Professional Documents
Culture Documents
CPM PERT Example
CPM PERT Example
Afzal Hussain
Project
A project is a temporary
endeavour
involving
a
connected sequence of activities
and a range of resources, which
is designed to achieve a specific
and unique outcome and which
operates within time, cost and
quality constraints and which is
often used to introduce change.
2
Project Network
Activity
A task or a certain amount of work required in the project
Requires time to complete
Represented by an arrow
Dummy Activity
Indicates only precedence relationships
3
Does not require any time of effort
B
A
B
A
D
B
Dummy
C
Concurrent Activities
Lay foundation
Order material
Lay
foundation
3
Dummy
2
0
1
Order material
(b) Correct precedence
relationship
Network example
Activity network
CPM calculation
Path
A connected sequence of activities leading from
duration
Critical Activities
All of the activities that make up the critical
path
CPM Example:
CPM Network
f, 15
h, 9
g, 17
a, 6
i, 6
b, 8
d, 13
c, 5
e, 9
9
j, 12
CPM Example
ES and EF Times
f, 15
h, 9
g, 17
a, 6
0 6
i, 6
b, 8
0 8
d, 13
c, 5
0 5
10
e, 9
j, 12
CPM Example
ES and EF Times
f, 15
6 21
h, 9
g, 17
a, 6
0 6
6 23
i, 6
b, 8
0 8
c, 5
0 5
d, 13
8 21
e, 9
5 14
11
j, 12
CPM Example
ES and EF Times
f, 15
6 21
g, 17
a, 6
0 6
6 23
i, 6
23 29
h, 9
21 30
b, 8
0 8
c, 5
0 5
d, 13
8 21
e, 9
5 14
12
j, 12
21 33
Projects EF = 33
CPM Example
LS and LF Times
a, 6
0 6
b, 8
0 8
c, 5
0 5
13
f, 15
6 21
6 23
g, 17
d, 13
8 21
e, 9
5 14
i, 6
23 29
27 33
h, 9
21 30
24 33
j, 12
21 33
21 33
CPM
CPM Example
Example
LS and LF Times
a, 6
0 6
4 10
b, 8
0 8
0 8
c, 5
0 5
7 12
14
f, 15
6 21
18 24
g, 17
6 23
10 27
d, 13
8 21
8 21
e, 9
5 14
12 21
i, 6
23 29
27 33
h, 9
21 30
24 33
j, 12
21 33
21 33
CPM
CPM Example
Example
Float
15
f, 15
3 6 21
h, 9
9 24
21 30
3
a, 6
g, 17
24 33
6
23
i,
6
4
3 0 6
10 27
3 9
4 23 29
27 33
b, 8
d, 13
0
8
j, 12
0
0 8
21 33
0 8 21
0
8 21
21 33
c, 5
e, 9
0
5
7
7 12
7 5 14
12 21
CPM Example
Critical Path
f, 15
h, 9
g, 17
a, 6
i, 6
b, 8
d, 13
c, 5
e, 9
16
j, 12
Forward Pass
Backward Pass
17
CPM analysis
float = LS - ES = LF - EF
Float is the maximum amount of time that this activity
can be delay in its completion before it becomes a
critical activity, i.e., delays completion of the project
Find the critical path is that the sequence of activities
and events where there is no slack i.e.. Zero slack
Longest path through a network
Find the project duration is minimum project completion
time
18
PERT
PERT is based on the assumption that an activitys
Variance: Vt = =
2
19
tp - to
6
PERT analysis
Draw the network.
Analyze the paths through the network and find the
critical path.
The length of the critical path is the mean of the project
duration probability distribution which is assumed to be
normal
The standard deviation of the project duration probability
distribution is computed by adding the variances of the
critical activities (all of the activities that make up the
critical path) and taking the square root of that sum
Probability computations can now be made using the
normal distribution table.
20
Probability computation
Determine probability that project is completed within specified
time
Z=
x-
21
= tp
22
Time
PERT Example
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.)
Time
(Hr.)
A
-4
6
8
B
-1
4.5
5
C
A
3
3
3
D
A
4
5
6
E
A
0.5
1
1.5
F
B,C
3
4
5
G
B,C
1
1.5
5
H
E,F
5
6
7
I
E,F
2
5
8
J
D,H
2.5
2.75
4.5
K
G,I
3
5
7
23
PERT Example
PERT Network
D
C
B
F
G
24
PERT Example
Activity
Variance
A
Expected Time
6
B
C
D
E
F
G
H
I
4
3
5
1
4
2
6
5
J
K
25
3
5
4/9
4/9
0
1/9
1/36
1/9
4/9
1/9
1
1/9
4/9
PERT Example
D,5
H,
6
A,
6
J,3
1
E,
I,5
4
B,
G,2
26
K,
5
F,4
C,3
PERT Example
27
Activity
ES
EF
LS
LF
Slack
11
15
20
12
13
13
13
11
16
18
13
19
14
20
13
18
13
18
19
22
20
23
18
23
18
23
PERT Example
Vpath = VA + VC + VF + VI + VK
path
28
Thank You
29