lower side of the pipe supports or the supporting steel dictates the minimum
elevation of overhead piping.
The distance between pipes shall allow for the turning of a spectacle blind, if present.
For pipe flanges size DN300 (NPS 12) and above, a min. of 460 mm (18 in.) shall be
provided as standing room between flange and any obstruction such as equipment, guard
rail etc. (see dimension B in Figure 26) for locations such as battery limit platforms, or
where the flange joint is meant for operations (e.g., vessel isolation) or maintenance (e.g.,
removal of valves, etc.). Due consideration shall be given to cold weather conditions which
may lead to the requirement of additional clearances over and above the minimum vertical
clearance of 460 mm (18 in.).
There shall be a minimum vertical clearance of 230 mm (9 in.) between low point drains
closure flange and soil, grade or platform. Due consideration shall be given to extreme
snow and ice conditions which may lead to requirement of additional clearances over and
above the minimum vertical clearance of 230 mm (9 in.).
DEP 30.00.60.20-Gen.
5.9 FLANGE HEIGHT
The space between a flange on a vertical pipe / vessel nozzles that penetrates decking
shall be the length of the flange bolt plus 25 mm (1 in.) (See dimension A on Figure 27
below). The same space requirement applies to a flange on a pipe that penetrates the
ground or grating on an elevated work platform.
DEP 30.00.60.20-Gen.
3. WORKSPACE ENVELOPE - MINIMUM REQUIREMENTS
3.1 STANDING POSITION
3.1.1 Minimal working volume
As a minimum, adequate standing workspace shall be provided wherever an operator or
maintainer is required to work. The minimum dimensions of this space shall be as shown in
Figure 1 and Table 1.
NOTE: There will be exceptions e.g. for the purpose of determining sizes of
muster areas or individual standing room at embarkation stations on
offshore/marine facilities. The width and depth dimension should be
reduced to 610 mm (24 in.). Designers are directed to their regional
HFE TA, for exceptions. These dimensions, furthermore, have been
corrected for various types of PPE (i.e. Cold Weather clothing and
SCBA).
Maximum effective forward reach (i.e. ability to grasp and turn/push/pull forward) shall be
460 mm (18 in.) from the front of the operator’s body.
Valves in a vertical section of the pipe e.g., located in a manifold or at battery limit, shall be
oriented with all the stems on the same side as shown in Figures 4.5 and 4.6, with a 75 mm
(3 in) clearance maintained between the lever and any obstruction.
Figure 4.6 Manifold or battery limit valves with 75 mm (3 in) minimum gap between
front face of lever’s outer surface and nearest flange/obstruction
NOTE: DEP 31.38.01.11-Gen., Section 3.8 requires that valves and flanges shall be staggered
whenever possible to ease operation and reduce space. This is acceptable as long as the
minimum clearance is maintained and valve heights comply with requirements of Table 4.2.
A. For flange assembly the following piping components are considered as critical, as they are subject to
wear, failure, and removal/repair for maintenance/inspection:
- Control valves
- Actuated valves
- Spool pieces, spacers, spectacle blinds
- Suction strainers
- Basket filters
- On line flow meters
Two main cases should be considered:
1. For flanges with an overall external diameter below 500 mm (around 12” diameter pipe):
- 900 mm in front of the assembly (allow 1 man to stand and to work).
- 460 mm behind the valve (allow 1 man standing in front to access the back of the flange with tools and hands
for bolting/unbolting operation).
2. For flanges with an overall external diameter equal or greater than 500 mm (around 12” diameter pipe):
- 1300 mm in front of the assembly (allow 1 man to stand, squat and work).
- 900 mm behind the valve (allow 1 man standing and working at the back of the flange with his tools)
B. For all other cases (eg. manual valve) not listed above:
- 750 mm in front of the assembly (allow 1 man to stand and to work)
- 75mm behind valve for flanges with an overall external diameter less than 500 mm (around less than 12"
diameter pipe).
- 460 mm behind the valve for flanges with an overall external diameter equal or greater than 500 mm
(around 12” diameter pipe)
(To allow 1 man standing in front to access the back of the flange with tools and hands for
bolting/unbolting operation)
C. For all cases, a minimum of 300 mm has to be considered below the assembly.
DEP 30.00.60.20-Gen.
4.2 WEIGHTS AND LIFTING
The maximum weight to be lifted by one person using two hands, with the load close to the
body, shall be 23 kg (50 lbs).
Refer cl.3.17 of DEP 31.38.01.11 for installation and orientation of tapping on orifice plate flanges for various services.
Following table is used during FEED stage. After receiving the manufacturer’s guideline during DD stage requirements shall be
piping classes.
DEP 30.00.60.20-Gen
5.3 AIR COOLERS (FIN FANS)
The drive assembly access platform on exchanger banks, mounted on a pipe rack, shall
have an extension platform that permits lifting the motor with a crane. Maximum travel
distance of the motor to the lift point shall be 33 m (108 ft.). Platform extensions shall be
level.
DEP 30.00.60.20-Gen
5.2 ROTATING EQUIPMENT
The minimum clearance between pumps or pumps and piping shall at least be 1.2 m (48 in.) for small
pumps (< 18 kW) and 1.5 to 2 m (60 in. – 80 in.) for larger pumps (taking base plates, valve
hand wheels, pipelines, etc. into account).
DEP 31.38.01.11-Gen.
4.2.2.7 Suction piping of centrifugal pumps
Suction piping shall be as short and as direct as possible, avoiding high spots where
pockets of gas or air could accumulate. Only eccentric reducers (top flat) may be used for
pipe diameter changes in horizontal pipes. For slurry services, eccentric reducer (bottom
flat) shall be used for pipe diameter changes in horizontal pipes to avoid accumulation of
solids. For horizontal suction pipes, a drain shall be provided upstream of the reducer. In
vertical pipes, eccentric or concentric reducers may be used.
The length of the straight pipe from the last elbow to the suction nozzle shall be sufficient to
ensure minimum turbulence at the pump suction. The minimum length, which shall not
include any reducer, strainer or stop-flow valve, shall be as indicated in Table 5:
Piping Design Philosophy
Removable spools shall be provided at each compressor to permit disassembly of equipment without
disturbing the main runs of the suction and discharge lines. It should be ensured that the removable
spool clears the edge of the compressor to allow removal of the compressor.
KHF-00-PDFEED-MP-7180-00005-0000/04
8.0 EQUIPMENT LAYOUT & SEPARATION CRITERIA
· Platform shall be provided in front of each heat exchanger where applicable, for
enabling installation of bundle pulling tool. Minimum length of platform shall meet
bundle length + 2 meter (for pulling device and command) + 1 meter (normal access
and maintenance). Platform shall be capable of carrying the weight of the bundle and
bundle pulling tool.
Spiral stairs permitted only on tanks or other round structures whose diameter is greater than 2440
mm (96 in.), and where a normal stair design is inappropriate. For tank height more than 6 meters,
spiral staircase shall be provided, otherwise for tanks height 6 meter and below cage ladder to be
provided or as specified in mechanical data sheet.
Two way stairs requiring stretcher access shall be considered in this project.
For access to tank roofs, spiral staircase shall be provided. Stair entry to the roof (landing) shall be located on
the upwind side of the prevailing wind direction. The spiral stair should ascend in clockwise direction to allow
the stair handrail to be on the right-hand side during descent.
Handrails shall be provided at the edge of the roof for the full circumference of all fixed roof tanks. Handrail is
to be provided to the center of the roof on all tanks exceeding 12.5m diameter if access is needed for nozzle
and associated valves etc.
Walkways and their steps higher than 1.5m above grade shall be provided with handrails on both sides
KHF-00-104133-MS-7771-00003-0000 / Rev 03
Specification of API Storage Tanks
4.1.4 Tanks less than 4500 mm inside diameter may be fabricated in shop and higher sizes
shall be site fabricated. Shop fabricated tank shall be provided with lifting lugs.
4.1.7 For tanks less than 4500 mm inside diameter, roof structure (rafter) construction is not
required and self-supported roof plate shall be considered in the design. If external
rafter is used in roof structure construction, shell standard drawing S 51.157-001 shall
be referred. For self-supported (no rafter) roof construction, the roof angle of 12 to 15
degree shall be considered, whereas for rafter supported roof, a slope of 1:6 shall be
considered in the design.
4.1.8 For tanks less than 4500 mm inside diameter, butt welded construction for bottom
plate may be considered, with back chip, MT examined and re-weld from other side
and the weld shall be ground flushed / smoothened to facilitate proper internal lining /
coating and avoid any damage to the lining. 100% Radiography shall be carried out for
the butt welded bottom plate joint, similar to those for radial joint of bottom annular
plate. For tanks with inside diameter of 4500 mm and more, lap welded bottom plate
construction shall be followed. Root MT and final MT shall be carried out for lap joints.
4.1.20 For tanks up-to and including 30 m in diameter, minimum two earthing bosses are
required. For tanks above 30m in diameter, minimum three earthing bosses are
required. The earthing bosses shall be in accordance with the drawings STD-4-0317-
001 and STD-4-0304-0001.
4.1.31 PVV's and blow off hatches shall be located very close to roof periphery.
4.1.33 Vacuum/Vent Nozzles are to be sited as near as possible to the blanket connection in
line with API 2000.
4.1.34 For Tank height more than 6 meters, spiral staircase shall be provided, otherwise for
tanks height 6 meter and below cage ladder to be provided or as specified in data
sheet.
drawing S 51.051. Cleats for handrail shall be taken from the tank top (preferably from
top curb angle). VENDOR shall also provide walkway / platform with handrails to
access Blow-off hatch, PVV and other nozzles / manways.
be located on
ction to allow
ks. Handrail is
ed for nozzle
Piping Design philosophy
8.16. Weld Proximity
For Shop and Field fabrication of piping refer DEP 31.38.01.31-Gen. and COMPANY specification
SP-1173 -Specification for Welding of On-plot Pipe work.
The toes of adjacent circumferential welds shall be separated by a minimum distance equal to the
nominal outside diameter of the pipe. Where this requirement cannot be met, the minimum distance
between the toes of adjacent circumferential welds shall not be less than five times the nominal wall
thickness or 50mm whichever is greater.
For circumferential welds on longitudinal welded pipes, the longitudinal welds shall be so positioned that:
· The weld is at the upper segment of 120° of the pipe
· Any two adjacent longitudinal welds shall be at least 45° apart or 200mm apart, whichever is less.
When it is not possible to meet the above separation requirements between two longitudinal welded joints,
the minimum separation shall be the greater of five times the nominal wall thickness or 50 mm provided
that the weld joint is fully radio-graphed and meets the acceptance criteria of SP-1173.
For easier handling, spading points should not be installed in vertical piping; if this is
unavoidable, special precautions shall be taken to improve access and handling.
Turning a spectacle blind requires all bolts except two to be removed and a small opening
to be made between the flanges. A relatively large force is required to turn a large
spectacle blind. A spectacle blind cannot easily be turned using a crane or a hoisting
device, and therefore the need for cranes and hoisting facilities shall be avoided. Personnel
should not pull or lift loads exceeding 25 kg (56 lbm). If the required force to turn spectacle
blinds exceeds 25 kg (56 lbm), spades with spacers should be used instead.
Spectacle blinds requiring a force of more than 25 kg (56 lbm) are tabulated below.
Spacers and spades exceeding a weight of 25 kg (56 lbm) should be provided with a lifting
lug. A mobile crane or, if this is not possible, special hoisting facilities should be used for
handling such items.
Spades having a weight of more than 25 kg (56 lbm) are tabulated below.
DEP 31.38.01.11-Gen.
If spectacle blinds in horizontal pipes are insulated, the spectacle blind should point
downwards at an angle of 45° to avoid water leaking into the insulation (see
DEP 30.46.00.31-Gen.).
However, spectacle blind can be installed together with actuated valve in downward orientation provided the
clearance between the center line of pipe and top of grade/platform is above the values indicated in the below
table.
DEP 31.38.01.29-Gen.
3.7 NON-INSULATED PIPES
In other cases, non-insulated pipes should rest directly on the supporting steel, except for
the following which should be supported on pipe shoes to avoid damaging the pipe wall:
a. Pipes with sizes larger than DN 600 (NPS 24);
b. Carbon steel pipes with a wall thickness less than schedule 20;
c. Stainless steel pipes with a wall thickness less than schedule 10S;
d. the pipe requires a slope;
NOTE: This is only for small slope corrections. The height of pipe shoes measured from the
underside of the pipe shall be maximum 400 mm (16 in).
DEP 31.38.01.11-Gen
8.7.3.2 Ergonomic aspects
A removable spool and blind flanges shall be used in the following situations:
a) where the nozzle is used for entry into the equipment;
b) where the nozzle is used for hoisting purposes (e.g. top nozzles on columns);
c) where the nozzle (e.g. the head of a heat exchanger) is used to remove internals
(e.g. the tube bundle);
d) where the nozzle is used for loading/unloading of solids (e.g. catalyst).
DEP 31.38.01.29-Gen.
3.7 NON-INSULATED PIPES
Non-insulated pipes shall be supported on main pipe rack beams with a 20 mm (3/4 in)
diameter round bar welded on top to avoid corrosion developing on the pipe along the
entire width of the construction member, or shall be supported on pipe shoes to avoid
damaging the pipe wall.
DEP 31.38.01.11-Gen.
b) Nominal pipe size in pipe tracks shall not be less than DN 50 (NPS 2);
c) Nominal pipe size in pipe racks shall not be less than DN 40 (NPS 1 ½);
DEP 31.38.01.11-Gen.
In a pipe rack, piping arrangements shall be implemented in accordance with
DEP 80.00.10.11-Gen. In addition, following shall beconsidered:
a) The cryogenic pipe should be located at the sides of the pipe rack to provide space
for expansion loops and to reduce the moments in the beams caused by the weight
and thermal expansion loads from the pipe.
b) The cryogenic pipes should be grouped separately and located on different pipe rack
tiers.
c) Complicated crossings should be avoided, e.g. by not installing pipe rack spurs
opposite each other.
DEP 80.00.10.11-Gen.
4.7 EXPANSION
During initial layout it is advisable to typically oversize (30 %) the capacity of instrument,
electrical, pipe racks/tracks and trenches to avoid expanding of these facilities during the
detailed design phase when more detailed information becomes available and plot area
may not be available anymore.
DEP 31.38.01.11-Gen.
3.3.1.3 Platforms
· The length of a dead-end platform shall not exceed 7 m (23 ft).
DEP 31.38.01.11-Gen.
3.3.1.2 Horizontal clearances
Around manholes, a minimum of 760 mm (30 in) on each side of the manhole and a
minimum of 1220 mm (48 in) directly in front of the manhole shall be provided clear of
obstruction to allow for entry and exit.
DEP 80.00.10.11-Gen.
7.7.17 Manholes
For sizes of manholes see DEP 31.22.10.32-Gen.
Manholes should be facing towards an access road to allow reach by a mobile crane.
Manholes should be provided with a davit. Adequate clearance must be left for the swing of
the manhole cover on its davit. Piping shall not obstruct entrance to the manhole.
An access platform is required if the manhole centre is higher than 4 m (13 ft) above grade.
Up to 4 m (13 ft) scaffolding can be used. Platforms may also be used at lower elevations if
the frequency of using the manhole justifies this.
From: Elango R
Sent: Friday, May 27, 2016 6:22 PM
To: Saravanan G; K, Pranesh
Cc: Vijayakumar M; Sathiyakumar B; Viswanath G; N, Siddhartha; Nicholson L
Subject: RE: Reg. Column Manway Elevation from platform
Recommended man hole elevation range is discussed and finalized to maintain 600 mm to 1100 mm .
DEP 31.38.30.11-Gen.
3.2 JACKETED PIPING
For typical details see (Appendix 3).
Recommended sizes are given in Table 4.Jacketed piping is applied for situations where
the heat input of (steam) tracing is not sufficient or where even small cold spots may cause
solidification of the product. The heating medium should be saturated low pressure (LP)
steam, medium pressure (MP) steam, or heat transfer fluid.
The process lines are in the centre of larger diameter steam lines. This is applied for
services which require a high heat input. Steam pressures up to 20 barg (300 psig) may be
considered.
The wall thickness of the inner pipe shall be designed to withstand the external pressure
exerted by the steam in the outer pipe. Differences in expansion shall be checked during
detailed design (for reference see ASME B31.3, 301.7.3, PD 5500, ASME Section VIII,
Div.1, Mandatory Appendix 9).
The inner and outer pipe shall be of the same grade of material.
Butt welds of the pipe within the jacket should be avoided. Otherwise these welds shall be
inspected and tested in accordance with DEP 31.38.01.31-Gen.
For consistency, jacketed lines shall also be identified in the Contractor's specification for
piping systems.
Generally, there are three methods of jacketing:
• fully jacketed from flange to flange, having jacketed valves;
• partly jacketed, having traced valves;
• hybrid systems, partially jacketed having standard valves and bolt-on jackets.
The use of fully jacketed lines shall be restricted to a minimum for economic reasons and
because of the bulky configuration. Fully jacketed lines are used when it is critical to
maintain the process fluid within a narrow temperature range. Fully jacketed lines are used
for very waxy process fluids, liquid sulphur lines, when rapid scaling (even on
valves/flanges) can be expected, and for slurry lines in polymerisation units, etc. The inner
pipe (process line) shall have oversize (reducing type) flanges, allowing the jacket to run
from flange to flange. The valves shall also be jacketed and have flanges of a size
corresponding to the jacket size. Fully jacketed systems shall only be applied when other
systems are not able to give the required heat input because of economic reasons and the
availability of the jacketed valves.
Partially jacketed lines should be used when there is still a high heat input demand but it is
less critical to maintain the process fluid within a narrow temperature range. Typical
applications are viscous slurry suction lines, drain collecting lines in trenches, etc. The
jacket shall be swaged to the inner pipe (process line) as close as possible to the process
line flanges. The valves are traced and are the same size as the process line flanges.
Hybrid jacketing combines advantages of partly and of fully jacketed systems. Bolt on
jackets are applied in positions where conventional jacketing would be expensive or difficult
to construct. Bolt on jacketing is commercially available for the application on valves,
elbows, tees, flanges etc., is capable to give a high and constant heat input.
The inner pipe and the outer pipe shall be of the same material or have the similar
coefficients of expansion.
For jacketed piping, detailed piping stress analysis (thermal and mechanical analysis) shall
be conducted to qualify the design.
Jacketed piping shall be designed such that a uniform temperature throughout the system
is obtained. Cold spots e.g. at flanges or valves, shall be avoided because they may cause
solidification of the product.
The annular space between the process and jacket pipes shall be maintained by spacers
size 6 mm x 75 mm (½ in x 3 in), welded to the inner pipe at maximum 3 m (10 ft) intervals.
The height of the spacer shall be such that the clearance between spacer and jacket pipe
inner is 1.5 mm (1/16 in). Jacketed pipe spools shall have a maximum length of 6 m (20 ft).
Each jacketed pipe spool shall have three nozzles supplied with welding neck flanges on
the jacket. At one side there shall be a nozzle for steam / heating fluid supply; at the other
side, there shall be one nozzle for condensate discharge (not required for liquid heating
fluid) and one nozzle for jump-over.
The steam inlet nozzle and the jump-over nozzle shall be located in line (on top if a
horizontal line); the condensate discharge nozzle shall be located opposite the jump-over
nozzle (at the bottom if a horizontal line).
If using heating liquid, the inlet nozzle and the jump over nozzle shall be located on
opposite ends and on opposite sides to one another. If the line is horizontal, the inlet nozzle
shall be located on the bottom. The jump over nozzle will therefore be on the top, at the
opposite end.
The nozzles shall be located as close as possible to the flanged spool ends.
The steam inlet nozzle shall have a 3 mm (1/8 in) thick wear (impingement) plate welded to
the inner pipe.
Steam shall be fed to the steam inlet nozzle of the jacket. Each pipe spool shall have its
own steam trap. The steam flow shall continue via the jump-over nozzle to the steam inlet
nozzle of the next spool, and so on. This is referred to as a "jacket circuit".
Each circuit shall have its own fresh steam supply. The requirements for the steam supply
and condensate return are similar to those for the tracing system, see (2.4).
The maximum length of a jacket circuit depends on the pressure drop and heat loss in the
steam system.
Although typical steam jacketed systems are normally relatively short, some steam jacketed
systems perform satisfactorily with circuits longer than 1 km (0.6 mi). Such long circuits
require temperature alarm instruments.
Test pressures and conditions for jacketed spools shall be determined, and stated on the
relevant documents (e.g. isometrics).
The steam condensate and jump-over piping shall be routed so that minimum forces will be
transferred to the nozzles.
Section 2.1.4 ISOLATION VALVE OPERATION CONTROL
Atmospheric relief of process fluids or hazardous substances in the process plant is not permitted.
In case of non-hazardous services safety relief valve discharging to atmosphere vertically, the exhaust pipe
shall terminate at least 3.0 m above any service platform within a horizontal radius of 15.0 m and 30.0 m
horizontally away from any source of ignition for hydrocarbon discharge. A 13 mm weep hole shall be provided
for drainage at the low point of the tail pipe.
DEP 80.45.10.10-Gen.
Piping Design Philosophy
8.19. Instrument Piping
8.19.1. General
Globe control valves shall be installed with their diaphragm actuator stem in vertical position, with sufficient
clearance above the actuator and under the bottom flange to allow the control valve to be dismantled without
removing the valve body from the pipe. Minimum valve rating for Control valves shall be 300#.
Supports on piping with in-line instruments (control valve, safety relief valve etc) shall be located so that the assembly is
self-supporting when the instrument is removed, if required, for maintenance.
ith sufficient
antled without
Swing type check valves contain a disc that is hinged at the top. Swing type check valves
may be used in horizontal pipes, and in vertical pipes when the flow is upwards. The swing
type is normally used in sizes DN 80 (NPS 3) and above.
DEP 31.38.01.11-Gen.
5.9 UTILITY HOSE STATIONS
The utilities required shall be specified by the Principal. Where utility hose stations are
specified they should be located so that all points of use in the area can be reached by
15 m (50 ft) long hoses. Each type of utility medium SHALL [PS] be provided with a
dedicated type of hose connection to prevent contamination and inadvertent connection to Each type of utility medium requirement for elevated strucutres and platforms shall be evaluated on case by case basis
the wrong utility medium. In the interest of safety and convenience utility hose station
connection points shall point downwards.
Utility hose stations with nitrogen connections shall have a check valve at each header
connection and at each utility hose station to prevent backflow of air or hydrocarbons.
Utility pipes to the manifolds shall branch off from supply headers which cannot contain
contamination, e.g. due to leaking heat exchangers, etc.
a) Pump and compressor areas shall have permanent utility stations as follows:
o Stations shall have steam, water, air, and nitrogen (if required) outlets.
o A block valve shall be provided at the coupling of each utility line.
b) Column and vessels shall have steam, water, air, and nitrogen, as required, piped to
all platforms. Block valves shall be provided at the origin of supply headers. Steam
and water lines shall have drains at low points.
c) Exchangers and furnaces shall be provided with steam, water, air, and nitrogen
connections as required.
d) Tool air, breathing air and nitrogen outlet connections shall have dedicated hoses
and fittings in order to prevent cross connection.
The sampling point shall be positioned so that the valves are easy to operate and taking the
sample will not impair the safety of personnel or plant or cause environmental impact.
The sample shall be maintained in a single phase. The sample take-off shall be at a point
where the gas is at least 10 °C (18 °F) above dew point or the liquid is at least 10 °C
(18 °F) below the bubble point.
Samples should be taken from a vertical pipe where possible; where this is not possible:
a) For gaseous products in horizontal pipes, sample take-off connections shall be
installed at the top of the pipe.
b) For liquid products in horizontal pipes, sample take-off connections shall be
installed at the side of the pipe.
Sample take-off connections shall not be located at dead ends of piping. The length of the
sample piping system shall be kept as short as possible to minimize purging.
For liquid sampling, the sample point should be placed in the 4 o'clock position and shall be
positioned no further than the 5 o'clock position.
Sample take-off connections shall be easily accessible and should be at ground level.
However, sample pipes shall be as short as possible and not longer than 8 m (26 ft). As far
as practicable, sample connections shall be grouped together and provided each with a
sample cabinet which can be connected to one common drain facility.
Sample points shall have two valves: one at the take-off point from the process pipe and
another at the sampling point. The block valve at the take-off point shall have the same size
as a standard drain valve. The sampling valve size shall be maximum DN 15 (NPS ½) and
shall have good throttling properties. If a short sample take-off pipe cannot be fitted, a
closed loop shall be provided. The closed loop shall be a connection to the same process
stream, at different pressure. The loop shall be provided with block valves at the
connections with the process pipe.
Precautions shall be taken to avoid freezing or plugging of the sample pipe, e.g. for highpour-
point or viscous fluids.
The outlet of a single sample connection, if not connected to a sample cabinet, shall either
have a male thread and be closed with a threaded cap, or it shall have a quick-fit coupling
which seals when not connected to a sample receiver.
Sample outlets for fluids above their auto-ignition temperature, for LPG and for very toxic
products SHALL [PS] have a self-closing downstream valve. If the effluent could flash and
create sub-zero temperatures, the distance between the two valves SHALL [PS] be at least
0.6 m (24 in).
Connections for hot samples (i.e. 80 °C or above) shall be provided with a permanently
installed sample cooler. The PEFS shall indicate where a cooler is required.
For ergonomic aspects of piping systems associated sampling systems, see section 5.12 of
DEP 30.00.60.20-Gen.
DEP 30.00.60.20-Gen.
5.12 MANUAL SAMPLE POINT LOCATION
Manual sample points shall be close coupled to the process and should be located such
that they are accessible from grade. If impractical, permanent access by stair may be
acceptable.
Sample cabinets, when used, shall shield the operator from contact with the material being
sampled. A 25 mm (1 in.) hole at the top of the cabinet door with plug shall be provided to
allow the interior air to be gas tested prior to opening cabinet door. The cabinet door shall
be provided with view panel to see sample bottles/bombs being filled. The see-through
panel should be a plexi-glass type material.
The sample cabinet shall be labelled and capable of being opened without requiring any
tools or the removal of any securing fasteners or other devices.
Top of sampling cabinet shall be no higher than 1900 mm (74 in.) and the bottom no lower
than 760 mm (30 in.).
Sample cabinets shall be heated where appropriate depending on ambient environmental
conditions (cold weather).
Volatile and/or toxic substances shall be prevented from escaping into the local atmosphere
by a venturi device and vented to a safe location.
All connections for gas bombs shall be located inside the cabinet. Connections for liquid
lines may be located outside the cabinet but must be close coupled in climates subject to
freezing.
The last sampling valve at the sampling point shall be located outside the cabinet but such
that the operator can visually observe the sample being collected.
The minimum standing worker envelope shall be provided around sampling points to allow
operator to perform sampling tasks while using appropriate personal protective equipment
such as gloves and respirators.
The sample bottles and bombs shall be properly secured in place when located inside a
cabinet during sampling. Lighting should be provided inside the cabinet and a minimum
clearance of 50 mm. (2 in.) shall be provided around the circumference of the sampling
bomb when connected to allow adequate room to grip the bomb while wearing gloves.
DEP 31.38.01.11-Gen.
Drip leg
Piping in steam service shall be arranged such that steam condensate accumulation is
avoided.
All steam pipes shall have drip leg (boot) with steam trap at the low points and at the end to
remove steam condensate (e.g. during commissioning). Drip leg (boot) with steam trap
shall be installed at the following locations in both saturated and superheated service:
a) At low points or at natural drainage points, e.g. in front of risers, expansion loops,
changes of direction, (closed) valves and regulators. In saturated steam service,
steam traps shall be fitted to drain-pockets.
b) Steam traps shall be as near as possible to the steam condensate outlet of the
equipment or piping to be drained, unless a cooling leg is required
d) Near “dead” ends. “Dead” ends include line sections to control valves, battery limit
valves and other block valves where steam can be at standstill and no back slope to
a line section with steam flow is provided.
Placement of steam trap connection shall be on the side of the drip leg (boot). The end of
main steam headers shall be provided with valved blow-off connection of size minimum
DN20 (NPS ¾).
Where sagging of steam pipes is unavoidable, the position and sizing of drip legs shall
minimise the risk of transporting slugs of water from a sag over longer distance when steam
velocities have increased.
DEP 30.75.10.10-Gen.
4.4 DRAINS AND DRIP LEGS
Drip legs SHALL [PS] be provided to collect condensate formed in steam lines, to facilitate
drainage and to prevent entrainment of water slugs with fast moving steam causing water
hammer.
Drip legs SHALL [PS] be installed in both saturated and superheated service at low points,
upstream of vertical line sections, near “dead” ends including line sections to control valves,
battery limit valves and other block valves where steam can be at stagnant, in sections
downstream of desuperheaters to remove injection water in excess of evaporation capacity.
Minimum drip leg diameters are indicated in (Appendix C). The bottom of the drip leg shall
be fitted with a blow down valve for cleaning purpose.
Drip leg shall be provided in accordance with the following dimensions:
a) For steam pipe of size DN 150 (NPS 6) and above, the nominal diameter of the drip
leg shall be at least 50 % of the steam pipe size.
b) For steam pipe of size DN 100 (NPS 4) and below, the nominal diameter of the drip
leg shall be same as that of the steam pipe size.
c) Minimum distance of steam trap branch connection shall be 50 mm (2 in) from the
closure piping component weld.
d) To prevent re-entrainment from drip legs a minimum depth shall be applied. The
length of a drip leg shall be 2.0 times the nominal steam line diameter with a
minimum of 250 mm (10 in.) and a maximum of 500 mm (20 in), measured from the
bottom of the steam line to the bottom of the drip leg.
e) Steam lines shall be installed sloping towards the nearest drip leg and necessary
measures shall be incorporated to minimize line sagging. In case, where sagging of
lines is unavoidable, the position and sizing of drip legs shall be such that it
minimises the risk of transporting slugs of water from a sag over longer distance at
high steam velocities.
The drain line from the drip leg down to the steam trap shall have a first block valve that
can be operated from grade or a platform and a tee with a drain valve that can be used for
removal of condensate during line warming up, as bypass during trap maintenance and for
blow out of dirt collected in the vertical line to the steam trap. The other part of the tee
hooks up to the steam trap with an upstream second block valve and strainer.
In case of drainage from superheated steam lines, where condensate discharging from the
trap can be expected only during warm up and severe upset conditions, it is acceptable to
discharge the trap to the AC system in a safe manner. Discharges from superheated steam
lines where condensation during operation can be expected shall be hooked up to
saturated steam lines.
In case of drainage from saturated steam lines, the steam trap shall discharge into a
condensate recovery system. For start-up and trap checking, the discharge shall be
provided with a bypass valve to the AC system.
For energy and water conservation, steam traps should discharge into a closed system.
However, open discharge is acceptable for steam traps on superheated steam lines and on
remote lines with very small condensate flow. The maximum temperature of discharging
condensate shall be compatible with the receiving system and safety of people shall not be
jeopardized.
An open drain shall collect the condensate from discharges along pipe tracks with steam.
To prevent the steaming hot condensate in the drain from imposing a HSE risk, it will be
flushed with firewater using water hoses during line warm up.
A strainer (40 mesh screen size) with blow-off valve should preferably be installed
upstream of any steam trap which does not include an integral strainer. Strainers shall be
installed for any thermodynamic disc style trap or orifice trap.
A check valve shall also be installed downstream of any trap when steam condensate will
be discharged to an overhead return line or against a lift. The pressure due to the lift shall
be added to the pressure in the overhead return line when determining the total back
pressure against which the trap discharges.
Steam traps shall have a bypass arrangement if the downtime needed to replace or repair
them would cause a process problem.
Steam traps up to and including DN 40 (NPS 1 ½) should be welded and should have
removable internals to allow repair without performing hot work.
Steam traps shall be positioned so that they are easy to maintain and replace. The
connecting piping up to and including the first downstream block valve shall be designed for
the full steam pressure and temperature. Steam traps inside buildings shall have a bypass
and shall not discharge into an open drain inside the building. Block valves and bypass
valves up to and including DN 40 (NPS 1 ½) should be welded and have welded bonnets.
Open steam trap discharges shall be located away from doors, windows and air intakes. In
cold areas, icing-up of personnel access areas shall be prevented.
For equalizing of pressure around valves in systems other than steam systems, see
(3.12.7) of this DEP.
DEP 30.75.10.10-Gen.
4.5 STEAM TRAPS
The steam trap design, performance and manufacturing shall comply with the following
codes and standards:
• ANSI/ASME PTC 39.1
• ANSI/FCI 69-1
• ANSI/FCI 85-1
Steam trap selection shall be robust to avoid water hammer and frost damage. Trim
material for traps and strainers shall be stainless steel. For steam tracing traps, the body
material shall also be stainless steel.
The size of valves and piping at steam trap shall be the same as the trap.
Steam trap isolation valves shall be provided for steam trap maintenance without having to
turn off the steam supply at the root valve.
Bypasses around steam traps shall be installed to allow traps removal and repair and for
start-up. Refer to also DEP 31.38.01.11-Gen for requirements.
Steam traps shall not be insulated. For safety, the use of expanded metal screening
wrapped around a trap, instead of insulation, can provide personnel protection where
necessary.
Steam traps shall not discharge into the open within an operating area. Traps shall be
accessible and near the equipment being drained. The maximum distance between two
consecutive steam traps for steam headers shall not exceed 50 m (165 ft) for saturated
steam and 150 m (500 ft) for superheated steam.
Condensate collecting piping for grouped tracer traps shall be such as to avoid excessive
back pressure on traps and trap discharge lines and should be based on the lowest
expected steam supply pressure.
Each tracer shall have its own steam supply valve and steam trap.
For heat conservation service, each trap shall have a block valve upstream and
downstream of trap. Traps will have an integral strainer and plugged drain. In winterization
service, no blocks will be required at steam traps. Drains will be valved.
The condensate load per trap shall be calculated based on condensation during warming
up and heat losses, other condensate entering the steam line, e.g. from branches, actual
number of drip legs in section, etc.
Placement of steam trap connection shall be on the side of the drip leg. The end of the
main steam headers shall be provided with a valved blow-off connection of the minimum
DN 20 (NPS ¾) size.
Suitable steam trap types shall be selected for given applications, sized for their duty and
installed correctly for the type of the steam trap.
A strainer of 40 mesh screen size with a blow-off valve shall be installed upstream of any
steam trap which does not include an integral strainer. Strainers shall be installed for any
thermodynamic disc trap or orifice trap.
The pressure due to the lift shall be added to the pressure in the overhead return line when
determining the total back pressure against which the trap discharges.
The steam trap back pressure shall not exceed 50 % of the upstream pressure.
Steam traps up to and including DN 40 (NPS 1-½) size should be welded and should have
removable internals to allow repair without performing hot work.
Steam traps shall be positioned so that they are easy to maintain and replace. The
connecting piping up to and including the first downstream block valve shall be designed for
the full steam pressure and temperature.
Steam pipes shall not discharge steam condensate into sewer systems but instead shall
run to a safe location such as collecting steam condensate pits, accidentally-contaminated
water rundown systems, gravel pits, gullies, etc. The safe locations shall be combined as
far as practical.
DEP 31.38.30.11-Gen.
1.3.2 Specific definitions
CM Collecting Manifold for steam tracers
DM Distribution Manifold for steam tracers
lead the steam line from a DM to a tracer
steam trap an automatic device used to remove condensate from a steam system with
a minimum loss of live steam. For terminology and diagrams of steam traps,
reference is made to ISO 6704.
tail the steam line from a tracer to the CM
tracer steam heating piping which runs along the process pipe
As an alternative to the above mentioned guidance on the number and size of tracers,
steam tracing systems can be designed to supply the largest of the following heat
requirements:
a. For lines DN 25 (NPS 1) and smaller, the theoretical heat requirement shall be
multiplied with a factor 1.5 to calculate the actual heat required to maintain the
minimum specified temperature.
b. For lines over DN 25 (NPS 1), vessels, and tanks, the theoretical heat requirement
shall be multiplied with a factor 1.25 to calculate the actual heat required to maintain
the minimum specified temperature.
c. For piping thaw-out and additional heat-up requirements, the theoretical heat
requirement shall be used to calculate the heat required.
Each tracer shall have a valve just after the steam supply header and just before the
condensate header.
``
Tubing can be used for tracing of piping systems and in-line equipment such as strainers.
Tracers shall follow the contours of the piping to be heated from the highest point sloping
towards the steam trap. Pockets should be avoided, and the maximum accumulated pocket
depth is 3 m (10 ft).
Single and multiple tracers shall run along the underside of horizontal lines, or at either side
of the supporting shoes. For details see (Appendix 2).
Multiple tracers may be connected to a common steam supply line, but each shall have an
individual steam trap and block valve.
If systems are designed to discharge sub-cooled condensate (i.e. below saturated steam
temperature), extra care shall be taken to ensure a constant slope of the tracer towards the
steam trap, in order to avoid excessive water hammer effects.
Multiple tracers on vertical pipes shall be equally spaced around the circumference of the
pipe.
Tracers on straight lines shall have expansion loops at 20 m (65 ft) intervals.
At line flanges the tracer shall also have flanges to permit dismantling.
The length of tracers shall not exceed the values specified in Table 3.
A steam tracing system shall be designed to minimise potential leaks. Therefore, the
number of flanges and valves shall be restricted as far as possible. In determining the
number of valves, the question of performing repairs on steam traps on live lines should be
considered; see (8).
Steam traps and valves should be of the socket weld type and valves should have welded
bonnets.
Block valves should only be installed upstream of a distribution manifold and downstream
of a collecting manifold.
Although tracers fed from one distribution manifold should discharge into one collecting
manifold, this is often not possible. In systems where tracers from one distribution manifold
will discharge into several collecting manifolds, block valves in the leads shall be
considered to allow maintenance without total steam tracing shut-down.
For isolation during maintenance, there shall be at least one flanged connection next to the
isolating block valve between each manifold and its header.
Single tracers, with direct connections to the tracing steam and condensate headers, shall
only be applied in areas with less than 3 steam tracers and for lines which must retain
steam heating at all times.
The distance from the lead to the actual tracer shall be minimised.
For energy conservation, steam traps should discharge into a closed system. The steam
traps should be grouped together on a collecting manifold.
The collecting manifold should be vertical with a valved drain connection at the lowest
point.
The steam trap back pressure shall not exceed 50 % of the upstream pressure. Steam
traps shall be selected, sized, installed and maintained in accordance with the steam trap
vendor standards.
Steam flashing and water hammer will seriously degrade condensate lines which are too
small. Condensate lines of systems which discharge condensate at saturated steam
temperatures shall be sized to handle the flash steam content, not just the condensate. The
condensate volume after flashing is normally so small that it may be ignored.
Open discharges from steam traps (only at locations without a condensate collecting
system) shall be located so that steam clouds formed at the trap discharge do not hamper
operation/maintenance activities in the vicinity of the trap. The condensate should
discharge in a suitable drain or soakaway.
Open steam trap discharges shall be located away from doors, windows and air intakes. In
cold areas, icing-up of personnel access areas shall be avoided.
Steam pipes shall not discharge condensate into sewer systems but instead shall run to a
safe location such as collecting condensate pits, contaminated water rundown systems,
gravel pits, gullies, etc., and shall be combined as far as practical.
Condensate pipes in areas where frost can occur shall be provided with protective heating
or insulation.
KHF-00-PDFEED-MP-7180-00005-0000/04
Point 9.2 Roads
All hydrocarbon process equipments are 15m away from main tarmac roads.
Please refer the below snapshot, flow element tag number not updated by piping in model.
Tag numbers for FE & RO need to be updated by piping as per PEFS for flow elements.
Please update Flow element tag number for orifice plate and Transmitter tag number for Orifice tapping.
Example:
Tag number as per PEFS: 82FI-061, for this piping need to provide three tag numbers (one for orifice plate and another two
Instrumentation will provide another two tag number for Transmitter & and its stanchion.
Vendor shall fully comply with the Project Specifications, Project Specific Datasheets and/or international
codes and standards.
Clause 2.2 of DEP 30.46.00.31 Gen. – Sept 2011 shall be followed unless otherwise specified in the project
specific documents. The requirement for Hot Insulation and Cold Insulation shall be defined by Process
Discipline.
Insulation codes shall be as defined by Process Discipline and not necessarily as per clause 2.2.2 of DEP
30.46.00.31-Gen.
APPENDIX 2 – PERSONNEL PROTECTION GUARD DISTANCES AND INSULATION
THICKNESS
For process temperatures above 60 °C to 250 °C metal protection should be applied, without insulati
60 % rigid perforated sheets or wire mesh). For process temperatures > 250 °C, rock wool with metal
jacketing is recommended.
Table: Recommended distances between perforated metal sheet/guards and bare surface, and
insulation thickness for personnel protection.
e applied, without insulation (e.g.
0 °C, rock wool with metal
External surface of the above ground Pipes and fittings shall be protected against weathering, sunlight, UV, etc. A resin-rich po
layer shall be applied, with a thickness of 0.3 to 0.5 mm. Use of UV resistance pigments in lieu of poly veil external layer may b
the company if sufficient qualification data in accordance with ASTM G90 is submitted for approval.
External surfaces of the buried pipeline or piping system materials should be manufactured with a resin rich top coat layer